Effect of Office Building Remodeling Project Characteristics on the Occurrence of Schedule Delay Risk Factors

오피스 리모델링 프로젝트 특성에 따른 공기지연 리스크 발생 영향도

  • Cho, Kyuman (School of Architecture, Chosun University) ;
  • Kim, Taehoon (School of Architecture, Chosun University)
  • Received : 2018.04.26
  • Accepted : 2018.07.18
  • Published : 2018.09.30

Abstract

Due to the inherent risk factors of the remodeling projects, the remodeling project is failing frequently, and schedule delay are occurring in most remodeling projects. The risk factors that cause the delays in these remodeling projects are not common to all remodeling projects, and the likelihood of risk factors will be affected by the various characteristics of the project. In this context, based on the results of a reliable survey conducted on 29 construction managers who have performed remodeling projects, this research analyzes (1) "importance of each characteristic", which means how frequently the characteristics of the remodeling project affect the occurrence of risk factors, (2) "the likelihood of delay risk factors for remodeling projects", which assesses which risk factors are most likely to occur, and 3) "the level of effect of project characteristics that affects the occurrence of each risk factor." Through this study, the relationship between various characteristics of the office building remodeling projects and the delay risk factors was analyzed in various aspects, in further, it is expected that the owner planning the remodeling will be able to grasp the delay risk that is likely to occur according to the characteristics of the project in advance.

리모델링 사업의 고유 리스크 요인들로 인해, 리모델링 사업의 실패가 빈번하게 발생하고 있는 실정이며 특히 공기지연이 거의 대부분의 리모델링 프로젝트에서 발생하고 있는 실정이다. 이러한 리모델링 프로젝트의 공기지연을 야기하는 리스크요인들이 모든 리모델링 프로젝트에 공통적으로 발생하는 것은 아니며, 해당 프로젝트의 다양한 특성에 따라 리스크 요인들의 발생가능성이 영향을 받게 된다. 이러한 맥락에서, 리모델링 프로젝트를 수행한 경험이 있는 29명의 현장관리자들을 대상으로 수행된 신뢰성 있는 설문조사 결과를 바탕으로, (1) 리모델링 프로젝트의 속성들이 리스크 요인의 발생에 얼마나 빈번하게 영향을 미치는지를 평가한 "프로젝트의 속성별 중요도"를 산정하였고, (2) 어떤 리스크 요인의 발생가능성이 가장 큰지를 평가한 "리모델링 사업의 공기지연 리스크 요인별 중요도" 그리고 (3) 이상의 두 가지를 혼합한, "각각의 리스크 요인의 발생에 영향을 미치는 프로젝트 속성별 영향도"를 분석하였다. 본 연구를 통하여, 리모델링을 고려하는 건축물의 다양한 특성들과 공기지연 리스크 발생가능성 사이의 관계를 다각적인 측면으로 분석하였고, 이를 통해, 리모델링을 계획하고 있는 발주자가 해당 프로젝트의 오피스의 특성에 따라 발생가능성이 높은 공기지연 리스크를 사전에 파악할 수 있을 것으로 기대된다.

