A Study on the Problem Analysis and Improvement Measures of Subcontract Management to Middle or Small Construction Contractors (중소건설사의 협력업체 관리실태에 대한 문제점 및 개선방안에 관한 연구)

  • Lee, Kang-Yong;Kang, Hyun-Wook;Kim, Yong-Su
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2007.11a
    • /
    • pp.580-584
    • /
    • 2007
  • The purpose of this study is to analyze managemental problems that were made by cooperator and to offer improvable plan for small and medium construction company. The adapted research method a case study three small and medium contractors and investigate the managemental operation of cooperator and rating standard. Also analyze problem of the rating standard and managemental state of the cooperator and offer improvable plan. The results of this research are as follows. 1)Applying open bid system for supplying low price subcontract for practical rule. 2) Applying rating ratio of subcontract that is followed by receiving status, constructing ability, and selling scale of small and medium construction company for improving working of cooperator.

  • PDF

Deriving Key Risk Sub-Clauses which the Engineer of FIDIC Red Book Shall Agree or Determine according to Sub-Clause 3.7 -based on FIDIC Conditions of Contract for Construction, Second Edition 2017- (FIDIC Red Book의 Engineer가 합의 또는 결정해야할 핵심 리스크 세부조항 도출 -FIDIC Red Book 2017년 개정판 기준으로-)

  • Jei, Jae Yong;Hong, Seong Yeoll;Seo, Sung Chul;Park, Hyung Keun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.43 no.2
    • /
    • pp.239-247
    • /
    • 2023
  • The FIDIC Red Book is an international standard contract condition in which the Employer designs and the Contractor performs the construction. The Engineer of FIDIC Red Book shall agree or determine any matter or Claim in accordance with Sub-Clause 3.7 neutrally, not as an agent of the Employer. This study aimed to derive Key Risk Sub-Clauses out of 49 Sub-Clauses that the Engineer of FIDIC Red Book recently revised in 18 years shall agree or determine according to Sub-Clause 3.7 using the Delphi method. A panel of 35 experts with more than 10 years of experience and expertise in international construction contracts was formed, and through total three Delphi surveys, errors and biases were prevented in the judgment process to improve reliability. As for the research method, 49 Sub-Clauses that engineers shall agree on or determine according to Sub-Clause 3.7 of the FIDIC Red Book were investigated through the analysis of contract conditions. In order to evaluate the probability and impact of contractual risk for each 49 Sub-Clause, the Delphi survey conducted repeatedly a closed-type survey three times on a Likert 10-point scale. The results of the first Delphi survey were delivered during the second survey, and the results of the second survey were delivered to the third survey, which was re-evaluated in the direction of increasing the consensus of experts' opinions. The reliability of the Delphi 3rd survey results was verified with the COV value of the coefficient of variation. The PI Risk Matrix was applied to the average value of risk probability and impact of each of the 49 Sub-Clauses and finally, 9 Key Risk Sub-Clauses that fell within the extreme risk range were derived.

Evaluation of Capability for Practicing CM at Risk in Korea (국내 시공책임형 건설사업관리 수행을 위한 기업 역량 평가)

  • Ryu, HanGuk;Lee, Sangwon;Choi, Jaehyun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.21 no.2
    • /
    • pp.79-87
    • /
    • 2020
  • The Korean domestic construction management at risk (CMAR) market is in the process of completing the pilot project execution under the leadership of the Ministry of Land, Infrastructure and Transport as of December 2019. The government starts practicing CMAR an alternative delivery method widely in order to diversify delivery methods and enhance construction technology. The CMAR market is thus expected to grow. This study was conducted to improve CMAR firms' capability by developing self-assessment tools for them to evaluate current capability more effectively. As a result of defining standard core capability and additional elements categorized by project execution phase and management area, and performing evaluation from the CMAR project participants, it was found that the general project management capability in the pre-design and procurement phase and quality management area was lower compared to the construction phase and other areas. In addition, the capability of cost management area was lower in spite of its high importance. Communication and coordination, process optimization, and target values achievement were at the initial level of capability and continuous improvement was required.

