Analysis and Quantitative Estimation of Risk Factors of Design-Build  

Oh, Guk-Yeol (고려개발)
Lee, Young-Dai (부경대힉교 토목공학과)
Publication Information
Korean Journal of Construction Engineering and Management / v.13, no.5, 2012 , pp. 12-24 More about this Journal
Abstract
The Risks in undertaking a construction project comes from many sources and often involves many participants in the project. This study has identified various kinds of risks, assessed the risk factors quantitatively and suggested risk management method for response pertinent in Design Build(Turn Key)type of projects in Korean context. A questionnaire was designed comprising of 145 possible risks in all types of construction projects. The population from owner, consultant and contractor groups was asked to indicate the risks applicable in DB projects. 25 numbers of critical risks in DB projects were identified and further analyzed for reveling inherent relationship between them through factor analysis. Factor analysis revealed 8 risk factors in DB projects. Construction site related, contract related and design related risk factor consisted about 72% of total risk weight. It has been found out about 6%, while considering the mutual dependency, it is about 10% of total cost of DB project. Therefore, It is suggested that 6% to 10% of construction amount as contingency has to be made provision for risk responses in the DB projects.
Keywords
design build; risk factors; risk response; factor analysis; contingency;
Citations & Related Records
Times Cited By KSCI : 1  (Citation Analysis)
연도 인용수 순위
1 Jannadi, O.A. and Almishari, S. (2003) "Risk Assessment in Construction" Journal of Construction Engineering and Management 129(5), pp. 492-500.   DOI   ScienceOn
2 Keytone, J. (2001), "Communication research: asking questions, finding answers", (2nd Ed.), McGraw-Hill.
3 Kim, T.W. and Joh, H.W. (2005), "Key barriers and their strategic responses to activate knowledge sharing in construction organization,", 1st International Conference on Construction Engineering and Management, 16-19 October, 2005, Seoul, Korea, CD-ROM, pp. 403-408.
4 Li, H., and Love, P.E.D., (1998), "Developing a theory of construction problem solving", Construction Management and Economics (Taylor and Francis), Vol.16, pp.721-727.   DOI   ScienceOn
5 Long Le-Hoai, Young Dai Lee, Guk Yeol Oh Cho(2010), Korean Journal of Construction Engineering and Management, Vol. 11 No.5, pp.84-94, "Modle for Predicting Success of Partnering in Vietnam:A Discriminant Analysis Approach".   DOI   ScienceOn
6 Toler, T.N. (2010), "Design-build vs. Traditional construction: risk and benefit analysis", Toler & Hanrahan LLC, USA, .
7 Walke, R., Topkar, V., Kabiraj, S(2010), "Risk Quantification Using EMV Analysis-A Strategic Case of Ready Mix Concrete Plants", IJCSIInternational Journal of Computer ScienceIssues, Vol.7, Issue5, .
8 Young Dai Lee, Nirmal Kumar Acharya,Jung Ki Kim(2007), "Korean Journal of Construction Engineering and Management", Vol. 8 No.2, pp246-262, "Investigation of Key Factors to measure on-site Performance of a Construction firm"
9 Bragg, T., (2001). "Three ways to deal with conflict in organizations," Peacemakers training, USA, .
10 Awakul, P., and Ogunlana, S.O., (2002), "The effect of attitudinal differences on interface conflicts in large scale construction projects: a case study," Construction Management and Economics, (T & F Spon), Vol. 20 (4), pp. 365-377.   DOI   ScienceOn
11 CEIM (Construction, Engineering and Infrastructure Management) (2010)," Risks in the construction of hydropower tunnels in Vietnam", < http://professionalprojectmanagement.blogspot.com/2009/11/risks-in-construction-of-hydropower.html>.
12 Cioffi, D.F. and Khamooshi, H. (2009) "A practical method of determining project risk contingency budgets" Journal of the Operational Research Society, vol. 60, pp. 565-571.   DOI   ScienceOn
13 Dikmen, I and Birgonul, T (2005), "An analytical process based model for risk opportunity assessment of international construction projects", Canadian Journal of Civil Engineering (in press).
14 Dikmen, I., Birgonul, M.T. and Han, S. (2007b) "Using fuzzy risk assessment to rate cost overrun risk in international construction projects", International Journal of Project Management vol. 25, 494-505.   DOI   ScienceOn
15 Hanscomb. Means (2004), "International Construction Intelligence", Vol. 16, No. 6, January/February.
16 Hsueh, S.L., Perng, Y.H., Yan, M.R. and Lee, J.R. (2007) "On-line multi-criterion risk assessment model for construction joint ventures in China" Automation in Construction 16, pp. 607-619.   DOI   ScienceOn
17 Irani, D.S. (2010), "Minimizing risks in Design/Build Projects: An owner's Engineer's view", PB world, .
18 이양규(2005), "토목공사 수주현황 분석을 통한 턴키 대안 입찰 제도의 문제점 및 개선방안 연구", 철도학회논문집 제8권 제5호, pp. 460-469.
19 오국열(2012)," 턴키 계약 프로젝트의 리스크요인 분석 및 대응 방안", 박사학위 논문
20 윤준선(2005), "건축턴키공사입찰안내서의문제점과개선방안에 관한연구", 중재연구, vol.15 No3, pp. 303-324.
21 이종수 (2003), "건축공사 턴키 발주방식의 개선 방안", 대한건축학회, Vol. 47 No.2, pp. 5-38.