Chang-Yong Yi;Chan-Sik Park;Doo-Jin Lee;Dong-Eun Lee
International conference on construction engineering and project management
/
2009.05a
/
pp.400-408
/
2009
Simulation applications for analyzing the productivity of construction operations at operation level and project schedules at project level are crucial methods in project management. The application at two different levels should be very tightly linked to each other in practice. However, appropriate integration at the levels is not achieved in that existing systems do not support to integrate operation models into a schedule model. This paper presents a new approach named to Discrete Event Simulation-Nesting modeling approach, which supports not only productivity analysis at operation level but also schedule management at a project level. The system developed by the authors allows creating operation models at the operation level, maintaining them in operation model library, executing sensitivity analysis to find the behaviors of the operation models when different combination of resources are used as existing DES systems do. On top of the conventional functions, the new system facilitates to find the optimum solution of resource combinations which satisfy the user's interest by computing the hourly productivity and the hourly cost of the operation. By drag-and-dropping an operation model kept in the operation model library, the operation models are integrated into an activity of the schedule model. When a complete schedule model is established by nesting operation models into the schedule model, stochastic simulation based scheduling is executed. A case study is presented to demonstrate the new simulation system and verify the validity of the system.
Korean Journal of Construction Engineering and Management
/
v.20
no.6
/
pp.98-106
/
2019
Recently, the number of project delay-related claims and disputes in Korean construction projects has been increasing rapidly. This suggests that the domestic construction contract practice, which has traditionally been superior to the client, is changing into a mutually balanced relationship among the contracting parties. The project delay analysis selects the application method according to the type of schedule approved at the start of the construction and how the schedule management was performed during the construction. The most important prerequisite for project delay analysis is that a complete CPM schedule agreed at the beginning of the construction is prepared and the actual progress of such schedule is well documented. This study is about applying the project delay analysis methodology of a case where a contractor claims damages to a client while constructing a large new private building construction project. In this study, it is determined whether the application of the as-planned analysis method is appropriate to the incomplete CPM schedule and then proposes the as-planned vs. as-built analysis method based on the new standard as an alternative. Next, apply the as-planned vs. as-built analysis method to the schedule in the case project, and then compare it with the result of the as-planned analysis method. The purpose of this study is to suggest a project delay analysis method suitable for the domestic schedule management practices, so that it can be used as a meaningful reference in project delay disputes and litigations of domestic construction projects.
The uncertainty of software projects makes a big gap between the initial schedule/expense and the final one. Moreover, it is difficult for a project manager to reschedule and re-budget for reflecting the effects of changes in the software development. In this paper, we suggest EVM (Earned Value Management) to control the schedule and the expenses of an on-going software development project. In order to apply EVM to a software project, we consider turnkey contracts and propose the way to calculate the earned value for the software development. Finally, we illustrate our method with the case of N-company. We expect our EVM help to analyze and to predict the final schedule and the expense of a software development project.
Since the size of the construction project has become massive, complicated and specialized, the use for a substantial amount of information provided from diverse participants is considered important. Schedule information obtained from a variety of sources is key during the construction project. Misunderstanding of schedule management information causes delay of construction period and low quality of construction. Currently, interest in BIM (Building Information Modeling) that produces the necessary data for the entire life cycle of the building process is rising. The study is to construct the BIM-base-information system in order to systematically manage schedule information of the construction work. For this purpose, the study established a BIM-base-schedule-management-business process and drew a classification system for the work for schedule-information construction. The study also drew information that can be extracted from the BIM model among properties required to build certain information. The schedule is made upon consideration of information needed for schedule management, and information required to schedule a timeline of the construction project by process is established.
Journal of Construction Engineering and Project Management
/
v.3
no.2
/
pp.21-34
/
2013
Various risk factors affect construction projects. Due to the uncertainties created by risk factors, actual activity durations frequently deviate from the estimated durations in either favorable or adverse direction. For this reason, evaluation of schedule uncertainty is required to make decisions accurately when managing construction projects. In this regard, this paper presents a new computer simulation model - the Repetitive Schedule Risk Analysis Model (RSRAM) - to evaluate unit-based repetitive building project schedules under uncertainty when activity durations and risk factors are correlated. The proposed model utilizes Monte Carlo Simulation and a Critical Path Method based repetitive scheduling procedure. This new procedure concurrently provides the utilization of resources without interruption and the maintenance of network logic through successive units. Furthermore, it enables assigning variable production rates to the activities from one unit to another and any kind of relationship type with or without lag time. Details of the model are described and an example application is presented. The findings show that the model produces realistic results regarding the extent of uncertainty inherent in the schedule.
Journal of Construction Engineering and Project Management
/
v.6
no.2
/
pp.24-29
/
2016
This paper elaborates the significance of scenario planning in risk management, and presents an integrated approach which takes into account the 'Risk Events' derived from scenario planning for risk prioritisation. This research integrates scenario planning with Risk Failure Mode and Effect Analysis (RFMEA) through examples from construction litigations of project schedule and cost overrun cases as a simplified approach to project risk management. The proposed methodology incorporates scenarios developed from realistic events of dispute and arbitration cases from construction projects, and thereby increasing potential to foresee risks and their effects well in advance. The results from this methodology shall be validated against outcome of survey study conducted by KPMG-PMI (2013) on project schedule and cost overruns that was based on Ministry of Statistics and Programme Implementation (MoSPI) Project Monitoring data for 2012-13.
Journal of the Korea Institute of Military Science and Technology
/
v.10
no.3
/
pp.100-108
/
2007
The purpose of the research is to propose an integrated project planning process and its implementation method. Although there is increasing interest in the application of the Earned Value Management(EVM) method in the project management area, the progress and maturity of the technical performance have not been included in assessing the Earned Value. The main concept of the planning process is to use cost, schedule, as well as the technical performance in the assessment of the Earned Value Management for Military R&D project management practices. The resulting process can enhance the efficiency of the project work by eliminating the currently duplicated activities between traditional project planning process and the newly implemented Earned Value Management process and by shortening the early planning process duration of projects adopting EVM practices.
International conference on construction engineering and project management
/
2005.10a
/
pp.929-934
/
2005
The complex and dynamic job nature and the ever-changing working environment of construction projects inevitably present uncertainties to construction operations. Identification, evaluation and control of uncertainties constitute main elements of risk management and critical tasks of project management in construction. This paper is focused on application of a simplified discrete-event simulation approach in management of schedule-overrun risks, each being the combination of the occurrence probability of an uncertain interruptive factor and its potential consequence in terms of time delay. A case study observed from a concreting operation in Hong Kong is converted into a simulation model and analyzed with an in-house-developed simulation package for demonstrating how the proposed approach can be implemented to manage multiple schedule-overrun risks on construction projects.
Korean Journal of Construction Engineering and Management
/
v.21
no.3
/
pp.76-84
/
2020
The rate of application of the modular plant in the plant industry is increasing, and for the success of the modularization projects, it is essential to develop and implement a systemized methodology across all phases of the project. However, Korean EPC firms lack project management capability when it comes to apply standardized methodology. Therefore, it is important to establish and systematize the cost/schedule integrated management method which are the two core elements of project management technology. This study was conducted to develop a methodology and guidelines for integrated management process for modular plant projects. The researchers developed a methodology for planning and managing cost and schedule, and integrated by module unit. Integrated cost and schedule methodology and guidelines developed can be used for various EPC modular plant projects to enhance the efficiency of project management.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.