Evaluating Schedule Uncertainty in Unit-Based Repetitive Building Projects  

Okmen, Onder (Project & Construction Department, General Directorate of State Hydraulic Works)
Publication Information
Journal of Construction Engineering and Project Management / v.3, no.2, 2013 , pp. 21-34 More about this Journal
Abstract
Various risk factors affect construction projects. Due to the uncertainties created by risk factors, actual activity durations frequently deviate from the estimated durations in either favorable or adverse direction. For this reason, evaluation of schedule uncertainty is required to make decisions accurately when managing construction projects. In this regard, this paper presents a new computer simulation model - the Repetitive Schedule Risk Analysis Model (RSRAM) - to evaluate unit-based repetitive building project schedules under uncertainty when activity durations and risk factors are correlated. The proposed model utilizes Monte Carlo Simulation and a Critical Path Method based repetitive scheduling procedure. This new procedure concurrently provides the utilization of resources without interruption and the maintenance of network logic through successive units. Furthermore, it enables assigning variable production rates to the activities from one unit to another and any kind of relationship type with or without lag time. Details of the model are described and an example application is presented. The findings show that the model produces realistic results regarding the extent of uncertainty inherent in the schedule.
Keywords
Construction management; Repetitive scheduling; Critical Path Method; Risk analysis; Correlation; Simulation models;
Citations & Related Records
연도 인용수 순위
  • Reference
1 J.C. Woolery, K.C. Crandall, "Stochastic network model for planning scheduling", Journal of Construction Engineering and Management, vol. 109, no. 3, pp. 342-354, 1983.   DOI   ScienceOn
2 H.N. Ahuja, V. Nandakumar, "Simulation model to forecast project completion time", Journal of Construction Engineering and Management, vol. 111, no. 4, pp. 325-342, 1985.   DOI   ScienceOn
3 R.E. Levitt, J.C. Kunz, "Using knowledge of construction and project management for automated schedule updating", Project Management Journal, vol. 16, no. 5, pp. 57-76, 1985.
4 L.S. Riggs, "Risk Management in CPM Networks", Computer-Aided Civil and Infrastructure Engineering, vol. 4, no. 3, pp. 229-235, 1989.
5 M.J. Mawdesley, "Time change charts for scheduling linear projects", Proceedings of the 6th ASCE Conference on Computing in Civil Engineering, pp. 613-620, 1989.
6 M.A. Ammar, E. Elbeltagi, "Algorithm for determining controlling path considering resource continuity", Journal of Computing in Civil Engineering, vol. 15, no. 4, pp. 292-298, 2001.   DOI   ScienceOn
7 D.J. Harmelink, J.E. Rowings, "Linear scheduling model: Development of controlling activity path", Journal of Construction Engineering and Management, vol. 124, no. 4, pp. 263-268, 1998.   DOI   ScienceOn
8 K.G. Mattila, D.M. Abraham, "Resource leveling of linear schedules using integer linear programming", Journal of Construction Engineering and Management, vol. 124, no. 3, pp. 232-244, 1998.   DOI   ScienceOn
9 A. Oztas, O. Okmen, "Judgmental risk analysis process development in construction projects", Building and Environment, vol. 40, no.9, pp. 1244-1254, 2005.   DOI   ScienceOn
10 A. Touran, E.P. Wiser, "Monte Carlo technique with correlated random variables", Journal of Construction Engineering and Management, vol. 118, no. 2, pp. 258-272, 1992.   DOI
11 I.T. Yang, "Risk Modeling of Dependence among Project Task Durations", Computer-Aided Civil and Infrastructure Engineering, vol. 22, no. 6, pp. 419-429, 2007.   DOI   ScienceOn
12 O. Okmen, A. Oztas, "Construction Project Network Evaluation with Correlated Schedule Risk Analysis Model (CSRAM)", Journal of Construction Engineering and Management, vol. 134, no. 1, pp. 49-63, 2008.   DOI   ScienceOn
13 R.B. Harris, P.G. Ioannou, "Scheduling projects with repeating activities", Journal of Construction Engineering and Management, vol. 124, no. 4, pp. 269-273, 1998.   DOI   ScienceOn
14 G.A. Duffy, G.D. Oberlender, D.H.S. Jeong, "Linear scheduling model with varying production rates", Journal of Construction Engineering and Management, vol. 137, no. 8, pp. 574-582, 2011.   DOI   ScienceOn
15 K. Cho, T. Hong, C. Hyun, "Scheduling model for repetitive construction processes for high-rise buildings", Canadian Journal of Civil Engineering, vol. 38, no. 1, pp. 36-48, 2011.   DOI   ScienceOn
16 A. Oztas, O. Okmen, "Risk analysis in fixed-price design-build construction projects", Building and Environment, vol. 39, pp. 229-237, 2004.   DOI   ScienceOn
17 A. Jaafari, "Criticism of CPM for project planning analysis", Journal of Construction Engineering and Management, vol. 110, no. 2, pp. 222-223, 1984.   DOI   ScienceOn
