The Concept of Schedule and Cost Progress Integrated Management on the BDM Network  

Kim, Seon-Gyoo (강원대학교 건축공학과)
Lee, Yong-Hyun (강원대학교 건축공학과)
Noh, Seong-Beom (강원대학교 건축공학과)
Ko, Dae-Gyu (강원대학교 건축공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.12, no.6, 2011 , pp. 54-64 More about this Journal
Abstract
Almost 40 years have been passed since the CPM was introduced to the construction industry in Korea. However most of construction projects in Korea do not prepare the CPM schedule neither operate it after established manually, as well as still depend on the Bar-chart schedule only. One of these reasons is because the CPM schedule does not reflect the site works realistically, it makes so difficult to recognize the actual progress clearly in visual format, and it is impossible to integrate and manage the time and cost oriented work progresses effectively. This paper proposes new concept of progress management that is able to integrate and manage the time oriented schedule progress and earned value oriented cost progress while maintaining the merits of CPM although the CPM schedule summarized automatically within a schedule hierarchy by the BDM that is a new CPM technique. We expect that this concept could make the applications of CPM technique to the domestic construction industry popular and help the advancement of the construction management in Korea as well.
Keywords
CPM; Progress Management; Beeline Diagramming Method; PDM; Schedule Hierarchy;
Citations & Related Records
연도 인용수 순위
  • Reference
1 김선규 (2010). 공정관리특론, 기문당
2 방종대, 손종락, 조건희, 이중호, 홍영남 (2002). 공동주택 건설 공사의 진도율 및 기성산정방법에 관한 연구, 대한주택공사
3 Buntrock, Aaron (2009). Progress & Performance Measure- ment, The Construction Institute, CMS Inc.
4 Callaham, Michael T. (1992). Construction Project Schedul- ing, McGraw-Hill.
5 Flemming. Q. W. and Koppleman, J. M. (1996). Earned Value Management System, Project Management Institute, Upper Darby, Pa.
6 Jung, Youngsoo and Kang Seunghee (2007). Knowledge- Based Standard Progress Measurement for Integrated Cost and Schedule Performance Control, Journal of Construction Engineering and Management.
7 Kim, Seon-Gyoo (2011). An Example of representing Three Level's Schedules within Schedule Hierarchy by BDM Technique, Proceedings of the International Conference on Construction Engineering and Project Management, Sydney, Australia.
8 Kim, Soo-Young and Lee, Jong-Chool (2004). A Performance Measurement of a Construction Project in Korea, Proceedings of the fifth Asia Pacific Industrial Engineering and Management Systems Conference.