Effect of Office Building Remodeling Project Characteristics on the Occurrence of Schedule Delay Risk Factors  

Cho, Kyuman (School of Architecture, Chosun University)
Kim, Taehoon (School of Architecture, Chosun University)
Publication Information
Korean Journal of Construction Engineering and Management / v.19, no.5, 2018 , pp. 22-31 More about this Journal
Abstract
Due to the inherent risk factors of the remodeling projects, the remodeling project is failing frequently, and schedule delay are occurring in most remodeling projects. The risk factors that cause the delays in these remodeling projects are not common to all remodeling projects, and the likelihood of risk factors will be affected by the various characteristics of the project. In this context, based on the results of a reliable survey conducted on 29 construction managers who have performed remodeling projects, this research analyzes (1) "importance of each characteristic", which means how frequently the characteristics of the remodeling project affect the occurrence of risk factors, (2) "the likelihood of delay risk factors for remodeling projects", which assesses which risk factors are most likely to occur, and 3) "the level of effect of project characteristics that affects the occurrence of each risk factor." Through this study, the relationship between various characteristics of the office building remodeling projects and the delay risk factors was analyzed in various aspects, in further, it is expected that the owner planning the remodeling will be able to grasp the delay risk that is likely to occur according to the characteristics of the project in advance.
Keywords
Office Building Remodeling Projects; Schedule Delay Risk Factors; Project Characteristics; Data Analysis;
Citations & Related Records
Times Cited By KSCI : 2  (Citation Analysis)
연도 인용수 순위
1 Yoon, Y. (2011). "Improvement plan for the remodeling of old apartment house." CERIK.
2 Cho, K., and Yoon, Y. (2016). "Decision support model for determining cost-effective renovation time." ASCE Journal of Mgmt. in Eng., 32(3), pp. 04015051-1 - 9   DOI
3 Shin, Y., Cho, K., and Kim, J. (2015). "Decision support process model for energy efficient remodeling projects focused on building envelope and renewable energy systems." Korean Journal of Construction Engineering and Management, KICEM, 16(3), pp. 91-100.   DOI
4 Kim, J., Cho, K., Kim, T., and Yoon, Y. (2018). "Predicting the monetary value of office property post renovation work." ASCE Journal of Urban Planning and Development, 144(2), pp. 04018007-1 - 9   DOI
5 Kim, J., Cho, K., and Kim, T. (2016). "Factors determining the price of remodeled multi-family housing." Korean Journal of Construction Engineering and Management, KICEM, 17(3), pp. 13-22.   DOI
6 Kim, K. (2010). "Decision-making criteria for the selection of construction methods to the office building remodeling." MS thesis, Hanyang Univ, Seoul.
7 Part, R. (2010). "A study on the determinant factors for remodeling apartments' price." MS thesis, Jeounju Univ, Jeounju.
8 Shen, L. Y. (1997). "Project risk management in Hong Kong." Int. J. Project Manage., 15(2), pp. 101-105.   DOI
9 Sun, Y., Fang, D., Wang, S., Dai, M., and Lv, X. (2008). "Safety risk identification and assessment for Beijing Olympic venues construction." J. Manage. Eng., 24(1), pp. 40-47.   DOI
10 Yuan, J. F., Deng, X. P., and Li, Q. M. (2008). "Critical risks identification of public private partnership in China and the analysis on questionnaire survey." 2008 4th Int. Conf. on Wireless Communications, Networking and Mobile Computing, IEEE, Piscataway, NJ, pp. 1-6.
11 Ke, Y., Wang, S., and Chan, A. (2010). "Risk allocation in public-private partnership infrastructure projects: Comparative study." J. Infrastructure Systems, 16(4), pp. 343-351.   DOI
12 El-Sayegh, S., and Mansour, M. (2015). "Risk assessment and allocation in highway construction projects in the UAE." J. Manage. Eng., 31(6), pp. 04015004-1 - 11   DOI
13 Choudhry, R., Aslam, M., Hinze, J., and Arain, F. (2014). "Cost and schedule risk analysis of bridge construction in Pakistan: Establishing risk guidelines." J. Constr. Eng. Manage., 140(7), pp. 04014020-1 - 9   DOI
14 Sarvari, H., Valipour, A., Yahaya, N., and Noor, N. (2014). "Risk identification and assessment in Malaysian public-private partnership projects." Vulnerability, uncertainty, and risk: Quantification, mitigation, and management, M. Beer, S.-K. Au, and J. W. Hall, eds., ASCE, Reston, VA, pp. 436-445.
15 Yoon, Y., Tamer, Z., and Hastak, M. (2015). "Protocol to enhance profitability by managing risks in construction projects." J. Manage. Eng., 31(5), pp. 04014090-1 - 10   DOI
16 Lee, S., and Son, B. (2013). "An analysis on characteristics and risk factors of the remodeling project." Korean Journal of Facility Management, 8(2), pp. 5-11.
17 Lee, D., and Cha, H. (2016). "A probabilistic risk-based cost estimation model for initial-stage decision making on apartment remodeling projects." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 70-79.   DOI
18 Hong, S., and Ahn, Y. (2004). "A study on countermeasures for the strategic risk management of remodeling in construction projects." Journal of the Architectural institute of Korea, 193, pp. 153-160.
19 Hair, J., Black, W., Babin, B., Anderson, R., and Tatham, R. (2006). Multivariate data analysis (6th ed.). Upper Saddle River, New Jersey 07458: Pearson Education, Inc.