• Title/Summary/Keyword: 기계식굴착

Search Result 33, Processing Time 0.022 seconds

Geotechnical investigation on causes and mitigation of ground subsidence during underground structure construction (터널 및 지중매설물 시공에 따른 지반함몰 발생 원인 및 대책에 대한 지반공학적 조사 연구)

  • Choi, Shin-Kyu;Back, Seung-Hun;An, Jun-Beom;Kwon, Tae-Hyuk
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.18 no.2
    • /
    • pp.143-154
    • /
    • 2016
  • This study investigated the occurrences, causes, and mitigation of the recent ground subsidence and underground cavity generation events in Korea. Two main causes of ground subsidence are (1) the soil erosion by seepage during tunneling and earth excavation and (2) the damage of underground pipes. The main cause of the soil erosion during tunneling was the uncontrolled groundwater flow. Especially, when excavating soft grounds using a tunnel boring machine (TBM), the ground near TBM operation halt points were found to be the most vulnerable to failure. The damage of underground pipes was mainly caused by poor construction, material deterioration, and differential settlement in soft soils. The ground subsidence during tunneling and earth excavation can be managed by monitoring the outflow of groundwater and eroded soils in construction sites. It is expected that the ground subsidence by the underground pipe damage can be managed or mitigated by life cycle analysis and maintenance of the buried pipes, and by controlling the earth pressure distribution or increasing the bearing capacity at the upper ground of the buried pipes.

Optimal Design for Minimizing Weight of Housing of Hydraulic Breaker (유압 브레이커의 중량 감소를 위한 하우징 최적설계)

  • Park, Gyu-Byung;Park, Chang-Hyun;Park, Yong-Shik;Choi, Dong-Hoon
    • Transactions of the Korean Society of Mechanical Engineers A
    • /
    • v.35 no.2
    • /
    • pp.207-212
    • /
    • 2011
  • A hydraulic breaker is an attachment installed at the end of excavator arm and is used for breaking. As per the authors' knowledge, there have been no research results on reducing the weight of the hydraulic breaker even though this weight reduction is very important for improving the performance of the excavator. In this study, we minimize the weight of the housing of the hydraulic breaker under normal operating conditions, while the maximum stress of the housing is lower than the allowable stress. A meta-model, which is generated by using the CAE results for the sampling design points determined by an orthogonal array, is used to solve the minimization problem. The weight of the housing according to the optimal design is found to be lower than the original weight by 4.8% while satisfying the constraint on the maximum stress.

Assessment of Hydraulic Drilling Data on Homogeneous Rock Mass (균질암반에서의 유압식 천공데이터 평가)

  • Kim, Kwang-Yeom;Kim, Chang-Yong;Kim, Kwang-Sik
    • Tunnel and Underground Space
    • /
    • v.18 no.6
    • /
    • pp.480-490
    • /
    • 2008
  • The drilling monitoring is a technique to assess rock mass properties by analyzing the mechanical quantities measured by drilling process. Since drilling survey can be conducted on real-time-basis for excavating blast holes or rockbolt holes, it may enables fast and quantitative prediction and evaluation of rock mass. Though a number of studies have been conducted on the drilling data, the selection of drilling parameters and numerical quantification of mechanical quantities or rock mass have not been well established yet. In this study, drilling tests were conducted with homogeneous rock specimen to identify drilling parameters and the relation of the drilling data. As a result, it is verified that above all drilling parameters, the percussion was the most important factor on the excavatability of hydraulic drilling.

A Study on Practicalization of Low Vibration New KINRECKER-II (미진동 발파용 New KINECKER-II 실용화에 관한 연구)

