• Title/Summary/Keyword: 설계시공일괄

Search Result 67, Processing Time 0.022 seconds

The Deduction of the Success Factor in Construction Projects by Design Build Methods (디자인 빌드(Design Build) 방식 건설 프로젝트의 성공요인 분석에 관한 연구 - 중.소규모 건설 프로젝트를 중심으로)

  • Lee, Chi-Joo;Kim, Sang-Ki;Kim, Jae-Jun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.5
    • /
    • pp.182-190
    • /
    • 2007
  • The minor construction companies in Korea have grown in focusing on the construction operation field. Also, soft field is vulnerable area, and there are not enough delivery systems, therefore, a capacity of the construction industry expansion and productivity is insufficient. Furthermore, the minor construction companies are losing their areas, because the major construction companies having numerous know-how and ample funds are competitive. As the construction industry are more larger and complicated, the design build methods might be increased in the construction industry and the minor construction companies could have more competitive. Hence, this paper analyzes the success factor in minor construction projects by design build methods focusing on instance $company^{\circ}{\phi}s$ case and survey, and critical success factor deduction and importance degree analysis of this factor using AHP analysis. In addition, this paper gives fundamental data how to manage the construction project effectively for minor construction $companies^{\circ}{\phi}s$ expansion in near future.

A Study on the Prevention for Differing Site Conditions Claims - Focused on Design-Build Project in Public Sector - (현장여건상이로 인한 클레임의 예방에 관한 연구 -공공부문의 설계$\cdot$시공일괄공사를 중심으로-)

  • Chung Myung-Woo;Lee Hwa-Young;Seo Yong-Chil;Hyun Chang-Taek
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.46-53
    • /
    • 2001
  • Differing Site Conditions('DSC') Claims among construction claims are on the increase as a direct result of the steady construction of Social Overhead Capital Facilities initiated by Government. As DSC claims generally became apparent during the intial stage of the construction project, it is necessary to timely review and study the proposal on the prevention of DSC claims because delayed settlement will incur more substantial damages to all parties concerned. This research is focused on the identification and analysis of the causes for DSC claims as applicable to design-build project in public sector and it presents the possible short term, medium and long term proposals on the improvement of causes related with DSC claims. The major results of this research are summarized as follows: 1. Improvement of contractor's tender practice 2. Contractor's division of responsibility on the site survey 3. Improvement of owner's exculpatory clause 4. Flexibility on the adjustment of contract amount The proposals stated above could be useful in resolving the DSC claims between owner and contractors.

  • PDF

The Investigation and Performance Assessment of the Design-Build Projects in Korea (국내 턴키/대안공사 실태조사를 통한 턴키/대안 입찰제도의 성과 분석)

  • Kim Sun-Hee;Kim Du Yeon;Park Sang Hyuk;Yeom Sang Min;Chae Myung Jin;Han Seung Heon
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2004.11a
    • /
    • pp.462-467
    • /
    • 2004
  • Design-build, which is defined as single source responsibility for design and construction, has been widely used in large public works since governmental formulation of measure for encouraging use of design-build in 1996. However, civic groups and small and medium sized enterprises are highlighting over-competition and unbalanced market shares of conglomerate in domestic design-bid market and insisting on decrease in the use of design-build and absorption into the lowest-price bidding. This study collected information about cost, schedule, quality, new technology adoption from 51 civil design-build projects and measured their performance.

  • PDF

Cost Performance Comparison of Project Delivery Methods in Public Sector - Focusing on Mediator Effect of Biddropping on Change Orders - (공공건설공사 발주방식에 따른 비용성과 실증비교 - 설계변경에 대한 낙찰률 매개효과를 중심으로 -)