18 R. Flanagan, G. Norman, "Risk management and construction", Cambridge: Backwell Scientific, 1993.
19 L. Edwards, "Practical risk management in the construction industry", London: Thomas Telford, 1995.
20 M. Ranasinghe, A.D. Russell, "Treatment of correlation for risk analysis of engineering projects", Civil Engineering Systems, vol. 9, pp.17-39, 1992.   DOI
21 S. Selinger, "Construction planning for linear projects", ASCE Journal of Construction Division, vol. 106, no. 2, pp. 195-205, 1980.
22 O. Moselhi, A. Hassanein, "Optimized Scheduling of Linear Projects", Journal of Construction Engineering and Management, vol. 129, no. 6, pp. 664-673, 2003.   DOI   ScienceOn
23 K. El-Rayes, O. Moselhi, "Resource-driven scheduling of repetitive projects", Journal of Construction Management and Economics, vol. 16, pp. 433-446, 1998.   DOI
24 D.B. Ashley, "Simulation of repetitive-unit construction", ASCE Journal of Construction Division, vol. 106, no. 2, pp. 185-194, 1980.
25 RM. Reda, "RPM: Repetitive project modeling", Journal of Construction Engineering and Management, vol. 116, no. 2, pp. 316-330, 1990.   DOI
26 A.D. Russell, W.C.M. Wong, "New generation of planning structures", Journal of Construction Engineering and Management, vol. 119, no. 2, pp. 196-214, 1993.   DOI   ScienceOn
27 T. Hegazy, O. Moselhi, P.Fazio, "BAL: An algorithm for scheduling and control of linear projects", AACE Trans, C8-1-C8-14, 1993.
28 D. Arditi, M.Z. Albulak, "Line-of-balance scheduling in pavement construction", Journal of Construction Engineering and Management, vol. 112, no. 3, pp. 411-424, 1986.   DOI   ScienceOn
29 J.J. O'Brien, "VPM scheduling for high-rise buildings", Journal of Construction Division, ASCE, vol. 101, no. 4, pp. 895-905, 1975.
30 P. Lumsden, "The line of balance method", London: Pergamon Press Ltd, 1968.
31 D.W. Johnston, "Linear scheduling method for highway construction", Journal of Construction Engineering and Management, vol. 107, no. 2, pp. 247-261, 1981.
32 O. Stradal, J. Cacha, "Time space scheduling method", Journal of Construction Division, ASCE, vol. 108, no. 3, pp. 445-457, 1982.
33 N. Sadeghi, A.R. Fayek, W. Pedrycz, "Fuzzy Monte Carlo Simulation and Risk Assessment in Construction", Computer-Aided Civil and Infrastructure Engineering, vol.25, no. 4, pp. 238-252.
34 Dept of the Navy. "PERT, program evaluation research task", Washington: Phase I Summary Rep., Special Projects Office, Bureau of Ordnance,1958.
35 A.H.S. Ang, A.A. Chaher, J. Abdelnour, "Analysis of activity networks under uncertainty", Journal of the Engineering Mechanics Devision, vol. 101, no. 4, pp. 373-387, 1975.
36 C.F. Diaz, F.C. Hadipriono, "Nondeterministic networking methods", Journal of Construction Engineering and Management, vol. 119, no. 1, pp. 40-57, 1993.   DOI
37 W.C. Wang, L.A. Demsetz, "Application example for evaluating networks considering correlation", Journal of Construction Engineering and Management, vol. 126, no. 6, pp. 467-474, 2000.   DOI   ScienceOn
38 W.C. Wang, L.A. Demsetz, "Model for evaluating networks under correlated uncertainty-NETCOR", Journal of Construction Engineering and Management, vol. 126, no. 6, pp. 458-466, 2000.   DOI   ScienceOn
39 R.I. Carr, "Simulation of construction project duration", Journal of Construction Division, ASCE, vol. 105, no. 2, pp. 117-128, 1979.