• Title/Summary/Keyword: TBM diameter

Search Result 54, Processing Time 0.023 seconds

Analysis of Standard Construction by TBM Diameter through the Rock Scenario Models in the Field (현장 암반 시나리오 모델을 통한 TBM 구경별 표준 공사기간 분석)

  • Park, Hong Taea;Lee, Yang Kyu
    • Journal of the Society of Disaster Information
    • /
    • v.9 no.2
    • /
    • pp.195-205
    • /
    • 2013
  • Construction Management means a comprehensive plan of given the resources and the operation of the elements to complete the construction within the construction period. The construction period of these shall be determined by calculation based on reliable initial business. However, in actual field, inaccurate task duration is determined to the intuitive judgments of representative, reference of a similar project construction period of the past. As previous studies for the improvement of existing methods, This study presented a standard model that can be utilized in the early stages of construction projects for the TBM method operating by diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m), and This study presented and calculated construction period which can estimated quickly the entire outline the construction period Therefore, When performing TBM construction work in the future, the total construction period which presented and analyze by TBM diameter, can be used as a useful material which plan and manage construction contracts, construction estimating, construction planning to the basic planning stage, and the basic design stage.

A study on the selection of optimal cross section according to the ventilation system in TBM road tunnels (TBM 도로터널의 환기방식에 따른 최적단면 선정에 관한 연구)

  • Lee, Ho-Keun;Kang, Hyun-Wook;Kim, Hyun-Soo;Kim, Hong-Moon
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.15 no.2
    • /
    • pp.135-148
    • /
    • 2013
  • Recently, road tunnels have become longer and the plans for long and deep road tunnel have been underway in urban areas. These long and deep tunnel excavations include NATM and TBM. Shield TBM is applied to around 80% of traffic tunnels in Europe, and approximately 30% of them in other developed countries. However, as much of equipment is imported from foreign countries at high prices and distribution rate of TBM tunnel is considerably low in Korea, NATM excavation method is commonly used. To increase TBM tunnel, it is necessary to do assure economic feasibility with the supply-demand of TBM equipment. For this, the selection of standardized TBM diameter is urgently needed. Therefore, the study aims to estimate the standardized optimum section properties of TBM by examining TBM excavation cross section utilization depending on the volume of traffic, the number of lane and its cross-section type(single or double deck), and ventilation system.

A Study of the Large Diameter Shield TBM Excavation for Subway Tunnels (지하철 터널에 적용된 대구경 쉴드 TBM의 굴착성능 연구 분석)

  • Lee, Seong-Won;Kang, Moon-Gu
    • Proceedings of the KSR Conference
    • /
    • 2010.06a
    • /
    • pp.1500-1505
    • /
    • 2010
  • The objective of this study is controlling of the large diameter Shield TBM excavation for subway tunnels. In this paper, it will focus on the selection of Shield TBM and the problems of excavation due to unusual abrasion of the Disk Cutters and the distorted Cutter Mounts, in mixed layer of soil in below and hard rock in above, and in rock layer. And also, it will be discussed that the type of ground improvement to change and repair the Disk Cutters and the distorted Cutter Mounts, Advance Rate, Cutter Torque, etc. The results of this study will be using controlling of the excavation in various large diameter Shield TBM for subway tunnels.

  • PDF

Statistical Characteristics and Rational Estimation of Rock TBM Utilization (암반굴착용 TBM 가동율의 통계적 특성 및 합리적 추정에 관한 연구)

  • Ko, Tae Young;Kim, Taek Kon;Lee, Dae Hyuck
    • Tunnel and Underground Space
    • /
    • v.29 no.5
    • /
    • pp.356-366
    • /
    • 2019
  • Various TBM performance prediction models have been developed and most of them were considered penetration rate only. Despite the fact that some models have suggested equations and charts for estimating the utilization factor, but there are a few studies to estimate the TBM utilization factor. Utilization factor is affected by the type of TBM machine, operation, maintenance of machine, geological conditions, contractor experience and other factors. In this study, more than 100 case studies are analyzed to determine the relationship between the utilization factor and RMR, geological conditions, TBM types, tunnel length, and TBM diameter. Simple and multiple linear regression analysis are performed to develop predictive models for the utilization factor. The predictive model with explanatory variables of geological conditions, TBM types, tunnel length, and TBM diameter does not give a good correlation. The predictive models with explanatory variable of RMR give higher values of the coefficient of determination.

Database Analysis for Estimating Design Parameters of Medium to Large-Diameter TBM (중대단면 TBM 설계 사양 예측을 위한 DB분석)

  • Choi, Soon-Wook;Park, Byungkwan;Chang, Soo-Ho;Kang, Tae-Ho;Lee, Chulho
    • Tunnel and Underground Space
    • /
    • v.28 no.6
    • /
    • pp.513-527
    • /
    • 2018
  • The Tunnel Boring Machine(TBM) is relatively insufficient to cope with unpredicted changes in ground conditions as compared with Conventional Tunnelling Methods. Therefore, it is very important to predict the TBM performance at the design stage and estimate the advance rate for the calculation of the construction period. In this study, we added data to 211 TBM databases constructed in the previous study and analyzed the correlation between TBM outer diameter, maximum thrust, maximum cutterhead torque, cutterhead driving power and RPM, which are the main design and manufacturing specifications of TBM. As a result of the analysis from results obtained in the previous studies, it was confirmed that TBM outer diameter is very effective and important in estimating maximum thrust, maximum cutterhead torque, and cutterhead driving power of the TBM. As a result of comparing the regression equations derived from other TBM databases outside the country and the regression equation obtained from the present study results, the maximum thrust showed a similar tendency to each other, but the maximum torque estimated from the regression equation of this study was higher than that of other countries in the case of the large scale TBM.