A Study of Analysis for Impact Assessment of the Cost Risk-Factor on the Design-Build Projects based on Business Process (설계시공일괄방식 사업의 업무단계별 사업비용 리스크요인에 대한 영향도 평가 및 분석)

  • Seo, Jae-Pil;Lee, Sang-Hyun;Song, Young-Woong;Choi, Yoon-Ki
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.3
    • /
    • pp.14-24
    • /
    • 2012
  • Recently, a delivery system has been rapidly changed in the global construction market. Also, construction projects are becoming bigger and more technology-intensive. A lot of projects have been delivered by Design-Build(DB) System; from the standpoint of cost, approximately 40% of delivered constructions by a Public Procurement Service were DB in 2009. Nevertheless, the achievement has not surpassed our expectations on management of the project cost. On the characteristic of DB, the reasons why that happens are that projects contract have been signed after the Design Development Stage; the insufficient review about new technology and up-to-date construction methods; a lack of discussion in process of design. Those reasons cause a risk of increasing Cost of the projects. In order to solve these problems, it is desirable to find Cost-increasing factors in promoting the projects and select on the order of priority for Risk-Factor with careful management. Therefore, this study analyzed the weight of each phase of the project on the authority of properties of DB project, and identified Risk-factors which is increasing the cost on the aspect of project management. Based on this analysis, the impact assessment of Risk-factor is evaluated through the Failure Mode and Effect Analysis(FMEA).

A Study on Improvement Direction for Construction Environment of Small Houses -Focused on Expert Group- (소형주택의 건설 프로세스 개선방향에 관한 연구 -전문가 집단을 중심으로-)

  • Ha, Jun-Geun;Yoo, Seok-Hyung
    • The Journal of the Korea Contents Association
    • /
    • v.18 no.7
    • /
    • pp.388-400
    • /
    • 2018
  • Small houses are continuously supplied after the alleviated housing act enacted in 2009. This study aimed to conduct a survey among an expert group associated with small house construction, propose problems by discovering difficulties and vulnerable points small and medium-sized construction companies experience while launching construction works as well as factors that impede the safety and housing environment of small houses. Furthermore, it ultimately intends to propose improvements. First, low-priced order is a major cause of unreasonable contract. Most companies were found to have low-priced orders in order to manage order performance. Low bidding and low-priced order are implemented to maintain construction businesses, ultimately threatening the safety environment of buildings. In addition, it is assumed that moderate bid periods and construction periods should be guaranteed. Second, work standardization for small and medium-sized companies is needed due to numerous cases that failed to meet order process. Additionally, regular instruction is required as many employees are not fully aware of relevant contents. Third, the most urgent policy direction turned out avoidance of low-priced bidding and removing insolvent enterprises from the market. Small and medium-sized construction companies that primarily build small houses undergo poor work condition. Therefore, the safety environment of small houses should be enhanced through work standardization and avoiding low-priced order.

A Case Study on the Risk Impact and Loss Cost of Temporary Aircraft Runway Construction (임시 활주로 건설공사의 위험영향 및 손실비용 사례분석)

  • Kang, Hyunwook;Lee, Wonbae;Kim, Minjung;Kim, Yongsu
    • Korean Journal of Construction Engineering and Management
    • /
    • v.21 no.1
    • /
    • pp.32-39
    • /
    • 2020
  • The purpose of this study is to derive the risk factors that occurred during the construction of the temporary aircraft runway and to analyse the risk costs and loss costs. For this purpose, actual construction data made during the construction of the aircraft runway were investigated. And the risk factors that occurred during the construction work were derived. So the increased construction costs and loss costs due to risk factors were analyzed. The results of this study are as follows: 1)The number of risk factors that occurred during the construction of the aircraft runway was derived from eight. 2)It was calculated that the total risk cost of 5.2million won, the risk cost of the owner's should be 243 million won and the cost of the contractor should be 277million won. 3)Owner's was up 2.36% from its planned budget and the contractor lost -277million won out of its planned profit of 443million won, resulting in a residual profit of 165million won. The results of the study are used as a reference for estimating risk factors and contingency that should be considered in aircraft runway construction.

