Cable Tension Force Management Using Vibration Method at Cable Stayed Bridge Construction Stages (진동법을 이용한 사장교 시공단계별 케이블 장력관리)

  • Park, Yeon-Soo;Cheon, Dong-Ho;Cheon, Yang-Bae;Kang, Kyoung-Koo
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.9 no.4
    • /
    • pp.127-134
    • /
    • 2005
  • Design and construction of long-span bridge are recently increasing by development of computer technology. Specially, cable stayed bridge and suspension bridge having cable component are representative of long-span bridge may do. Therefore, this paper a present a methodology for cable tension force monitoring in cable-stayed bridge under construction using acceleration data acquired by the vibration method. To improve accuracy construction, all stay cables are measured, according to 4-step construction stage and change of temperature.

A Study on Evaluation Method of Cable Tension for Railway Steel Composite Bridge (강철도 복합교량 케이블의 장력 평가기법에 관한 연구)

  • Choi, Jung-Youl;Lee, Soo-Jae;Chung, Jee-Seung
    • The Journal of the Convergence on Culture Technology
    • /
    • v.8 no.4
    • /
    • pp.407-413
    • /
    • 2022
  • In this study, the empirical formula for evaluating cable tension based on long-term measurement for about 3 years according to temperature change was proposed by proving the correlation between the expansion joint displacement of the upper road bridge and the cable tension of the lower railway bridge. The tension prediction results using the empirical formula for tension evaluation each cables proposed in this study were found to be in good agreement with the cable tension using the vibration method within 3%. Therefore, it was analyzed that it could be applied together with the vibration method that was an experimental technique, to predict and evaluate the cable tension in serviced railway steel composite bridge. As a result of applying the estimated temperature calculated by the empirical formula for expansion proposed in this study to the empirical formula, it was analyzed that a high level of reliability could be secured when compared with the vibration method. Therefore, it is judged that the empirical formula for cable tension evaluation reflecting the estimated temperature proposed in this study can be used to predict the tension of cables according to climate change in the future and establish a maintenance plan.

A Study on Temperature Properties Analysis for Tension Measurement of Steel Cables Using Magnetic Sensor (자기센서에 의한 강재 케이블 장력측정에서 온도특성에 대한 연구)

  • Park, Hae-won;Ahn, Bong-young;Lee, Seung-seok;Park, Jeong-hak
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.13 no.2 s.54
    • /
    • pp.181-188
    • /
    • 2009
  • Measuring the tensile strength of steel cables used to support bridges is a critical inspection item in terms of the safety of a bridge. Today, cable tension is measured with the vibration method and loadcell. Recently, some advanced countries have conducted studies on measuring tension with magnetic method and are suggesting prospective results. Since there were no such studies ongoing in Korea, we began a study on measuring tension with magnetic method as we are undergoing researches to improve the precision of measurements. It is necessary to consider the influence for the magnetic field and the temperature of steel cables in tension measurement of magnetic method. In this paper, we tested an output characteristic of tension sensor according to temperature and deduced temperature compensation coefficient in the given magnetic field and applied the compensation coefficient to the tension measurement system in the lab. We analyzed and evaluated testing results for the output voltages of the tension sensor according to cable tensions.

Development of Magnetic Sensor for Measurement of the Cable Tension of Large Scale Bridge (대형교량 케이블 장력 측정을 위한 자기센서 개발)

  • Park, Hae-Won;Ahn, Bong-Young;Lee, Seung-Seok;Kim, Jong-Woo
    • Journal of the Korean Society for Nondestructive Testing
    • /
    • v.27 no.4
    • /
    • pp.339-344
    • /
    • 2007
  • Safety of large scale cable in bridge is very important because it may cause the unwanted catastrophic failure. Although the proof load were considered at the design stage, its soundness must be monitored continuously because the cable may be broken out without warning by the variable external load. The cable tension of in-use structures has been mainly measured by the resonance method and its use has been limited because of relatively large measurement uncertainty. Recently a new magnetic method was developed and its reliability is known to be good for evaluating the cable tension. In this study a system which can deliver the calibrated load to the cable was developed and the measurement reliability of developed magnetic sensor according to the change of external load was analyzed quantitatively. The effect of magnetization frequency, bias magnetic field, and temperature on the sensor output was also evaluated.

Effect of Cable Tension Changes on Track Irregularity of Railway Ballasted Track on Railway Steel Composite Bridge (케이블 장력변화가 강철도 복합교량 상 자갈궤도의 궤도틀림에 미치는 영향)

  • Jung-Youl Choi;Soo-Jae Lee
    • The Journal of the Convergence on Culture Technology
    • /
    • v.9 no.4
    • /
    • pp.633-638
    • /
    • 2023
  • In this study, the effect of the change in cable tension on the track irregularity of railway ballasted track on a railway steel composite bridge was analyzed. As a result of comparing design and analysis results for cable tension, a difference of less than 3% was found, and analysis modeling was analyzed to reflect the design conditions well. In addition, the adequacy of the analysis modeling was demonstrated by comparing the field measurement results with the analysed cable tension. By considering the change in cable tension as a variable, the track irregularity of the railway steel composite bridge was analyzed. As a result of the analysis, it was analyzed that the total and one-sided cable tension change had a direct effect on the vertical irregularity among the track irregularity items. In addition, it was found that the change in track irregularity occurred in the section close to the cable position. It was analyzed that the change in cable tension had a more direct effect on track irregularity that had a direct correlation with the vertical direction rather than the lateral direction.

