• Title/Summary/Keyword: CPM Schedule

Search Result 52, Processing Time 0.019 seconds

The Concept of Schedule and Cost Progress Integrated Management on the BDM Network (BDM 네트워크 공정 및 비용 진도율 통합관리 개념)

  • Kim, Seon-Gyoo;Lee, Yong-Hyun;Noh, Seong-Beom;Ko, Dae-Gyu
    • Korean Journal of Construction Engineering and Management
    • /
    • v.12 no.6
    • /
    • pp.54-64
    • /
    • 2011
  • Almost 40 years have been passed since the CPM was introduced to the construction industry in Korea. However most of construction projects in Korea do not prepare the CPM schedule neither operate it after established manually, as well as still depend on the Bar-chart schedule only. One of these reasons is because the CPM schedule does not reflect the site works realistically, it makes so difficult to recognize the actual progress clearly in visual format, and it is impossible to integrate and manage the time and cost oriented work progresses effectively. This paper proposes new concept of progress management that is able to integrate and manage the time oriented schedule progress and earned value oriented cost progress while maintaining the merits of CPM although the CPM schedule summarized automatically within a schedule hierarchy by the BDM that is a new CPM technique. We expect that this concept could make the applications of CPM technique to the domestic construction industry popular and help the advancement of the construction management in Korea as well.

AN EXAMPLE OF REPRESENTING THREE LEVEL'S SCHEDULES WITHIN SCHEDULE HIERARCHY BY BDM TECHNIQUE

  • Seon-Gyoo Kim
    • International conference on construction engineering and project management
    • /
    • 2011.02a
    • /
    • pp.445-452
    • /
    • 2011
  • The schedule hierarchy in construction project is generally composed of three levels. The highest level is a milestone schedule and represented by Bar Chart format. The middle level is an integrated project schedule (IPS) and represented by CPM (Critical Path Method) format. The lowest level is a detail working schedule and usually represented by Bar Chart. The traditional scheduling techniques such as ADM (Arrow Diagramming Method) or PDM (Precedence Diagramming Method) cannot represent all kinds of schedule within schedule hierarchy as identical schedule format. However, the BDM (Beeline Diagramming Method) technique can represent all kinds of schedule within schedule hierarchy as identical CPM format. This paper describes the basic concept, principle, interpretation methods, and schedule computation methods of the BDM as a new networking technique that can represent all kinds of overlapping relationships between activities, and then presents an example of representing three level's schedules within schedule hierarchy by the BDM technique.

  • PDF

Dongeui Visual-PERT/CPM for R&D Project Management (연구개발 프로젝트관리를 위한 시각화모델)

  • 황흥석
    • Proceedings of the Korean Operations and Management Science Society Conference
    • /
    • 2000.10a
    • /
    • pp.268-271
    • /
    • 2000
  • In these days, the technical advances and complexities have generated much of the difficulties in managing the project resources, both time and costing to accomplish the project in the most efficient manner. The project manager is frequently required to render judgements concerning the schedule and resource adjustments. This research develops an analytical model for a schedule-cost and risk analysis based on visual PERT/CPM. We used a two-step approaches :in the step 1, a deterministic PERT/CPM model for the critical path and estimating the project time schedule and related resource planning, In the second step, we developed a heuristic model for crash and stretch out analysis based upon a time-cost trade-off associated with the crash and stretch out of the project. Computer implementation of this model is provided based on GUI-Type objective-oriented programming for the users and provided displays of all the inputs and outputs in the form of visual graphical. Also developed GUI-type program, Dongeui Visual-PERT/CPM. The results of this research will provide the project managers with an efficient management tool.

