The Ground Reinforcement on Daylight Collapsed Block in Driving Work at the National Road No. 3 Line (국도 3호선 터널건설 공사 중 붕락구간에 대한 지반보강)

  • 천병식;정덕교;이태우;정진교
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 1999.02a
    • /
    • pp.14-22
    • /
    • 1999
  • Daylight collapse have been occurred by about 6.$^{0}$ m deep at ground surface which connected to the ground surface and excessive overbreak have been occurred by the space and height of 3.$^1$~6.$^2$m at crown head part of the tunnel during tunnelling of lower-half part after completing upper-half part on tunnelling of a phyllite mountain by NATM method at the construction work of two way-double track national road. This study is a successful illustration case of earth improvement by confirming structural safety of the tunnel in a whole through solving the cause of the tunnel collapse and the work have completed successfully through applying such earth strengthening method as cement mortarㆍcement milk injection, S.G.R, steel pipe reinforced multi-step grouting etc.

  • PDF

A Case Study on the Field Investigation and Stability Analysis of the Collapsed Cut-Slope in Tunnel Portal, Danyang (단양 지역 터널입구부 붕괴절토사면 현장조사 및 안정성 해석 사례 연구)

  • Kim, Seung-Hyun;Koo, Ho-Bon;Kim, Seung-Hee
    • The Journal of Engineering Geology
    • /
    • v.19 no.3
    • /
    • pp.401-408
    • /
    • 2009
  • Old national Road No. 59 that connects Danyang and Gagok has 35 dangerous cut slopes. It is relatively narrow and has a poor alignment. The torrential rains in 2002 and 2006 has caused numerous slope collapses, landslides and road settlements in this area. The old road's high risk level lead to the planning and construction of a new national road. During the construction of the new road in December 2006, the right side of Dugcheon Tunnel entrance has collapsed and tension cracks were observed on the district road above the tunnel. In order to determine the cause of failure, intensive field investigation and monitoring cracks were performed together with Lower Hemisphere Projection Analysis, Limit Equilibrium Analysis and Finite Difference Analysis.

Analysis of Ground Vibration due to Demolition (구조물 발파해체로 인한 지반진동의 해석 연구)

  • Kim, Seung-Kon;Park, Hoon;Yang, Hyung-Sik
    • Tunnel and Underground Space
    • /
    • v.12 no.3
    • /
    • pp.210-219
    • /
    • 2002
  • In the ground vibration due to demolition blasting vibration and impact vibration of collapsed structure are separated. In this paper, model structures were collapsed by blasting with different charge locations. Ground vibrations were measured and separated as blasting and impact vibrations by waveform and dominant frequency. Vibration characteristics of different charge locations were examined.

A Study on the Stability Analysis and Countermeasure of Tunnel Portal Failure Slope - in Suanbo Hot Springs 1 and 2 Tunnel Failure Site (터널 갱구부 붕괴 사면의 안정성 해석 및 보강공법에 관한 연구 - 수안보 온천 1, 2터널 붕괴 현장을 중심으로)

  • Baek, Yong;Koo, Ho-Bon;Yoo, Ki-Jeong
    • The Journal of Engineering Geology
    • /
    • v.12 no.4
    • /
    • pp.367-378
    • /
    • 2002
  • Recently, the number of tunnels on national roads has been increased due to the trend that construction of the large-scaled cut slopes is limited because of the environmental issues. Therefore, the slope failures of tunnel portal have often occurred. The tunnel portal in use has limitations on selection of the countermeasure and construction against slope failure. In the cases of Suanbo hot springs 1 and 2 tunnel portals, seedding was chosen and constructed as the countermeasureof slope failure when the tunnel was first built but collapsed in April, 2002. In this study, the failure sites were examined accurately through the site investigation and an efficient countermeasure according to stability analysis is presented. It is shown that it is very efficient to use resloping for Suanbo hot springs 1 tunnel and concrete buttress, rock anchor to reinforcement countermeasure, and attached rockfall prevention net by dividing the site into 3 sections for Suanbo hot springs 2 tunnel.

