Analysis of Standard Construction by TBM Diameter through the Rock Scenario Models in the Field  

Park, Hong Taea (Department of Civil Engineering, Kongju National University)
Lee, Yang Kyu (Department of Civil Environmental Daelim University)
Publication Information
Journal of the Society of Disaster Information / v.9, no.2, 2013 , pp. 195-205 More about this Journal
Abstract
Construction Management means a comprehensive plan of given the resources and the operation of the elements to complete the construction within the construction period. The construction period of these shall be determined by calculation based on reliable initial business. However, in actual field, inaccurate task duration is determined to the intuitive judgments of representative, reference of a similar project construction period of the past. As previous studies for the improvement of existing methods, This study presented a standard model that can be utilized in the early stages of construction projects for the TBM method operating by diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m), and This study presented and calculated construction period which can estimated quickly the entire outline the construction period Therefore, When performing TBM construction work in the future, the total construction period which presented and analyze by TBM diameter, can be used as a useful material which plan and manage construction contracts, construction estimating, construction planning to the basic planning stage, and the basic design stage.
Keywords
Construction Management; Construction Duration Analysis; TBM diameter;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Ultra Construction, Tunnel Boring Machine Method. 1993. 5, pp 1-40
2 Kim BS, Jean JG, A Study on Estimation Model of Construction Duration for Public Construction, Korean Journal of Construction Engineering and Management, Volume 6, No. 6, 2005, 12, pp 11-16
3 Lee, YI. Case Law on the TBM Tunnel Excavation, Korea Journal of the Tunnel, 1997. 2, pp 1-8
4 Lee YS, Lee DY, Park CS, A Case Study on the Efficiency of Construction Durations and Activities Based on Resource, Korean Journal of Construction Engineering and Management Conference, 2009. 11, pp 32-43
5 Lee JS, Study on introduction of 'Pre-Agreement system for Additional Incidental Cost' related to construction time extension, Korean Journal of Construction Engineering and Management Conference, 2012. 11, pp 33-44
6 Mun Seong Woo, Park Sang Cheon, Approximate Estimating of Plant Construction Duration Using a Standard Schedule Model, Korean Journal of Construction Engineering and Management Conference Volume 10, No. 2 (Serial No. 48) 2009. 3 pp.26-33
7 Park, HT, Soung, YS, A Study on Efficiency Improvement through Productivity Analysis Based on TBM Operation Data, Journal of the Society of Civil Engineers, 2010. 4, pp 55-60