  • PDF

A Method for Schedule Simulation Considering Rework and Uncertainty (재작업과 불확실성을 고려한 일정 시뮬레이션 방법론)

  • Kim, Chan-Mook;Park, Young-Won
    • Journal of the Korean Society for Railway
    • /
    • v.12 no.1
    • /
    • pp.135-143
    • /
    • 2009
  • The majority of development projects fail to meet their target schedule and cost, with the overrun typically between 40 and 200 percent. These overruns happen because the planners underestimate the work or do not consider the need to rework at project planning. Representative schedule planning/management techniques such as Gantt Chart, PERT/CPM etc. that are used in domestic project planning are unable to reflect rework. This paper proposes a method to consider rework to provide more realistic estimates at schedule planning. Additionally, to prevent the underestimation of the work this paper proposes a simulation method that calculates a probabilistic estimated schedule and the associated variance based on the random variable modeling of individual task completion dates.

A Study on Schedule Management in Construction Project Using the Dependency Structure Matrix(DSM) (DSM을 이용한 건설사업 공정관리에 관한 연구)

  • Jang, Se-Hoon;Park, Moon-Seo;Lee, Hyun-Soo
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2007.11a
    • /
    • pp.682-686
    • /
    • 2007
  • Construction project has been more complex and bigger as various demands of the times. But current schedule management method in construction project uses only PERT or CPM made in 1950s without innovation. Also current schedule management focuses on not information flow between activities and variability of information exchanged but result. This paper suggest using the DSM(Dependency Structure Matrix) in schedule management of construction project to overcome limitations of current scheduling tools. DSM has been introduced as a new theory in construction industry in 1990s at the United States, but its application is still insufficient in domestic field due to the absence of systematic study.

  • PDF

A Study on Schedule Management in Construction Projects by CCPM (CCPM을 이용한 건설사업 일정관리에 관한 연구)

  • Park Young-Min;Kim Soo-Yong;Kim Ki-Young
    • Korean Journal of Construction Engineering and Management
    • /
    • v.5 no.5 s.21
    • /
    • pp.84-92
    • /
    • 2004
  • Construction work varies with the project types. However, the success of all project types depends upon three conditions i.e. schedule, quality and cost. If these three conditions are fulfilled, then project said to be successful. In this paper, scheduling of a construction Project has been dealt with the application of CCPM method. CCPM has been introduced as a new theory in construction industry in 1997 at the United States, but its application is still insufficient in domestic field due to the absence of systematic study, A simulation has been conducted in a Bridge construction project to validate the possibility of CCPM in order to complement PERT/CPM in construction field. The result of study shows that the CCPM could be effective to reduce the project time duration than existing PERT/CPM technique.

Case Analysis on Application of Project Delay Analysis Method in Domestic Construction Project (국내 건설공사에서 공기지연 분석방법 적용 사례 분석)

  • Kim, Seon-Gyoo;Kwon, Soonwook
    • Korean Journal of Construction Engineering and Management
    • /
    • v.20 no.6
    • /
    • pp.98-106
    • /
    • 2019
  • Recently, the number of project delay-related claims and disputes in Korean construction projects has been increasing rapidly. This suggests that the domestic construction contract practice, which has traditionally been superior to the client, is changing into a mutually balanced relationship among the contracting parties. The project delay analysis selects the application method according to the type of schedule approved at the start of the construction and how the schedule management was performed during the construction. The most important prerequisite for project delay analysis is that a complete CPM schedule agreed at the beginning of the construction is prepared and the actual progress of such schedule is well documented. This study is about applying the project delay analysis methodology of a case where a contractor claims damages to a client while constructing a large new private building construction project. In this study, it is determined whether the application of the as-planned analysis method is appropriate to the incomplete CPM schedule and then proposes the as-planned vs. as-built analysis method based on the new standard as an alternative. Next, apply the as-planned vs. as-built analysis method to the schedule in the case project, and then compare it with the result of the as-planned analysis method. The purpose of this study is to suggest a project delay analysis method suitable for the domestic schedule management practices, so that it can be used as a meaningful reference in project delay disputes and litigations of domestic construction projects.

