Preliminary Scheduling Based on Historical and Experience Data for Airport Project  

Kang, Seunghee (College of Architecture, Myongji University)
Jung, Youngsoo (College of Architecture, Myongji University)
Kim, Sungrae (College of Architecture, Myongji University)
Lee, Ikhaeng (College of Architecture, Myongji University)
Lee, Changweon (Incheon International Airport Corporation)
Jeong, Jinhak (Incheon International Airport Corporation)
Publication Information
Korean Journal of Construction Engineering and Management / v.18, no.6, 2017 , pp. 26-37 More about this Journal
Abstract
Preliminary scheduling at the initial stage of planning phase is usually performed with limited information and details. Therefore, the reliability and accuracy of preliminary scheduling is affected by personal experiences and skills of the schedule planners, and it requires enormous managerial effort (or workload). Reusing of historical data of the similar projects is important for efficient preliminary scheduling. However, understanding the structure of historical data and applying them to a new project requires a great deal of experience and knowledge. In this context, this paper propose a framework and methodology for automated preliminary schedule generation based on historical database. The proposed methodology and framework enables to automatically generate CPM schedules for airport projects in the early planning stage in order to enhance the reliability and to reduce the workload by using structured knowledge and experience.
Keywords
Preliminary Scheduling; Airport Project; Standard Duration; Influencing Factors; Planning Stage; Historical Datad;
Citations & Related Records
Times Cited By KSCI : 3  (Citation Analysis)
연도 인용수 순위
1 Czarnigowska, A., and Sobotka, A. (2014). "Estimating construction duration for public roads during the preplanning phase" Journal of Engineering Projec, and Production Management, 4(1), p. 26.
2 Hammad, A. A. A., Ali, S. M. A., Sweis, G. J., and Bashir, A. (2008). "Prediction model for construction cost and duration in Jordan" Jordan Journal of Civil Engineering, 2(3).
3 Hoffman, G. J., Thal Jr, A. E., Webb, T. S., and Weir, J. D. (2007). "Estimating performance time for construction projects" Journal of Management in Engineering, ASCE, 23(4), pp. 193-199.   DOI
4 Jin, R., Han, S., Hyun, C., and Cha, Y. (2015). "Application of Case-Based Reasoning for Estimating Preliminary Duration of Building Projects" Journal of Construction Engineering and Management, ASCE, 142(2), 04015082.   DOI
5 Jung, I. S., Hwang, J. H., Park, J. S., and Lee, C. S. (2000). "Predictive Model for the Estimation of Net Working Days in the Military Facility Construction" Journal of the Architectural Institute of Korea, 16(9), pp. 67-74.
6 Jung, Y. S. (2008). "Automated Front-End Planning for Cost and Schedule: Variables for Theory and Implementation" Proceedings of the 2008 Architectural Engineering National Conference, ASCE, Denver, USA.
7 Jung, Y. S., and Kang, S. H. (2007). "Knowledge-Based Standard Progress Measurement for Integrated Cost and Schedule Performance Control" Journal of Construction Engineering and Management, ASCE, 133(1), pp. 10-21.   DOI
8 Jung, Y. S., Lee, Y. S., and Woo, S. K. (2009). "Automated CPM Schedule Generation for Early Project Planning: Methodology and Case Study" Proceedings of Construction Research Congress 2009, ASCE, Seattle, USE, pp. 816-825.
9 Kim, K. J., Cho, J. Y., Lee, D. Y., and Lee, M. J. (2016 ). "Development of an automated As-planned schedule system for efficient scheduling" KSCE Journal of Civil Engineering, 20(4), pp. 1131-1137.   DOI
10 Kim, K. J., Yun, W. G., and Kim, I. K. (2016). "Estimating approximate construction duration of CFRD in the planning stage" KSCE Journal of Civil Engineering, pp. 1-10.
11 Kim, S. J., and Lee, J. S. (2004). "An Optimal Scheduling Method Using Probability on the Estimation of Construction Duration" Korean Journal of Construction Engineering and Management, KICEM, 5(6), pp. 72-79.
12 Koo, H. S., and Choi, B. C. (1999). "A Study on the Estimation of Construction Period Considering Weather Factor in Building Construction" Journal of the Architectural Institute of Korea, 15(11), pp. 87-96.
13 Kwon, D. C., and Lee, C. S. (2004). "The Estimation of Construction Duration for High School Buildings Based on the Actual Data" Korean Journal of Construction Engineering and Management, KICEM, 5(6), pp. 138-145.
14 Stoy, C., Pollalis, S., and Schalcher, H. (2007). "Early estimation of building construction speed in Germany" International Journal of Project Management, 25(3), pp. 283-289.   DOI
15 Lee, B. S., Kim, K. N., and Lee, M. J. (2015). "A Study on Normal Project Duration for Water Resource Project" Korean Journal of Construction Engineering and Management, KICEM, 16(1), pp. 35-43.   DOI
16 Lee, S. B. (2001). "A Study on the Optimal Duration Estimating Method by Line of Balance" Journal of the Architectural Institute of Korea, 17(9), pp. 233-240.
17 Lin, M., Tserng, H. P., Ho, S., and Young, D. (2011). "Developing a construction-duration model based on a historical dataset for building project" Journal of Civil Engineering and Management, 17(4), pp. 529-539.   DOI
18 Martin, J., Burrows, T. K., and Pegg, I. (2006). "Predicting construction duration of building projects" XXIII Congreso FIG.
19 Shin, J. H., and Lee, C. S. (1996). "Estimating method for Construction Duration in the Frame Work of Reinforced Concrete Wall-Slab Type Apartments" Journal of the Architectural Institute of Korea, 12(7), pp. 349-364.