• Title/Summary/Keyword: wrong installation

Search Result 17, Processing Time 0.019 seconds

A Study on the Corrosion Property of Sprinkler Pipe and the Solution (스프링클러 배관의 부식 특성과 대책에 관한 연구)

  • Kim, Dongsung;Cho, Cheol Won;Kim, Byungseon;Lee, Tae Shik
    • Journal of Korean Society of societal Security
    • /
    • v.1 no.2
    • /
    • pp.87-92
    • /
    • 2008
  • This paper investigates the corrosion property of sprinkler pipe and provides the prevention solution. This study examines the property of stainless pipe widely used as sprinkler pipe and performs theoretical studies on the corrosion procedure. It was found that corrosion of the pipes mainly results from deterioration of pipe and wrong installation. The test result is expected to be useful in designing of the pipe system and minimizing of the corrosion.

  • PDF

A Study on Grounding Technology for the Reduction of Electric Surge in IBS Building (IBS 빌딩에서의 서어지 저감을 위한 접지방안 연구)

  • 박중양;김학련;최규형
    • Proceedings of the Korean Institute of IIIuminating and Electrical Installation Engineers Conference
    • /
    • 2003.11a
    • /
    • pp.87-92
    • /
    • 2003
  • According to the realization of highly information dependent society, the recent building system is developed into the concept of suitable for management of intellegent work, which is demanded to unify of IBS(Intelligent Building System), IC(information communication), OA(office automation), BA(building automation) system and computer technology. However inspite of the presence arrester, cable shielding, insulated TR, filter, earth etc., in the IBS building for the cope with several surge and noise has several problems from the wrong operation of the equipment which caused from several surge, damage of equipment, and noise etc. And the miss operation caused by wrong earth works, which must be considered at first during the building construction. In order to minimize these problems, it's necessary that various earth project are performed effectively, and bonding methods between the mutual wiring of earth system and the equipments in the building should be improved sucessively. So in this paper, we analyze present domestic conditions of the earth technology in IBS building, and propose minimization method for the various surge and noise problem, and examine and analyze through the applied works.

  • PDF

Analysis of Partial Discharge Inception Voltages for the Wrong Positioning Defects in the Joint of Distribution Power Cables

  • Kim, Jeong-Tae;Kim, Dong-Uk;Lee, Young-Jo;Koo, Ja-Yoon
    • Journal of Electrical Engineering and Technology
    • /
    • v.7 no.6
    • /
    • pp.977-982
    • /
    • 2012
  • In order to find out partial discharge (PD) phenomena in the cable joint due to the poor workmanship during the installation, the relationship between PD inception voltages and joint defects was investigated. For the purpose, in the joint of 22.9kV CNCV cables, electric fields were calculated for various semiconductive layer wrong positioning (WP) defects. And, PDIV were investigated through the experiments and compared with the results of electric field analysis. In all WP defect cases, the PD inception field calculated using measured PDIVs was similarly shown to be the average value of 1.84kV/mm. In addition, the calculated PDIV and the measured PDIV were almost equal, from the PDIV calculation using maximum electric fields and the measured PDIV for the normal case. Throughout this study, it is possible to analyze WP defects due to the poor workmanship and to establish better joint design for the distribution grade extruded cable system.

A Study on the Marine Lattern Development using Light Emitting Diodes (해상용 LED(Light Emitting Diode) 등명기 연구개발)

  • Jeong, Hak-Geun;Jung, Bong-Man;Han, Su-Bin;Yu, Seong-Won;Kim, Hoon
    • Proceedings of the Korean Institute of IIIuminating and Electrical Installation Engineers Conference
    • /
    • 2004.05a
    • /
    • pp.167-170
    • /
    • 2004
  • A high light lantern system using LEDs is composed of power supply, flash controller, and daylight controller and proper case considering work condition. The performance of developed LED lantern is better than that of the existing marine lantern using an incandescent electric lamp and that of foreign products(Vega LED lantern made in New Zealand, Tideland system made in America). The electric consumption of our products is 30% compared with that of existing marine lantern using an incandescent electric lamp, and the luminous Intensity of them is 200% to 400% compared with that of existing marine lantern and foreign LED lantern. In addition, our LED lantern system is easy to repairing something wrong and changing the LED module and other controllers on the sea when they are in accident.

  • PDF

Efficiency analysis of PV tracking system with PSA algorithm (PSA 알고리즘에 의한 태양광 추적시스템의 효율분석)

  • Back, Jung-Woo;Ko, Jae-Sub;Choi, Jung-Sik;Jang, Mi-Geum;Kang, Sung-Jun;Chung, Dong-Hwa
    • Proceedings of the Korean Institute of IIIuminating and Electrical Installation Engineers Conference
    • /
    • 2009.05a
    • /
    • pp.412-415
    • /
    • 2009
  • This paper analyzes efficiency of photovoltaic(PV) tracking system using position solar algorithm(PSA). Solar location tracking system is needed for efficiently and intensively using PV system independent of environmental condition. PV tracking system of program method is presented a high tracking accuracy without the wrong operating in rapidly changed insolation by the clouds and atmospheric condition. Therefore, this paper analyzes efficiency of PV system using PSA algorithm for more correct position tracking of solar. Also, controlled altitude angle and azimuth angle by applied algorithm is compared with data of korea astronomy observatory. And this paper analyzes the tracking error and roves the validity of applied algorithm.

