Analysis of Actual Duration by Effecting Elements to Duration Estimate - Focused on Standard Duration of the Office Building Construction - (공기산정 영향요인별 실적공기 비교분석 - 사무소 건축공사 공기산정기준을 중심으로 -)

  • Hwang Hyo-Sang;Kim Kyung-Rai;Suh Sang-Wook;Kim Chang-Duk;Shin Dong-Woo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.3 no.3 s.11
    • /
    • pp.84-93
    • /
    • 2002
  • It is important to reduce construction duration in private sales and lease business for management of cash now in the owner's aspect. However, because the concept of standard duration hasn't been established in the domestic construction industry, it is difficult to present the standard of duration estimate. To solve this problem, this paper (1) grasped the effecting elements considered in the duration estimate through referring the existing literature related to the schedule management, (2) accomplished a comprehensive research on actual duration based on office buildings through the questionnaire survey and the expert interview, (3) presented the collected research data analyzed by effecting elements as standard duration, (4) compared standard duration with actual duration of countries advanced in construction projects as well as analyzed them, and then (5) raised the necessity of duration reduction in the domestic construction industry.

A Study on the Estimate Criteria and Influence Factors of Construction Duration of Domestic Firms -Focused on the Apartment Building Firms- (국내 건설 업체 공기산정 기준 및 영향요인 연구 -공동주택 중심으로-)

  • Kim Sun-Yeop;Kim Sun-Kuk;Han Choong-Hee
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2004.11a
    • /
    • pp.447-450
    • /
    • 2004
  • The domestic construction industry have focus on duration than construction cost. But recently it have interesting to The domestic construction industry, social requirement is changing. At the moderate speed duration has other angle of reducing cost and management of efficiency. specially Apartment building construction process is similar to other construction industry so it Is obtain a strong Point. This study on, A Target of construction industry is short duration than other it, general construction duration in summary schedule of level is studied, is based and construction duration for the point it is indicated reduction duration

  • PDF

The Estimation of Construction Duration for High School Buildings Based on the Actual Data (실적자료에 의한 고등학교 시설 공기산정)

  • Kwon Dong-Chan;Lee Chan-Sik
    • Korean Journal of Construction Engineering and Management
    • /
    • v.5 no.6 s.22
    • /
    • pp.138-145
    • /
    • 2004
  • The construction duration for any building or facilities such as high school building influence the quality of the building as well as the total cost for them. Since there are no guidelines to estimate construction duration correctly, an employer(or owner) estimate it by their own experience or intuition. Therefore some conflicts related to construction duration happen between contract parties during construction. The purpose of this study is to suggest a predictive model which helps decision makers calculate exact net working days for high school building construction at the early stage of the construction project. To measure net working days for high school construction, 15 data were collected from actual spot in Incheon region. Multiple linear regression analysis was conducted to obtain the model which calculate construction duration for the substructure, the superstructure and the finishing works. total construction duration could be obtained by adding net working days to non working days which would be based on the meteorological statistics for Incheon region since 1974 to 2003.

Estimation on Affecting Factors and Contribution Rate for Air Permeability of Sawdust as Bulking Agent on Composting (퇴비화 첨가재인 톱밥의 공기투과성에 미치는 영향요인 및 기여도 평가에 관한 연구)

  • Kim, Byung Tae
    • Journal of the Korea Organic Resources Recycling Association
    • /
    • v.23 no.4
    • /
    • pp.52-62
    • /
    • 2015
  • This study estimated the contribution rates of inlet air flow, moisture content, air-filled porosity and particle size on the total pressure drop for the sawdust used as the bulking agent in the composting. The statistical model for pressure drop including the affecting factors was proposed.($R^2=0.998{\sim}0.950$) While the laminar air flow(v) and particle size(SIZE*v) had the positive relations to the total pressure drop, the turbulent air flow($v^2$), moisture content(MC*v) and air-filled porosity(AFP*v) had the negative relations. Total pressure drop sharply increased with increasing of the inlet air flow. And the most significant factors affecting to total pressure drop were the particle size(SIZE*v) as positive factor and air-filled porosity(AFP*v) as negative factor. The contribution rate to total pressure drop by the particle size(SIZE*v) was continuously increased with increasing of the inlet air flow, but the contribution rate by air-filled porosity(AFP*v) was decreased. And total pressure drop was little changed even though the increasing of moisture content above the range of dry moisture content 0.25. The contribution rates of affecting factors had the different tendencies with increasing of the moisture content, especially in the negative factors as air-filled porosity(AFP*v) and moisture content(MC*v). For effective composting process, it is preferable to select the sawdust with higher air-filled porosity as bulking agent to enhance the air permeability.

Effect of Office Building Remodeling Project Characteristics on the Occurrence of Schedule Delay Risk Factors (오피스 리모델링 프로젝트 특성에 따른 공기지연 리스크 발생 영향도)

  • Cho, Kyuman;Kim, Taehoon
    • Korean Journal of Construction Engineering and Management
    • /
    • v.19 no.5
    • /
    • pp.22-31
    • /
    • 2018
  • Due to the inherent risk factors of the remodeling projects, the remodeling project is failing frequently, and schedule delay are occurring in most remodeling projects. The risk factors that cause the delays in these remodeling projects are not common to all remodeling projects, and the likelihood of risk factors will be affected by the various characteristics of the project. In this context, based on the results of a reliable survey conducted on 29 construction managers who have performed remodeling projects, this research analyzes (1) "importance of each characteristic", which means how frequently the characteristics of the remodeling project affect the occurrence of risk factors, (2) "the likelihood of delay risk factors for remodeling projects", which assesses which risk factors are most likely to occur, and 3) "the level of effect of project characteristics that affects the occurrence of each risk factor." Through this study, the relationship between various characteristics of the office building remodeling projects and the delay risk factors was analyzed in various aspects, in further, it is expected that the owner planning the remodeling will be able to grasp the delay risk that is likely to occur according to the characteristics of the project in advance.

