Abstract
This study is as to payment improvement method of additional incidental cost to be occurred upon extension of public construction time. According to the result of analysis about the cause of non-payment of additional incidental cost of construction time extension through site examples, it was found that difficulties exist in disputes & proofing over the scope of actual cost recognition, and in this regard the result of experts opinion indicated that a construction extension pre-agreement system can be executed which agrees the scope of recognition of additional incidental cost of construction time extension once the statistical standard is clear and accurate. Accordingly, in this study, by totalling multiple sites data, calculations were implemented in terms of type of construction projects, amount of constructions, period of constructions. According to the result of calculation, the element of type of construction project and construction period appears to have none direct effect to the occurrence of additional cost of construction time extension, but direct relationship was indicated related to the contract amount element. In view of above, in this study a standard additional incidental cost of construction time extension was proposed, and presented a system improvement plan to implement the construction extension pre-agreement system.
본 연구는 공공공사 공기연장 시 발생하는 추가간접비의 지급개선방안에 관한 연구이다. 현장사례를 통해 공기연장 추가 간접비 미지급 원인을 분석한 결과 실비의 인정범위에 대한 다툼 및 증빙의 어려움이 있는 것으로 조사되었으며, 전문가 의견조사 실시결과 통계적 기준이 명확하다면 공기연장 추가간접비의 인정범위를 합의하는 '공기연장 사전합의 제도'를 실시할 수 있을 것으로 조사되었다. 따라서 본 연구는 다수의 현장 실비자료를 집계하여 공사프로젝트의 공종별, 공사금액별, 공사기간별 측면에서 산정하였다. 산정한 결과 공종 및 공사기간별 요인은 공사기간연장 추가간접비 발생금액에 직접적 영향을 미치는 것으로 볼 수 없으나 도급계약금액요인에 따라서는 직접적 연관성이 있는 것으로 나타났다. 이에 계약금액별 공사기간연장에 따른 추가비용인 '공기연장 표준추가간접비'를 제시하였으며, 공기연장비용 사전합의 제도를 시행하기 위한 제도적 개선방안을 제시하였다.