Upheaveal Behaviour of Tunnel Bottom in the Weatherd Fracture Zone under Tunnel Excavation (터널 굴착 중 바닥부 연약대로 인한 터널 융기 거동 사례 분석)

  • Chang, Yongchai;Kim, Nagyoung;Jin, Kyudong;Son, Yongmin
    • Journal of the Korean GEO-environmental Society
    • /
    • v.15 no.6
    • /
    • pp.49-56
    • /
    • 2014
  • The stability of tunnel construction depends entirely on the characteristics of the soil strength. If the soil strength is weak, collapse of tunnel occurs frequently under construction. In general, it copes with collapse by conducting half section excavation or reinforcement in advance under these conditions. Nevertheless, it can be collapsed under upper section excavation in the weathered fracture zone and it can be recovered through the application of reinforcement. As it has a bad influence on the upper section in case of upheaveal of tunnel bottom, it can be adversely affected on the overall stability of the tunnel. Thus, an in-depth review of reinforcement is needed in poor bottom ground. As the practices that has a bad affect on the stability of the tunnel due to upheaveal of tunnel bottom is increasing, research is needed for applicable standards for reinforcement. In this paper, it were investigated at actual field cases of upheaveal of bottom ground and characteristics of behavior and reinforcement measures were analyzed.

Face stability analysis of large-diameter underwater shield tunnel in soft-hard uneven strata under fluid-solid coupling

  • Shanglong Zhang;Xuansheng Cheng;Xinhai Zhou;Yue Sun
    • Geomechanics and Engineering
    • /
    • v.32 no.2
    • /
    • pp.145-157
    • /
    • 2023
  • This paper aims at investigating the face stability of large-diameter underwater shield tunnels considering seepage in soft-hard uneven strata. Using the kinematic approach of limit upper-bound analysis, the analytical solution of limit supporting pressure on the tunnel face considering seepage was obtained based on a logarithmic spiral collapsed body in uneven strata. The stability analysis method of the excavation face with different soft- and hard-stratum ratios was explored and validated. Moreover, the effects of water level and burial depth on tunnel face stability were discussed. The results show the effect of seepage on the excavation face stability can be accounted as the seepage force on the excavation face and the seepage force of pore water in instability body. When the thickness ratio of hard soil layer within the excavation face exceeds 1/6D, the interface of the soft and hard soil layer can be placed at tunnel axis during stability analysis. The reliability of the analytical solution of the limit supporting pressure is validated by numerical method and literature methods. The increase of water level causes the instability of upper soft soil layer firstly due to the higher seepage force. With the rise of burial depth, the horizontal displacement of the upper soft soil decreases and the limit supporting pressure changes little because of soil arching effect.

Stability Assessment of Tunnel Excavation Face Utilizing Characteristics of Collapse Cases (터널 시공현장 붕괴 사례를 이용한 막장의 안정성 평가 연구)

  • Kim, Mintae
    • Journal of the Korean Geotechnical Society
    • /
    • v.40 no.2
    • /
    • pp.55-64
    • /
    • 2024
  • While shield tunneling has demonstrated stability in international cases, the new Austrian tunneling method (NATM) encounters challenges in urban environments with shallow cover, weathered ground, and high groundwater levels. This paper introduces two typical collapse scenarios observed in urban areas, specifically within weathered bedrock and uncemented sandy soil layers. The collapses are analyzed using six stability evaluation methods, and the results are synthesized to assess the excavation face stability through a hexagonal diagram. The study finds a consistent agreement between the analysis results of the two collapsed tunnel sites and the evaluation outcomes. The employment of the stability evaluation diagram, a comprehensive method that considers the ground characteristics of the target tunnel, proves crucial for ensuring barrier stability during the tunnel design stage. This method is essential for a holistic evaluation, especially when addressing challenging ground conditions in urban settings.