Preliminary Scheduling Based on Historical and Experience Data for Airport Project (초기 기획단계의 실적 및 경험자료 기반 공항사업 기준공기 산정체계)

  • Kang, Seunghee;Jung, Youngsoo;Kim, Sungrae;Lee, Ikhaeng;Lee, Changweon;Jeong, Jinhak
    • Korean Journal of Construction Engineering and Management
    • /
    • v.18 no.6
    • /
    • pp.26-37
    • /
    • 2017
  • Preliminary scheduling at the initial stage of planning phase is usually performed with limited information and details. Therefore, the reliability and accuracy of preliminary scheduling is affected by personal experiences and skills of the schedule planners, and it requires enormous managerial effort (or workload). Reusing of historical data of the similar projects is important for efficient preliminary scheduling. However, understanding the structure of historical data and applying them to a new project requires a great deal of experience and knowledge. In this context, this paper propose a framework and methodology for automated preliminary schedule generation based on historical database. The proposed methodology and framework enables to automatically generate CPM schedules for airport projects in the early planning stage in order to enhance the reliability and to reduce the workload by using structured knowledge and experience.

Calculation of Non-Working Days due to Weather Factors during Structural Steel Works (기후요소에 의한 철골공사 작업불가능일 산정에 관한 연구)

  • Lee, Duk-Hyung;You, Jung-Sik;You, Jae-Kil;Jung, Jae-Hun;Jung, Hee-Kyung;Yu, Jung-Ho;Kim, Chang-Duk
    • Korean Journal of Construction Engineering and Management
    • /
    • v.7 no.4 s.32
    • /
    • pp.137-145
    • /
    • 2006
  • Calculating non-working days is very important element for the accurate estimation of construction time. And non-working days are largely affected by weather factors such as rainfall, wind velocity, snowfall and temperature. In the case of concrete works, there are lots of referable information for the calculation of non-working days due to the weather factors. However, for the structural steel works, there are very limited information only. Through literature survey and interviews with a few engineers, this paper established the weather factors that affect steel structural works and the impact of those factors. Based on the factors and the expected impact of the factors together with the weather data during the last 15 years in Seoul region gathered from Korea Meteorological Administration, this paper suggests the monthly non-working day of structural steel work due to weather factors. This information can be used for the early estimation of construction time.

Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension (공사기간 연장에 따른 추가간접비 사전합의 제도 도입 방안 연구)

  • Jeong, Ki-Chang;Lee, Jae-Seob;Park, Yang-Ho
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.6
    • /
    • pp.33-44
    • /
    • 2012
  • This study is as to payment improvement method of additional incidental cost to be occurred upon extension of public construction time. According to the result of analysis about the cause of non-payment of additional incidental cost of construction time extension through site examples, it was found that difficulties exist in disputes & proofing over the scope of actual cost recognition, and in this regard the result of experts opinion indicated that a construction extension pre-agreement system can be executed which agrees the scope of recognition of additional incidental cost of construction time extension once the statistical standard is clear and accurate. Accordingly, in this study, by totalling multiple sites data, calculations were implemented in terms of type of construction projects, amount of constructions, period of constructions. According to the result of calculation, the element of type of construction project and construction period appears to have none direct effect to the occurrence of additional cost of construction time extension, but direct relationship was indicated related to the contract amount element. In view of above, in this study a standard additional incidental cost of construction time extension was proposed, and presented a system improvement plan to implement the construction extension pre-agreement system.

Direction of Selecting the Alternative considered Correlation between Building Systems in Remodeling Design Process (리모델링 설계단계에서 건축시스템 상관관계를 고려한 대안선정 방안)

  • Lee Dong-Jun;Park Chan-Gil;Park Sang-Jun;Chun Jae-Youl
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.415-418
    • /
    • 2002
  • As Remodeling is proceed in the limited condition that is utilization of existing resource, the selection of remodeling objects and scope are affected by the correlation of building systems. Unexpected problems have occurred in construction phase by lack of the consideration about correlation of building systems; increasing of cost, delaying of schedule etc. Therefore, this research suggests the Building System Correlation Diagram Model and the direction of cost estimation .for selecting alternative reasonably in remodeling design process.

  • PDF

A Study on the Priority Analysis of Work Delay Factors in Steal-frame Work using FMEA (FMEA를 활용한 철골공사 작업지연요인의 중요도에 관한 연구)

  • Lee, Hyun-Chul;Lee, Jae-Hong;Go, Seong-Seok
    • Korean Journal of Construction Engineering and Management
    • /
    • v.10 no.1
    • /
    • pp.91-101
    • /
    • 2009
  • The factors of uncertainty such as work delay could cause many problems, for example, increase of construction cost and terms of work, and the deterioration of quality. Because of these, the uncertainty risk is regarded as an important management factor to obtain the success of construction project. So, the systematic management plan about the uncertainty factors is needed because it plays an important role in the completion of entire project. And also analysis of some factors which can cause the work delay can be one way of improving construction project's certainty and making it competitive. In this reason, we have to make an effort to set a priority based on analysis of quantitatively numerical value about work delay factors to manage them effectively. Thus, this study aims to suggest the basic data for the effective management and prevention of work delay in steel-frame work which is progressive actively now, along with increasing of demand of high-rise buildings by analyzing each reasons of work delay factors and also by suggesting important management factors that are coded according to each construction work using FMEA method which could give a data about the importance of work delay factors through quantitatively numerical value.