Development of an Unit Cost Modification Model for Proper Actual Cost Data in Small Building Construction Projects (소규모 건축공사의 적정 실적공사비 단가보정 모델 개발)

  • Kim, Kang-Shik;Hyun, Chang-Taek;Hong, Tae-Hoon;Jo, Seong-Min;Mun, Hyun-Seok
    • Journal of the Korea Institute of Building Construction
    • /
    • v.10 no.1
    • /
    • pp.81-89
    • /
    • 2010
  • Since 2004, the government has changedthe cost estimate system to one of an actual cost basis in order to calculate the optimum construction cost by reflecting changes in circumstance on the construction site in a timely manner. Currently, this is being applied to public construction work forover a billion won of actual cost data in estimation by contract unit cost. However, directly reflecting actual cost, which for large-sized construction work was originally an average unit cost, to a small building, entails the application of a low discount rate for the cost of materials, labor, etc. and therefore can frequently give rise to cases in which the actual cost of work performed exceeds the contract sum, which in turn causes problems such as decreased revenues, bad effectson business operation, productivity, etc. Therefore, to apply actual cost to small-sized construction work (less than a billion won), there should be a plan to modify unit cost in a manner that can reflect project scale, etc. in order to resolve the problem of unit cost application of actual cost to small-building construction projects. The unit cost modification model for proper actual construction cost in small-scale construction projects developed by this study will help to increase the relevant productivity and proper gain, preventing the aggravation of business operations. Organizations placing orders are also expected to be able to secure a more realistic construction cost in arranging the budget.

The Effect of Corporate Social Responsibility on Organizational Trust, Job Satisfaction and Turnover Intention (건설기업의 사회적 책임 활동이 조직신뢰, 직무만족과 이직의도에 미치는 영향)

  • Cho, Jin-Ho;Kim, Byung-Soo
    • Korean Journal of Construction Engineering and Management
    • /
    • v.20 no.5
    • /
    • pp.83-94
    • /
    • 2019
  • Recently, the proportion of overseas orders of domestic construction companies is increasing, and the global market demands management transparency on corporate social responsibility activities. Therefore, domestic companies are faced with the need to systematically prepare for social responsibility activities. The purpose of this study was to examine whether CSR activities have a moderating effect on the relationship between organizational trust, job satisfaction, turnover intention and contract type. This study analyzed the effect of CSR activities on organizational trust, job satisfaction and turnover intention. The study targets regular and irregular workers in construction companies who promote CSR activities through the homepage, public service ad, and media. The questionnaire distributed 300 copies online. The final valid sample is 255 (145 Regular and 110 Irregular). Empirical analysis used a structural equation model. The results of the study are as follows. First, in CSR activities, economic responsibility, philanthropic responsibility and ethical responsibility had a positive (+) effect on organizational trust. Second, organizational trust had a positive (+) effect on job satisfaction in CSR activities. Finally, the magnitude of the Moderate effect of the type of labor contract according to the group classification showed that the CSR activity on organizational trust had many regular employees with economic responsibility. Also, organizational trust in job satisfaction was found to be large in regular employees. The results of this study can be a guide to CSR activities of construction companies in terms of organizational effectiveness.

AA Study on the Selection Criteria for Delivery Systems of Public Construction Projects in Local Governments (지자체 공공건설사업의 발주방식 선정기준에 관한 연구)

  • Choi, Eun-A;Kim, Byung-Ok;Lee, Sang-Beom
    • Journal of the Korea Institute of Building Construction
    • /
    • v.9 no.5
    • /
    • pp.111-117
    • /
    • 2009
  • With the current trend in the industry toward increasingly complex, diversified and large construction projects, advanced countries in the construction field have already introduced and applied a variety of methods for placing orders in order to cope with such changes in construction circumstances. In Korea, there have been efforts to continuously improve approaches to placing an order. With the aim of diversifying the methods of Delivery Systems, the "Technical Proposal Type Bid," and the "Design Competition and Technical Proposal Type Bid" were introduced through a revision of Korea's contract law enforcement ordinance. In line with the government's efforts, criteria for a method of placing an order that is suitable for a public construction project should be presented. This study enumerates the current issues using a survey for construction projects already placed and an analysis of the current status, and presents the selection criteria for Delivery Systems by business type as an improvement for the problem.

A Study on the Improvement of Specification in connection with Construction Lessons Learned Database (건설공사 지식데이터베이스 연계를 통한 시방서 개선방안)

  • Song Jae-Young;Lee Tai-Sik;Choi Jae-Ho
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.511-514
    • /
    • 2002
  • Nowadays, domestic construction companies make an effort to share knowledge and experience accumulated while conducting a project. One way of improving knowledge sharing is to develop specifications which are linked to the expert's knowledge and experience based on the specification classification. Therefore, the purpose of this paper is to review the current domestic specification system and develop the specification linked to the construction lessons learned database. It is expected that the proposed specification system will support the decision making process by effectively providing the knowledge and solution.