Analysis of Excavation Speed and Direct Construction Cost Based on the Operating Productivities of TBM Method Site

TBM 굴착 공법 적용 현장의 생산성 분석을 통한 암질별 굴진속도 및 직접공사비 분석

  • 송용선 (공주대학교 건설환경공학부) ;
  • 박홍태 (공주대학교 건설환경공학부)
  • Received : 2012.05.11
  • Accepted : 2012.08.03
  • Published : 2012.11.15

Abstract

This research collected work drilling report of TBM method site developed by WRITH company to TBM equipment company in Germany and analyzed work operating productivity. Based Oil the data analyzed TBM operating productivity, This research derived and presented excavation speed (m/day) by TBM diameter (3.0m, 3.5m, 3.8m) and rock. Also, based on the excavation speed (m/day) by TBM diameter, This research estimated a day direct construction cost and total direct construction costs by applying a direct construction cost which spent on per 1m. When we perform a similar geological construction in the future, excavation speed and direct construction cost which were derived by TBM diameter and rock is thinking the effective utilization data to estimate construction cost and plan schedule management before the start of construction.

본 연구는 대표적인 TMB 장비 회사인 독일 WRITH사에서 개발한 TMB 공법 적용 현장의 굴진보고서를 수집하여 작업운영 생산성을 분석하였다. 그리고 분석된 자료를 근거로 구경별(3.0m, 3.5m, 3.8m) 굴진속도(m/일)를 도출하였다. 또한, 도출된 구경별 굴진속도를 근거로 독일의 WRITH사에서 구경별로 제시한 1m당 굴진에 소요되는 직접공사비를 적용하여 총 직접공사비를 산출하였다. 암질별 구경별로 도출된 굴진속도는 향후 유사한 암질에서 공사를 수행할 때, 공사 착수 전 총작업일수 및 총직접공사비의 산정을 활용한 공정 계획 및 관리를 수행하는데 효과적인 활용 자료가 될 것으로 사료된다.

Keywords

References

  1. Civil Engineering (1998) Case Studies of Japanese Mountain Tunnel Construction.
  2. Dawid Marin (1998) Proven TBM's Turn Power up in Norway Tunneling.
  3. Dohwal Design Company (2000) Ulsan Industrial Water Project Design Report.
  4. Lee, Y. I. (1997) Case Law on the TBM Tunnel Excavation, Korea Journal of the Tunnel.
  5. Nishida, T. and Matsumura, Y. (1993) Rock Mechnical Viewpoint on Excavation of Pressure Tunnel by TBM.
  6. Park, H.T. and Soung, Y.S. (2010) A Study on Efficiency Improvement through Productivity Analysis Based on TBM Operation Data, Journal of the Society of Civil Engineers.
  7. Park, Y. O. (1996) Case Law on the TBM Tunnel at Hard Rock, Korea Journal of Geotechnical Engineering.
  8. Ultra Construction (1993) Tunnel Boring Machine Method.
  9. Ultra Construction TBM tunnel excavation process of technological innovation (2010).