The body of an excavator, one sort of the construction equipment, consists of mainframe part, track frame part, boom part and arm part. The all parts are manufactured in the body welding operation. The scheduling in the body welding operation of a construction equipment manufacturing is to take all the various constraints into consideration. The offset time, due date, daily capacity of operations, daily jig's capacity, precedence relation, outsourcing, alternative resource and all of the shop floor environment should be considered. An APS(Advanced Planning & Scheduling) system is a proper and efficient system in such circumstance. In this paper, we present an APS system, the optimal scheduling system for the construction equipment manufacturing specifically for the body welding operation, using ILOG Solver/Scheduler. ILOG Solver/Scheduler is a general purposed commercial software which supports to find a feasible or optimal solution using object oriented technique and constraints satisfaction programming, given constraints and objectives.