A Study on the Operation Development Method through the Application Result TBM Tunneling in the Bard Rock (암반터널에서의 TBM 공법 적용 사례 분석을 통한 운영 개선 방안)

  • Song, Young-Sun;Choi, Jae-Jin;Park, Hong-Tae
    • Journal of the Korea Academia-Industrial cooperation Society
    • /
    • v.9 no.4
    • /
    • pp.1050-1058
    • /
    • 2008
  • The application of TBM tunneling has been progressively increased since the first entrance into Korea in 1985. In order to an apprehension and operation development of TBM method which has excellent boring in hard rock tunnel, this study has analyzed mutual relation of lose time and TBM boring from actual construction result TBM tunneling. This study compared an analyzed result with TBM tunnelling construction results of Korea, America, Japan, analyzed a primary factor of TBM boring effect and suggested operation development method from the analyzed results. accordingly this study can be used an index when similar construction apply TBM method to planning steps.

A Study on the Operation Development Method through the Application Results Large-Diameter Tunnel (대구경 터널공법 적용 사례분석을 통한 운영 개선방안)

  • Lee, Yang Kyu
    • Journal of the Society of Disaster Information
    • /
    • v.8 no.2
    • /
    • pp.108-118
    • /
    • 2012
  • The application of TBM tunneling has been progressively increased since the first entrance into korea in 1985. In order to an apprehension and operation development of TBM method which has excellent boring in hard rock tunnel, this study has analyzed mutual relation of lose time and TBM boring from actual construction results TBM tunneling. This study compared this analyzed results with TBM tunnelling construction results of korea, america, japan, analyzed a primary factor of TBM boring effect and suggested operation development method from the analyzed results. accordingly this study can be used an index when contract apply TBM method to planning steps.

A Study on Efficiency Improvement through Productivity Analysis Based on TBM Operation Data (TBM공법 적용 현장별 생산성 분석을 통한 효율성 개선 방안)

  • Park, Hong Tae;Song, Young Sun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.30 no.1D
    • /
    • pp.71-77
    • /
    • 2010
  • This study presented the operation method through of productivity on eight analysis work items (TBM boring, cutter check and exchange, TBM maintenance, succeeding facilities, reinforcement in tunnel, operation alternation, a tram car) which have developed equipment at WRITH with TBM a waterway tunnel works. It was inquired lose time with analyzed result by work items and removed lose time. It was analyzed TBM boring length, TBM boring length percentage and TBM boring length time. This study analyzed TBM operation utility factor of a foreign work with TBM operation boring length percentage, a monthly average boring length, pure boring length percentage etc. and assumed a monthly average boring length and a monthly average boring length of rise forecast. Based on analyzed Data, TBM boring has been forecasted propriety pure boring length at compressive strength $675{\sim}1662kgf/cm^2$.

The $Mer{\aa}ker$ TBM Project in Norway (노르웨이 메로케르 수력발전소의 TBM 굴착)

  • Park Yeonjun;Park Chulwhan
    • Tunnel and Underground Space
    • /
    • v.15 no.1 s.54
    • /
    • pp.22-27
    • /
    • 2005
  • This paper presents an article explaining a TBM project overall in Norway. The paper which published in Norwegian TBM Tunnelling by Norwegian Soil and Rock Eng. Assoc. in 1998, contains most of the items considered in TBM tunnelling. New powerplants, tunnels and dams have been built at Meraker in Central Norway. A total of 44 km of tunnels with cross sections varying from $7\;m^2\;to\;32\;m^2$ have been excavated in hard rock formation. Tunnel of 10 km with the 3.5 m diameter was excavated by a HP TBM in a year. his project gives the special attention to the TBM drive and equipment selection, including planning, site organization and performance.

Prediction of Disk Cutter Wear Considering Ground Conditions and TBM Operation Parameters (지반 조건과 TBM 운영 파라미터를 고려한 디스크 커터 마모 예측)

  • Yunseong Kang;Tae Young Ko
    • Tunnel and Underground Space
    • /
    • v.34 no.2
    • /
    • pp.143-153
    • /
    • 2024
  • Tunnel Boring Machine (TBM) method is a tunnel excavation method that produces lower levels of noise and vibration during excavation compared to drilling and blasting methods, and it offers higher stability. It is increasingly being applied to tunnel projects worldwide. The disc cutter is an excavation tool mounted on the cutterhead of a TBM, which constantly interacts with the ground at the tunnel face, inevitably leading to wear. In this study quantitatively predicted disc cutter wear using geological conditions, TBM operational parameters, and machine learning algorithms. Among the input variables for predicting disc cutter wear, the Uniaxial Compressive Strength (UCS) is considerably limited compared to machine and wear data, so the UCS estimation for the entire section was first conducted using TBM machine data, and then the prediction of the Coefficient of Wearing rate(CW) was performed with the completed data. Comparing the performance of CW prediction models, the XGBoost model showed the highest performance, and SHapley Additive exPlanation (SHAP) analysis was conducted to interpret the complex prediction model.