  • Moon, Hyosoo;Lee, Hyun-Soo;Park, Moonseo;Lee, Bogyeong;Joo, Seonu;Son, Bosik
    • Korean Journal of Construction Engineering and Management
    • /
    • v.16 no.5
    • /
    • pp.86-96
    • /
    • 2015
  • According to previous research, the reason why Design-Build(hereinafter "DB") outperforms Design-Bid-Build(hereinafter "DBB") in terms of cost is due to less change orders(hereinafter "COs"). However, if biddropping was low for DBB resulting into increasing COs, then it would be wrong to conclude that DB is superior due to less COs. Therefore, in order to confirm such misjudgment, the attempt to comprehensively analyze biddropping, COs and delivery method was made as previous methods had analyzed either the relationship between delivery method and COs, or biddropping and COs. This research uses path analysis, which simultaneously compares effect sizes on COs according to delivery method and biddropping based on the project type, and validated the mediator effect. The research proved that DB outperforms DBB due to less COs cannot be validated as biddropping caused a mediator effect by intervening between the delivery method and COs for specific project types. Therefore, the mechanism of delivery method acts on COs through biddropping was established. Also, the identity of biddropping was investigated in a different perspective from previous research. Based on this result, this research is expected to help determine a delivery method by considering the mediator effect of specific projects and evaluate performance.

A Study on the Analysis of Change Order - Claim in Design-Build (설계시공 일괄입찰공사에서 설계변경 클레임요인의 분석에 관한 연구)

  • Lee, Sang-Beom;Hwang, Jae-Woo
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • 2006.11a
    • /
    • pp.301-304
    • /
    • 2006
  • The insistence of rights and interests in contract is being generalized by opening in construction market which is following F.T.A, internationally. Conditions of contract in construction have different specialities compared with other industries. Different conditions of contract should be established because of a specific character that is different from each construction, such as work, environment, circumference conditions. Although the order of Turn-key is being expanded by increasing construction scale and demanding hybrid function, the suitable regulations of contract are not settled. As a result, various factors of claim is occurring in Change Order-Claim, because they just obey a part of guide-line. This study suggests useful solutions in detail concerned with the main factor of Change Order-Claim by each D/B phases through practical sorting and analysis of the causes of Change Order-Claim.

  • PDF

A Reduction of Claims for Efficient Turn-key Project (효율적인 턴키사업 추진을 위한 클레임 저감방안)

  • Oh, Ye-Keun;Sohn, Jeong-Rak;Kim, Jae-Jun
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.3
    • /
    • pp.122-130
    • /
    • 2012
  • Currently, TK(Turn-key) projects have been implemented, the projects on TK basis still have shown several problems rather than its own merits as a bidding method. Increasing the number of claims being occurred during construction process of the projects is reality because of unclear notice of tender documents and conditions of the contract, design review system, and decision process of the qualified bidder. To establish desirable TK projects in domestic market, not only should resonable alternatives for carrying out design review system and selecting the bid winner be set up, but also proper standards for reforming irrational system of contract, bid, and notice of tender related to TK projects. This study is intended to reduce the number of claims and implement efficient projects of apartment construction on TK basis by identifying potential problems through analysis of claim examples of TK projects which have difficulties of revising contract agreement such as drawings and suggesting improvement methods for contract conditions and notice of tender docuements.

Analysis and Quantitative Estimation of Risk Factors of Design-Build (턴키 프로젝트에서 리스크요인 분석 및 정량적 평가)

  • Oh, Guk-Yeol;Lee, Young-Dai
    • Korean Journal of Construction Engineering and Management
    • /
    • v.13 no.5
    • /
    • pp.12-24
    • /
    • 2012
  • The Risks in undertaking a construction project comes from many sources and often involves many participants in the project. This study has identified various kinds of risks, assessed the risk factors quantitatively and suggested risk management method for response pertinent in Design Build(Turn Key)type of projects in Korean context. A questionnaire was designed comprising of 145 possible risks in all types of construction projects. The population from owner, consultant and contractor groups was asked to indicate the risks applicable in DB projects. 25 numbers of critical risks in DB projects were identified and further analyzed for reveling inherent relationship between them through factor analysis. Factor analysis revealed 8 risk factors in DB projects. Construction site related, contract related and design related risk factor consisted about 72% of total risk weight. It has been found out about 6%, while considering the mutual dependency, it is about 10% of total cost of DB project. Therefore, It is suggested that 6% to 10% of construction amount as contingency has to be made provision for risk responses in the DB projects.

