Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension  

Jeong, Ki-Chang (동국대학교 건축공학과)
Lee, Jae-Seob (동국대학교 건축공학과)
Park, Yang-Ho (사단법인 건설원가연구원)
Publication Information
Korean Journal of Construction Engineering and Management / v.13, no.6, 2012 , pp. 33-44 More about this Journal
Abstract
This study is as to payment improvement method of additional incidental cost to be occurred upon extension of public construction time. According to the result of analysis about the cause of non-payment of additional incidental cost of construction time extension through site examples, it was found that difficulties exist in disputes & proofing over the scope of actual cost recognition, and in this regard the result of experts opinion indicated that a construction extension pre-agreement system can be executed which agrees the scope of recognition of additional incidental cost of construction time extension once the statistical standard is clear and accurate. Accordingly, in this study, by totalling multiple sites data, calculations were implemented in terms of type of construction projects, amount of constructions, period of constructions. According to the result of calculation, the element of type of construction project and construction period appears to have none direct effect to the occurrence of additional cost of construction time extension, but direct relationship was indicated related to the contract amount element. In view of above, in this study a standard additional incidental cost of construction time extension was proposed, and presented a system improvement plan to implement the construction extension pre-agreement system.
Keywords
Additional incidental costs; Construction time extension; Delay of the construction time; Delay claim; Liquidated damages;
Citations & Related Records
연도 인용수 순위
  • Reference
1 박성용, 양진국, 김병옥, 이상범 (2009). "건설공사 사전분쟁요인 도출 및 분석."한국건설관리학회 논문집, 제10권 제6호, 한국건설관리학회, pp. 48.
2 사단법인 한국원가관리협회 (2010). 공사기간 연장에 따른 간접비 지급방안 개선, 1판, 기획재정부, 과천, pp. 54-63.
3 이재섭 (1999)." 공기지연 보상청구의 기준 및조건."건설산업동향, 제55호, 한국건설산업연구원, pp. 9-13.
4 이재섭 (2009). "공기연장손실비용눈덩이."건설저널, 제94권, 한국건설산업연구원, pp. 14-15.
5 조영준, 이상범 (2005). "공공건설사업에서 계약기간 연장처리 방법 개선에 관한 연구."한국건설관리학회 논문집, 제6권 제3호, 한국건설관리학회, pp. 81-85.
6 FIDIC (2010). Conditions of Contract for Construction (MDB Edition), FIDIC, Switzerland, pp. 119-120.
7 Yates, J. K. and Epstein, Alan (2006). Avoiding and Minimizing Construction Delay Claim Disputes in Relational Contracting, JOURNAL OF PROFESSIONAL ISSUES IN ENGINEERING EDUCATION AND PRACTICE, USA, pp. 173-174.