Analysis of Standard Cost and the Construction Period Applied TBM Excavation Method (TBM 굴착 공법 적용 구경별 표준 공사비 및 공사기간 분석 연구)

  • Park, Hong Tae
    • Journal of the Society of Disaster Information
    • /
    • v.8 no.4
    • /
    • pp.319-327
    • /
    • 2012
  • This research collected work drilling report of TBM method site developed by WRITH company to TBM equipment company in Germany and analyzed work operating productivity. Based the data analyzed TBM operating productivity, This research derived and presented excavation speed(m/day) by TBM diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m) and rock. Also, based on the excavation speed(m/day) by TBM diameter, This research estimated a day direct construction cost and total direct construction costs by applying a direct construction cost which spent on per 1m. Based on hard rock 40.0%, soft rock 30.0%, usually rock 20%, weathered rock 10.0%, TBM boring velocity, m per cost, total construction period shall estimate the construction cost and the construction period by the effective use by diameter when future applying TBM method to the basic planning stages and in the preliminary design phase.

Development of a model for an equation for estimating construction costs based on the resource-based cost estimating system for TBM (TBM 공법의 자원기반 적산 방식에 의한 개산 공사비 예측 식 모델 개발)

  • Han, Seung-Hee;Park, Hong-Tae
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.14 no.3
    • /
    • pp.1474-1480
    • /
    • 2013
  • This study attempted to estimate construction costs in accordance with the resource-based cost estimation (unit cost price) system by diameter for TBM method, and analyzed the direct cost and the total cost. Based on such figures, this study performed a regression analysis and proposed a model for an equation for estimating construction costs. model for the resource-based cost estimation (unit cost price) system classified by diameter for TBM method proposed by this study can be effectively applied to business planning, preliminary investigation, feasibility study, construction cost estimations in the early design stages.

Analysis of Excavation Speed and Direct Construction Cost Based on the Operating Productivities of TBM Method Site (TBM 굴착 공법 적용 현장의 생산성 분석을 통한 암질별 굴진속도 및 직접공사비 분석)

  • Song, Young Sun;Park, Hong Tae
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.32 no.6D
    • /
    • pp.637-643
    • /
    • 2012
  • This research collected work drilling report of TBM method site developed by WRITH company to TBM equipment company in Germany and analyzed work operating productivity. Based Oil the data analyzed TBM operating productivity, This research derived and presented excavation speed (m/day) by TBM diameter (3.0m, 3.5m, 3.8m) and rock. Also, based on the excavation speed (m/day) by TBM diameter, This research estimated a day direct construction cost and total direct construction costs by applying a direct construction cost which spent on per 1m. When we perform a similar geological construction in the future, excavation speed and direct construction cost which were derived by TBM diameter and rock is thinking the effective utilization data to estimate construction cost and plan schedule management before the start of construction.

A Study on the Operation Development Method through the Application Results Large-Diameter Tunnel (대구경 터널공법 적용 사례분석을 통한 운영 개선방안)

  • Lee, Yang Kyu
    • Journal of the Society of Disaster Information
    • /
    • v.8 no.2
    • /
    • pp.108-118
    • /
    • 2012
  • The application of TBM tunneling has been progressively increased since the first entrance into korea in 1985. In order to an apprehension and operation development of TBM method which has excellent boring in hard rock tunnel, this study has analyzed mutual relation of lose time and TBM boring from actual construction results TBM tunneling. This study compared this analyzed results with TBM tunnelling construction results of korea, america, japan, analyzed a primary factor of TBM boring effect and suggested operation development method from the analyzed results. accordingly this study can be used an index when contract apply TBM method to planning steps.

Case of assembly process review and improvement for mega-diameter slurry shield TBM through the launching area (발진부지를 이용한 초대구경 이수식 쉴드TBM 조립공정 검토 및 개선 사례)

  • Park, Jinsoo;Jun, Samsu
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.24 no.6
    • /
    • pp.637-658
    • /
    • 2022
  • TBM tunnel is simple with the iterative process of excavating the ground, building a segment ring-build, and backfilling. Drill & Blast, a conventional tunnel construction method, is more complicated than the TBM tunnel and has some restrictions because it repeats the inspection, drilling, charging, blasting, ventilation, muck treatment, and installation of support materials. However, the preparation work for excavation requires time and cost based on a very detailed plan compared to Drill & Blasting, which reinforces the ground and forms a tunnel after the formation of tunnel portal. This is because the TBM equipment for excavating the target ground determines the success or failure of the construction. If the TBM, an expensive order-made equipment, is incorrectly configured at the assembly stage, it becomes difficult to excavate from the initial stage as well as the main excavation stage. When the assembled shield TBM equipment is dismantled again, and a situation of re-assembly occurs, it is difficult throughout the construction period due to economic loss as well as time. Therefore, in this study, the layout and plan of the site and the assembly process for each major part of the TBM equipment were reviewed for the assembly of slurry shield TBM to construct the largest diameter road tunnel in domestic passing through the Han River and minimized interference with other processes and the efficiency of cutter head assembly and transport were analyzed and improved to suit the site conditions.