Study on Local Buckling of District Heating Pipes Using Limit State Design (한계상태 설계법을 이용한 지역난방 열배관의 국부좌굴 연구)

  • Kim, Joo-Yong;Lee, Sang-Youn;Ko, Hyun-Il;Cho, Chong-Du
    • Transactions of the Korean Society of Mechanical Engineers A
    • /
    • v.34 no.12
    • /
    • pp.1829-1836
    • /
    • 2010
  • The district heating system distributes the heat generated from a cogeneration plant to wider locations. In this process, the district heating pipe (DHP) is subjected to internal and external loadings. The internal loadings are generally caused by the operating conditions such as water temperature and internal pressure. Frictional interactions between the pipes and the soil contribute to the external loadings. Thus, investigation of the mechanisms of failure of DHPs will help to guarantee both mechanical stability and heating efficiency. In this study, we investigate the local buckling of DHPs using limit state design (LSD). Two methods are considered: the use of the limit state for the width-thickness ratio and the use of the limit state for the strain. The results are used to confirm that the DHP is stable under local buckling. Finally, we suggest a minimum preheating temperature for avoiding local buckling.

Classification and Analysis of Characteristics of Changes in Apartment Landscape Work (아파트조경공사 설계변경의 유형분류와 특성분석)

  • Park, Chun-Soo;Park, Seung-Burm
    • Journal of the Korean Institute of Landscape Architecture
    • /
    • v.37 no.1
    • /
    • pp.28-42
    • /
    • 2009
  • In the wake of categorizing the design changes occurred during the period from 2004 till the first half of 2006 in Choongcheong province area, based on purpose and reason of design changes identified by the Korea National Housing Corp, it included 11 types such as the image of the apartment complex, scenic elements, consideration by the user, prevention of the defect, constructability, site conditions, incompatibility between the activities, superordinate standard, prevention of civic complaints, design details and others, along with 47 subordinate elements. And the evaluation intended to identify the corelation between the number and time of design change approval, frequency and scale of design change by type and the cost variations indicated that; firstly, enhancing the image of the apartment complex proved to be the main reason for design changes, accounting for 22% in terms of frequency and 54.9% in terms of cost variation. Secondly, the higher the increase in cost by design change aimed at improving the image of the complex, the lower the decrease in cost by design change for uncertain reasons, dubbed the inverse proportional relations, indicating that the design changes for uncertain reasons were mostly aimed at reducing the construction cost. Thirdly, with regard to the number of design change approval and the time of the initial approval, twice or less and 90 days or less before completion of the construction work, respectively, accounted for $52{\sim}53%$, indicating the design change deliberation and approval tended to have been carried out collectively in the form of ex post facto approval, which seemed to be attributable to the attempt of reducing the construction cost or budget problem, as a result of comparing with the cases in which the cost was reduced.

Effect of Multyparty Contract in IPD Project Case study of USA and Korean Projects (IPD 계약은 IPD 프로젝트의 필수조건인가 - 국내외 사례조사를 통하여 -)

  • Yoo, Seungeun;Kim, Taewan;Yu, Jungho
    • Korean Journal of Construction Engineering and Management
    • /
    • v.18 no.1
    • /
    • pp.3-16
    • /
    • 2017
  • Integrated project delivery (IPD) is suggested as an alternative to traditional delivery methods such as design-build (DB), design-bid-build (DBB), and construction management at risk (CMR). Many foreign research studies have approached IPD not only in the contractual aspect but also the work implementation method aspect. However, most research projects in Korea have focused on the contractual aspect of IPD for asserting that the characteristics are the critical matter. The Korean institutional and legal system does not permit the multi-party agreement; therefore, it is difficult to adopt IPD in Korea's construction industry. The researchers do not wait the system to be changed, but we do identify the possibility of adopting IPD in Korea in the perspective of work implementation method, except the contractual characteristics. Thus, the goal of this research is to identify one project that does not include IPD agreement but utilizes other IPD characteristics whose contractual results have similar performance to those that utilize all characteristics of IPD including agreement. This research is expected to enhance performance of the construction project in a Korean construction environment by embracing IPD characteristics as overcoming limits and bounds of the traditional delivery method.