Analysis on Surface Collapse of the Road NATM Tunnel through the Weathered Rock (풍화대를 통과하는 도로 NATM 터널의 천단부 함몰에 대한 연구)

  • Shin, Eun-Chul;Yoo, Jai-Sung
    • Journal of the Korean Geosynthetics Society
    • /
    • v.15 no.2
    • /
    • pp.55-64
    • /
    • 2016
  • The construction of the road NATM tunnel, which undergoes the weathered zone of the mountain, was in process with the reinforcement methods such as the rock bolt, shotcrete depositing, and the multi step grout with large diameter steel pipe. The collapse from the ceiling, and on the ground surface area(sink hole), of which were measured to be 25m from the ground surface($V=12m(W){\times}14m(L){\times}5m(H)=840m^3$), as well as excessive displacements in the tunnel, had occurred. In order to execute the necessary reconstruction work, the causes of the surface collapses were inspected through the field investigation, in-situ tests, and numerical analysis. As a result, several proper solutions were suggested for both internal and external reinforcements for the tunnel. As a result of numerical analysis, the collapsed zone of the tunnel was reinforced up to 0.5D~1.0D laterally by the cement grouting on the ground surface, 0.5D longitudinally by the multi step grout with large diameter steel pipe in tunnel. With further reinforcement implemented by rebars in lining, the forward horizontal boring was executed to the rest of the tunnel to evaluate the overall status of the tunnel face. Appropriate reinforcement methods were provided if needed.

A Study on development of the real-time monitoring program about the bridge using ubiquitous technology (유비쿼터스 기술을 이용한 교량의 상시 모니터링 프로그램 개발에 관한 연구)

  • Jo, Byung-Wan;Kim, Do-Keun;Park, Jung-Hoon;Kim, Heoun
    • 한국방재학회:학술대회논문집
    • /
    • 2008.02a
    • /
    • pp.493-496
    • /
    • 2008
  • In case of collapsed or damaged Servicing infrastructure, such as a bridge, tunnel, dam, a severe loss may have to be incurred. Therefore, infrastructure should not be designed and constructed properly but also maintained impeccably. This paper tried to build an intelligent bridge maintenance system that warn the people on bridge and control traffic in the danger. For the purpose, diverse wireless sensor fields are composed and structure's database is established. Also the paper develops a bridge maintenance program. Developed programme is regarded as a good tool to provide the utmost bridge management scenario, which is exactly correspondent with the demand and restraint by improving the present bridge management strategy.

  • PDF

Soft Sedimentary Rock Slopes Design of Diversion Tunnel

  • Jee, Warren Wangryul
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 2007.10a
    • /
    • pp.63-79
    • /
    • 2007
  • Several remedial works were attempted to stabilize the collapsed area of the inlet slopes of diversion tunnel, but prevention of any further movement was being only carried out at beginning stage by filling the area with aggregates and rock debris, after several cracks had been initiated and developed around the area. The extra specialty developed folding zone is consisted with highly weathered Greywacke and Black shale. The suggested solution is to improve the properties of the rock mass of failed area by choosing the optimum level of reinforcement through the increment of slope rock support design so as to control the movement of slopes during the re-excavation. The Bakun hydroelectric project includes the construction of a hydroelectric power plant with an installed capacity of 2,520MW and a power transmission system connecting to the existing transmission networks in Sarawak and Western Malaysia. The power station will consist of a 210m height Concrete Faced Rockfill Dam. During the construction of the dam and the power facilities the Balui River has to be diverted of the tunnels is 12m and the tunnel width is 16m at the portal area. This paper describes the stability analysis and design methods for the open cut rock slopes in the inlet area of the diversion tunnels. The geotechnical parameters employed in stability calculations were given as a function of four defined Rock Mass Type (RMT) which were based on RMR system from Bieniawski. The stability calculations procedure of the rock slopes are divided into two stages. In the first stage, it is calculated for the stability of each "global" slope without any rock support and shotcrete system. In the second stage, it is calculated for each "local" slope stability with berms and supported with rock bolts and shotcrete. The monitoring instrumentation was performed continuously and some of the design modification was carried out in order to increase the safety of failed area based on the unforeseen geological risks during the open cut excavation.

  • PDF