Analysis of Standard Cost and the Construction Period Applied TBM Excavation Method (TBM 굴착 공법 적용 구경별 표준 공사비 및 공사기간 분석 연구)

  • Park, Hong Tae
    • Journal of the Society of Disaster Information
    • /
    • v.8 no.4
    • /
    • pp.319-327
    • /
    • 2012
  • This research collected work drilling report of TBM method site developed by WRITH company to TBM equipment company in Germany and analyzed work operating productivity. Based the data analyzed TBM operating productivity, This research derived and presented excavation speed(m/day) by TBM diameter (2.6m, 3.0m, 3.5m, 5.0m, 8.0m) and rock. Also, based on the excavation speed(m/day) by TBM diameter, This research estimated a day direct construction cost and total direct construction costs by applying a direct construction cost which spent on per 1m. Based on hard rock 40.0%, soft rock 30.0%, usually rock 20%, weathered rock 10.0%, TBM boring velocity, m per cost, total construction period shall estimate the construction cost and the construction period by the effective use by diameter when future applying TBM method to the basic planning stages and in the preliminary design phase.

Statistical Characteristics and Rational Estimation of Rock TBM Utilization (암반굴착용 TBM 가동율의 통계적 특성 및 합리적 추정에 관한 연구)

  • Ko, Tae Young;Kim, Taek Kon;Lee, Dae Hyuck
    • Tunnel and Underground Space
    • /
    • v.29 no.5
    • /
    • pp.356-366
    • /
    • 2019
  • Various TBM performance prediction models have been developed and most of them were considered penetration rate only. Despite the fact that some models have suggested equations and charts for estimating the utilization factor, but there are a few studies to estimate the TBM utilization factor. Utilization factor is affected by the type of TBM machine, operation, maintenance of machine, geological conditions, contractor experience and other factors. In this study, more than 100 case studies are analyzed to determine the relationship between the utilization factor and RMR, geological conditions, TBM types, tunnel length, and TBM diameter. Simple and multiple linear regression analysis are performed to develop predictive models for the utilization factor. The predictive model with explanatory variables of geological conditions, TBM types, tunnel length, and TBM diameter does not give a good correlation. The predictive models with explanatory variable of RMR give higher values of the coefficient of determination.

A Study on the Excavation Efficiency in Rock Mass Applied TBM Method (TBM공법을 적용한 암반현장에서의 굴착효율에 관한 연구)

  • Jeong, Hyeong-Sik;Lee, Seung-Ho;Park, Jong-Bae
    • Geotechnical Engineering
    • /
    • v.11 no.1
    • /
    • pp.51-62
    • /
    • 1995
  • The use of TBM has been rapidly increased in recent years since TBM has been introduced to Korea in 1985 and Korea came to occupy 27% of TBM holding ratio in the world. Despite a lot of experience, study on promoting the efficiency of TBM excavation is insufficient. The factors that influence the efficiency of excavation are the mechanical farttor geotechnical factor and management factor. The study on the efficiency of excavation has focused on the improvement of mechanical factor. But geotechnical factor is also very important and by this factor engineer can estimate the applicability of TBM. The purpose of this paper is to understand the effectiveness of TBM excavation for vari orts rock quality by analysing relations between rock quality and TBM excavation.

  • PDF

Analysis of Excavation Speed and Direct Construction Cost Based on the Operating Productivities of TBM Method Site (TBM 굴착 공법 적용 현장의 생산성 분석을 통한 암질별 굴진속도 및 직접공사비 분석)

  • Song, Young Sun;Park, Hong Tae
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.32 no.6D
    • /
    • pp.637-643
    • /
    • 2012
  • This research collected work drilling report of TBM method site developed by WRITH company to TBM equipment company in Germany and analyzed work operating productivity. Based Oil the data analyzed TBM operating productivity, This research derived and presented excavation speed (m/day) by TBM diameter (3.0m, 3.5m, 3.8m) and rock. Also, based on the excavation speed (m/day) by TBM diameter, This research estimated a day direct construction cost and total direct construction costs by applying a direct construction cost which spent on per 1m. When we perform a similar geological construction in the future, excavation speed and direct construction cost which were derived by TBM diameter and rock is thinking the effective utilization data to estimate construction cost and plan schedule management before the start of construction.

Analysis of Monthly Excavation Length Depending on Ground Condition and TBM Diameter (터널 보링 머신 공법 구경별 지질조건에 따른 월굴진장 분석)

  • Choi, Jae Jin;Park, Hong Tae
    • Journal of the Society of Disaster Information
    • /
    • v.10 no.1
    • /
    • pp.141-150
    • /
    • 2014
  • This study analyzed monthly excavation length and amount of time occupied by the work item based on drilling reports to record the entire work process of TBM tunnel site. TBM equipment( ${\varnothing}2.6m$, ${\varnothing}3.0m$, ${\varnothing}3.5m$, ${\varnothing}3.8m$) was developed by WIRTH company in Germany. In addition, This study analyzed rising expected monthly excavation length based on the lowest loss rate of operating shifts among the field of nine. Analysis results are confident to be a useful tool when Planning and Managing TBM method construction to the primary planning steps in the field similar to geological conditions and analyzed geological conditions.