CPM BAR CHART TECHNIQUE FOR CONSTRUCTION SCHEDULING

  • Kyung-hwan Kim;Soo-yoo Kim;Jae-jun Kim
    • International conference on construction engineering and project management
    • /
    • 2005.10a
    • /
    • pp.1118-1123
    • /
    • 2005
  • This paper proposes the CPM bar chart (CBC), a hybrid of the bar chart and the critical path method (CPM). The CBC overcomes shortages of the fence bar chart, while still retaining its advantages. The fence with direction is applied instead of the broken fence, which triggers considerable problems to identify and apply in the fenced bar chart. In addition, the notorious task to find dummy activities is no longer required. Upon the benefits of simplicity in the bar chart and logical work sequence in the CPM network, the CBC provides a relatively easy way to create and understand a schedule, thus improving communication quality between project participants.

  • PDF

Project Schedule Risk Assessment Based on Bayesian Nets (베이지안넷 기반의 프로젝트 일정리스크 평가)

  • Sung, Hongsuk;Park, Chulsoon
    • Journal of Korean Society of Industrial and Systems Engineering
    • /
    • v.39 no.1
    • /
    • pp.9-16
    • /
    • 2016
  • The project schedule risk in the engineering and facility construction industry is increasingly considered as important management factor because the risks in terms of schedule or deadline may significantly affect the project cost. Especially, the project-based operating companies attempt to find the best estimate of the project completion time for use at their proposals, and therefore, usually have much interest in accurate estimation of the duration of the projects. In general, the management of projects schedule risk is achieved by modeling project schedule with PERT/CPM techniques, and then performing risk assessment with simulation such as Monte-Carlo simulation method. However, since these approaches require the accumulated executional data, which are not usually available in project-based operating company, and, further, they cannot reflect various schedule constraints, which usually are met during the project execution, the project managers have difficulty in preparing for the project risks in advance of their occurrence in the project execution. As these constraints may affect time and cost which role as the crucial evaluation factors to the quality of the project result, they must be identified and described in advance of their occurrence in the project management. This paper proposes a Bayesian Net based methodology for estimating project schedule risk by identifying and enforcing the project risks and its response plan which may occur in storage tank engineering and construction project environment. First, we translated the schedule network with the project risks and its response plan into Bayesian Net. Second, we analyzed the integrated Bayesian Net and suggested an estimate of project schedule risk with simulation approach. Finally, we applied our approach to a storage tank construction project to validate its feasibility.

IMPROVING THE USABILITY OF STOCHASTIC SIMULATION BASED SCHEDULING SYSTEM

  • Tae-Hyun Bae;Ryul-Hee Kim;Kyu-Yeol Song;Dong-Eun Lee
    • International conference on construction engineering and project management
    • /
    • 2009.05a
    • /
    • pp.393-399
    • /
    • 2009
  • This paper introduces an automated tool named Advanced Stochastic Schedule Simulation System (AS4). The system automatically integrates CPM schedule data exported from Primavera Project Planner (P3) and historical activity duration data obtained from a project data warehouse, computes the best fit probability distribution functions (PDFs) of historical activity durations, assigns the PDFs identified to respective activities, computes the optimum number of simulation runs, simulates the schedule network for the optimum number of simulation runs, and estimates the best fit PDF of project completion times (PCTs). AS4 improves the reliability of simulation-based scheduling by effectively dealing with the uncertainties of the activities' durations, increases the usability of the schedule data obtained from commercial CPM software, and effectively handles the variability of the PCTs by finding the best fit PDF of PCTs. It is designed as an easy-to-use computer tool programmed in MATLAB. AS4 encourages the use of simulation-based scheduling because it is simple to use, it simplifies the tedious and burdensome process involved in finding the PDFs of the many activities' durations and in assigning the PDFs to the many activities of a new network under modeling, and it does away with the normality assumptions used by most simulation-based scheduling systems in modeling PCTs.

  • PDF