  • PDF

Comments on a Case Study on Engineering Failure Analysis of Link Chain

  • Yu, George Y.H.
    • Safety and Health at Work
    • /
    • v.12 no.4
    • /
    • pp.544-545
    • /
    • 2021
  • The article by Tae-Gu Kim et al. conducted elastic FE modeling, which was inappropriate for fracture of elastic-plastic chain material (11.3% of elongation). FE analysis results and the findings in the fracto-graphic analysis did not tally but contradicted each other. The article identified "incorrect installation"/bending forces as the root cause while FE results of the chain under bending forces showed very low stresses at fracture locations but the highest stress in the middle of shank of the chain. The article's "step-like topographies indicating the fracture due to bending moment rather than uniaxial tension" lacked scientific support. The load value carried by each chain section under bending/incorrect installation was only half of that under tension, thus the article using same load value in FE simulation comparison for bending and tension was incorrect. The real cause of the chain fracture was likely improper checking the lifted load or/and using the wrong chain with much lower safety working load.

Development of Defects Detecting System for Corrugated Board, Mill Application, and Changes of Production Defects Ratio (골판지 불량 검색 시스템 개발, 현장적용과 생산 불량률 변화)

  • Jeong, Jin-Mo;Min, Kyung-Eun;Kim, Mun-Sung;Park, Jong-Moon
    • Journal of Korea Technical Association of The Pulp and Paper Industry
    • /
    • v.40 no.2
    • /
    • pp.37-42
    • /
    • 2008
  • Defects of corrugated board were limiting factors to the corrugated industry's growth. On-line detecting systems of defects are beneficial to increase profits of the corrugated board companies by reducing base paper consumption, increasing process reliability, and increasing productivity. By replacing naked eye inspection of defects to a defects detecting system, continuous inspection without fatigue may guarantee final products quality. The system was developed, which was consisted of line scan CCD camera, lens, illuminating parts, high speed image processor, software, various input parts, and output parts. First installation location of the system was at before fluting process after base paper unwinding, and surface of liner board was inspected by the system. Second installation location was after fluting process and combining process for liner board. Production loss includes ragged appearance of edge, irregular flute shape, wrong combination of flute, score cracking, defects in base paper, and flute cracking. The production loss was analyzed before and after the system installation at a commercial domestic mill. The production loss ratio was defined as a production loss weight per total production weight. The production loss ratio before the installation was decreased a lot from 1.28%(during 3 months before installation) to 0.76%(during 12 months after the first installation) and to 0.25%(during 6 months after the second installation).

Efficiency Analysis of PV Tracking System with PSA Algorithm (PSA 알고리즘에 의한 태양광 추적시스템의 효율분석)

  • Choi, Jung-Sik;Ko, Jae-Sub;Chung, Dong-Hwa
    • Journal of the Korean Institute of Illuminating and Electrical Installation Engineers
    • /
    • v.23 no.10
    • /
    • pp.36-44
    • /
    • 2009
  • This paper analyzes efficiency of photovoltaic(PV) tracking system using position solar algorithm(PSA). Solar location tracking system is needed for efficiently and intensively using PV system independent of environmental condition. PV tracking system of program method is presented a high tracking accuracy without the wrong operating in rapidly changing insolation by the clouds and atmospheric condition. Therefore, this paper analyzes efficiency of PV system using PSA algorithm for more correct position tracking of solar. Also, controlled altitude angle and azimuth angle by applied algorithm is compared with data of korea astronomy observatory. And this paper analyzes the tracking error and generation efficiency then proves the validity of applied algorithm.

HA Study on the Selection of Mobile Crane Model for Heavy Equipments Installation (중량물 설치 시 이동식 크레인 기종선정에 관한 연구)

  • Jeong, Jae-Bok;Yoo, Ho-Seon
    • Plant Journal
    • /
    • v.8 no.2
    • /
    • pp.59-69
    • /
    • 2012
  • This study focuses on avoiding the failures from the wrong selections by experiences as simulation programs is not available, and suggests the methods which effectively select the alternatives when the selected model is not appropriate for the original plan. First, CC8800-1K of DEMAG has the longest boom whose length is 216 m at the maximum. The combination of the boom is feasible to second level except for MANITIWOC M 2250 (M-1200 RINGER) which is possible to third level. Second, the angle of boom is from 20 degrees to 82 degrees. Suitable angle to work is in the 55-78 degrees. The working load of crawler type and hydraulic one to be applied is 75-85% in the critical loads capacity. As increasing operating radius, crawler type is a favorable position over hydraulic one. Lastly, related problems were verified through examination by suggestions for the design of the selection methods for the case analysis. The major problems are stemming from the selection based on its experiences, unreasonable demand for the existing facility and repeated selections by the designer who accumulates his experiences via same or similar projects.

  • PDF

A Study on the Current Status and Analysis on the Problem of Unfloored space and Floor Repair in Rural House (농촌주택의 봉당·마루 개보수 현황 및 문제점 분석)

  • Park, Gil-Beom;Park, Jun-Mo;Kim, Ok-Kyue
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2014.11a
    • /
    • pp.117-118
    • /
    • 2014
  • The unfloored space and floor is one of characteristic of traditional house in Korea. This space is used to connecting passage between room or entrance of house. Currently, according to decline of heat insulation property thereby becoming decrepit house, native is repairing it for block external environment such as rain, wind and so on. But, variety problem is happening from wrong repair. This object of this study is current status and analysis on problem of unfloored space and floor repair. As a result, current status of repair is classified repair type, installation position and using form. And position of problem is confirmed connection between original house and extend space.

  • PDF