Keywords

References

  1. Yoon, Y. (2011). "Improvement plan for the remodeling of old apartment house." CERIK.
  2. Cho, K., and Yoon, Y. (2016). "Decision support model for determining cost-effective renovation time." ASCE Journal of Mgmt. in Eng., 32(3), pp. 04015051-1 - 9 https://doi.org/10.1061/(ASCE)ME.1943-5479.0000418
  3. Shin, Y., Cho, K., and Kim, J. (2015). "Decision support process model for energy efficient remodeling projects focused on building envelope and renewable energy systems." Korean Journal of Construction Engineering and Management, KICEM, 16(3), pp. 91-100. https://doi.org/10.6106/KJCEM.2015.16.3.091
  4. Kim, J., Cho, K., Kim, T., and Yoon, Y. (2018). "Predicting the monetary value of office property post renovation work." ASCE Journal of Urban Planning and Development, 144(2), pp. 04018007-1 - 9 https://doi.org/10.1061/(ASCE)UP.1943-5444.0000434
  5. Kim, J., Cho, K., and Kim, T. (2016). "Factors determining the price of remodeled multi-family housing." Korean Journal of Construction Engineering and Management, KICEM, 17(3), pp. 13-22. https://doi.org/10.6106/KJCEM.2016.17.3.013
  6. Kim, K. (2010). "Decision-making criteria for the selection of construction methods to the office building remodeling." MS thesis, Hanyang Univ, Seoul.
  7. Part, R. (2010). "A study on the determinant factors for remodeling apartments' price." MS thesis, Jeounju Univ, Jeounju.
  8. Shen, L. Y. (1997). "Project risk management in Hong Kong." Int. J. Project Manage., 15(2), pp. 101-105. https://doi.org/10.1016/S0263-7863(96)00045-2
  9. Sun, Y., Fang, D., Wang, S., Dai, M., and Lv, X. (2008). "Safety risk identification and assessment for Beijing Olympic venues construction." J. Manage. Eng., 24(1), pp. 40-47. https://doi.org/10.1061/(ASCE)0742-597X(2008)24:1(40)
  10. Yuan, J. F., Deng, X. P., and Li, Q. M. (2008). "Critical risks identification of public private partnership in China and the analysis on questionnaire survey." 2008 4th Int. Conf. on Wireless Communications, Networking and Mobile Computing, IEEE, Piscataway, NJ, pp. 1-6.
  11. Ke, Y., Wang, S., and Chan, A. (2010). "Risk allocation in public-private partnership infrastructure projects: Comparative study." J. Infrastructure Systems, 16(4), pp. 343-351. https://doi.org/10.1061/(ASCE)IS.1943-555X.0000030
  12. Choudhry, R., Aslam, M., Hinze, J., and Arain, F. (2014). "Cost and schedule risk analysis of bridge construction in Pakistan: Establishing risk guidelines." J. Constr. Eng. Manage., 140(7), pp. 04014020-1 - 9 https://doi.org/10.1061/(ASCE)CO.1943-7862.0000857
  13. Sarvari, H., Valipour, A., Yahaya, N., and Noor, N. (2014). "Risk identification and assessment in Malaysian public-private partnership projects." Vulnerability, uncertainty, and risk: Quantification, mitigation, and management, M. Beer, S.-K. Au, and J. W. Hall, eds., ASCE, Reston, VA, pp. 436-445.
  14. Yoon, Y., Tamer, Z., and Hastak, M. (2015). "Protocol to enhance profitability by managing risks in construction projects." J. Manage. Eng., 31(5), pp. 04014090-1 - 10 https://doi.org/10.1061/(ASCE)ME.1943-5479.0000339
  15. El-Sayegh, S., and Mansour, M. (2015). "Risk assessment and allocation in highway construction projects in the UAE." J. Manage. Eng., 31(6), pp. 04015004-1 - 11 https://doi.org/10.1061/(ASCE)ME.1943-5479.0000365
  16. Lee, S., and Son, B. (2013). "An analysis on characteristics and risk factors of the remodeling project." Korean Journal of Facility Management, 8(2), pp. 5-11.
  17. Lee, D., and Cha, H. (2016). "A probabilistic risk-based cost estimation model for initial-stage decision making on apartment remodeling projects." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 70-79. https://doi.org/10.6106/KJCEM.2016.17.2.070
  18. Hong, S., and Ahn, Y. (2004). "A study on countermeasures for the strategic risk management of remodeling in construction projects." Journal of the Architectural institute of Korea, 193, pp. 153-160.
  19. Hair, J., Black, W., Babin, B., Anderson, R., and Tatham, R. (2006). Multivariate data analysis (6th ed.). Upper Saddle River, New Jersey 07458: Pearson Education, Inc.