A Study on the Application of TACT Planning & Scheduling in Finish Work of Apartment Houses

공동주택 마감공사에서의 택트공정관리 적용에 관한 연구

  • 윤유상 (경원대학교 대학원 건축학과) ;
  • 서상욱 (경원대학교 건축학과)
  • Published : 2003.11.01

Abstract

The purpose of this study is using a TACT planning and scheduling for apartment houses construction that have many of same units. Because using a TACT planning and scheduling is concluded time reduction at same units as apartment plan. The main contents of this study are 1) window and door work through the field study, 2) adjust worker assignment to minimize work time variation, and 3) an effect of working time through a case study. As a result, the total working time can be improved $21.2\%$ by using the TACT planning and scheduling. The stu요 recommends that 1) establish an accurate data between work period and resource, and 2) preparation to measures minimization of waiting time before using a TACT planning and scheduling.

건축공사의 고층화 추세에 따라 반복공정의 수가 증가하고, 마감공사에서의 관련 공종 수가 증가하여 작업 연속성에 대한 계획 및 공사관리가 중요하게 인식되고 있으며, 이러한 마감공사의 효율적 은용을 위해 각 작업을 일정한 리듬으로 반복되도록 함에 따라 공정의 개선을 이루고자 하는 기법이 택트공정관리이다. 그러나 택트공정관리는 세부공정 및 작업구역에 따른 상이한 시공속도와 이로 인한 선행공정의 작업지연 등 비효율적 요소 때문에 적용에 어려움이 있었다. 따라서 본 연구에서는 작업별 소요시간의 동기화(同期化)를 통한 개선효과를 파악하기 위해 기존의 공동주택 창호공사를 대상으로 작업방식의 세부작업단위 및 작업인원 수를 작업시간의 동기적(同期的)연결 및 최소 요구인원 수를 기준으로 조정한 후, 공기단축 효과를 분석하였다.

Keywords