Determination of Initial Tension and Reference Length of Cables of Cable-Stayed Bridges (사장교의 케이블 초기장력 및 기준길이 결정에 관한 연구)

  • Yhim, Sung-Soon
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.9 no.2
    • /
    • pp.137-146
    • /
    • 2005
  • This study presents the shape iteration method and the updated Lagrangian methods to calculate the initial tension and the reference length of cables of cable-stayed bridges. The girders and towers of cable-stayed bridge are modelled as 3-dimensional frame elements and the cable as nonlinear truss element or Ernst's cable element. Compared with the initial tensions of cables by finite element method in this study and by trial-and error method in practices, the tensions by the former are shown to be a little less than the those by the latter. The reference lengths of cables by Ernst's cable elements are almost consistent with those of cables by nonlinear truss elements. And the reference length of cables in this study are almost consistent with the arc length of beam with the same initial tension. Therefore the reference lengths of cables in cable-stayed bridges are shown to be obtained simply by the theory of beam with the initial tension calculated in this study.

Evaluation of Applicability of Cable Force Monitoring System of Cable-stayed Bridge by Field Loading Test (재하시험을 통한 사장교의 케이블 장력 모니터링 시스템의 적용성 평가)

  • Kim, Jeong-Hoon;Song, Jae-Ho
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.13 no.1 s.53
    • /
    • pp.205-213
    • /
    • 2009
  • This study was planned to develop monitoring system of cable force to resolve cable force of cable-stayed bridge efficiently in a long-term plan. In the proposed monitoring system, firstly data are sampled from real-time acceleration record, secondly these sampled data are frequency analyzed by using the FFT(Fast Fourier Transform) algorism and lastly the analyzed results are averaged and generalized. For evaluating the applicability of this monitoring system, field loading test has performed in real cable-stayed bridge. In comparison with cable force by field manual calculation and cable force of monitoring system by semi-automatic calculation, the difference of calculated cable forces has within 1% error range and it is acceptable range. Additionally within negligible 5% error range of difference has occur between field manual calculation and monitoring system by automatic calculation. so monitoring system in this study has been verified to be reliable.

A Study on the Point to Be Considered When Installing Underground Distribution Cable into Conduit (관로 내 케이블 포설시 고려사항에 관한 연구)

  • Jung, Jong-Yon
    • Proceedings of the KIEE Conference
    • /
    • 2011.07a
    • /
    • pp.479-480
    • /
    • 2011
  • 관로내 케이블 포설시 케이블 허용장력이 포설장력을 초과하지 않도록 주의해야 한다. 또한, 케이블 포설 도중 Kink가 발생하지 않도록 케이블 드럼을 반드시 세워서 포설해야 하고, 케이블 드럼을 눕혀서 포설해서는 안 된다. 또한, 허용전류를 고려하여 케이블 상호간의 간격을 일정하게 유지해야 한다. 관로 내 케이블을 설치할 경우 직선구간 뿐 아니라 굴곡구간에도 설치되므로 포설측압이 허용측압을 초과하지 않도록 시설해야 한다. 측압에 견디기 위해서는 케이블 포설시 곡률 반경을 케이블 외경의 10배 이상으로 유지하는 것이 중요하다.

  • PDF

Estimation of Stay Cable Tension Using String Vibration Theory (현이론을 이용한 사장교 케이블 장력산정)

  • Park, Yeon-Soo;Choi, Sun-Min;Lee, Byung-Geun;Kim, Nin Jung
    • Journal of the Korean Society of Hazard Mitigation
    • /
    • v.9 no.2
    • /
    • pp.17-22
    • /
    • 2009
  • Estimate method of cable tension forces can be classified into direct method and indirect method. Direct method is not accuracy and it has many restrictions. Therefore, in generally Indirect method, vibration method using natural frequency, has been applied to estimate the tension forces. In this study, cable tensions of recently constructed cable-stayed bridge are measured using string vibration method and this result comparing with result of multiple mode method. To put it brief, the error of string vibration method is not exceeding 2% under 7th mode. Specially third and 4th mode error is not exceeding 1%. safety.

Cable Tension Measurement of Long-span Bridges Using Vision-based System (영상처리기법을 이용한 장대교량 케이블의 장력 측정)

  • Kim, Sung-Wan;Cheung, Jin-Hwan;Kim, Seong-Do
    • Journal of the Korea institute for structural maintenance and inspection
    • /
    • v.22 no.2
    • /
    • pp.115-123
    • /
    • 2018
  • In a long-span bridge, the cables are important elements that support the load of the bridge. Accordingly, the cable tension is a very important variable in evaluating the health and safety of the bridge. The most popular methods of estimating the cable tensions are the direct method, which directly measures the cable stresses using load cells, hydraulic jacking devices, etc., and the vibration method, which inverses the tensions using the cable shapes and the measured dynamic characteristics. Studies on the use of the electromagnetic (EM) sensor, which detects the magnetic field variations caused by the change in the stress of the steel in the cable, are increasing. In this study, the lift-off test, the EM sensor, and the vibration method (Vision-based System and Accelerometer) were used to measure cable tension, and their results were compared and analyzed.