  • Jang, Seung-Ho;Park, Hee-Won;Lim, Jung-Hyuk;Lee, Chang-Yeop;Ahn, Bong-Do;Kang, Dae-Woo;Lee, Ha-Young
    • Explosives and Blasting
    • /
    • v.35 no.1
    • /
    • pp.43-52
    • /
    • 2017
  • Mountain and hill areas occupy by more than 70% in South Korea and Rock drilling should be applied in order to reduce noisy & vibration from massive civil engineering business such as road expansion, high-way construction, subway construction and construction of site renovation such as a newly-built & re-development of apartment, newly-built of high-rising building in downtown area. As Blasting noise & vibration such as vibration, noise, fly rock etc caused by blasting operation from large small scale construction occurs, neighboring residents who demand the compensation file a civil complaint so that the business reach a deadlock. As the excavation method for these areas, There are blasting of micro-vibration, mechanical excavation method(Rock splitter, Breaker etc), similar blasting method(plasma, gel fragmentation etc) to date. In this study, we are trying to find the feature & performance which get improved economic feasibility & construct ability through improving sympathetic detonation of New KINECKER-I used in blasting of micro-vibration & formulation and would provide convenience for use by introducing standard blasting pattern & construction method. Also, checked and confirmed all the blasting with connecting cap has been cleary detonated.

Suggestion of empirical formula between FPI and specific energy through analysis of subsea tunnel excavation data (해저 터널 굴진자료 분석을 통한 FPI와 비에너지의 경험식 제시)

  • Kim, Kyoung-Yul;Bae, Du-San;Jo, Seon-Ah;Ryu, Hee-Hwan
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.20 no.4
    • /
    • pp.687-699
    • /
    • 2018
  • The construction of subsea tunnel differs from that of inland tunnel because of high water pressure due to sea water level and difficulties to reinforce the ground under construction. Therefore, it is very important to prevent trouble in advance when the subsea tunnel is constructed. In this paper, we established lots of databases about characteristics of geological and mechanical parameters on the construction of subsea tunnel using micro slurry TBM which depth is about 60 m. The correlation analysis is conducted to confirm the effect of thrust, torque and RPM among the excavation database on the net penetration rate. Also, An empirical formula is suggested to predict the net penetration rate through the correlation analysis between FPI (Field Penetration Index) and specific energy from the subsea tunnel excavation database.

Development of penetration rate model and optimum operational conditions of shield TBM for electricity transmission tunnels (터널식 전력구를 위한 순굴진율 모델 개발 및 이를 활용한 쉴드TBM 최적운전 조건 제안)

  • Kim, Jeong-Ju;Ryu, Hui-Hwan;Kim, Gyeong-Yeol;Hong, Seong-Yeon;Jeong, Ju-Hwan;Bae, Du-San
    • Journal of Korean Tunnelling and Underground Space Association
    • /
    • v.22 no.6
    • /
    • pp.623-641
    • /
    • 2020
  • About 5 km length of tunnels were constructed by mechanized tunnelling method using closed type shield TBM. In order to avoid construction delay problems for ensuring timely electricity transmission, it is necessary to increase the prediction accuracy of the excavation process involving machines according to rock mass types. This is important to corroborate the project duration and optimum operation for various considerations involved in the machine. So, full-scale tunnelling tests were performed for developing the advance rate model to be appropriately used for 3.6 m diameter shield TBM. About 100 test cases were established and performed using various operational parameters such as thrust force and rotational speed of cuttterhead in representative uniaxial compressive strengths. Accordingly, relationships between normal force and penetration depth and, between UCS and torque were suggested which consider UCS and thrust force conditions according to weathered, soft, hard rocks. Capacity analysis of cutterhead was performed and optimum operational conditions were also suggested based on the developed model. Based on this study, it can be expected that the project construction duration can be reduced and users can benefit from the provision of earlier service.

A Case Study of Delay Analysis for E.P.B Shield TBM Method in Construction Site (E.P.B(Earth Pressure Balance) Shield TBM 공사의 공기지연 사례연구)

  • Kwak, Jun-Hwan;Park, Hyung-Keun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.29 no.6D
    • /
    • pp.737-743
    • /
    • 2009
  • Shield TBM, since it was employed for Suyoungman Bay riverbed tunnel of Busan Subway in 2000,has been increasingly adopted in Korea, and in line with growing popularity, the study on Shield TBM has been expanded. However the studies mostly focus on ground condition in a bid to estimate the advancement rate and develop the model for calculating the excavation efficiency, whereas the efforts to analyze the cause of delay and to develop the improvement measures have been neglected. Thus the studies were mostly intended to analyze the schedule slippage focusing on ground conditions, while the study on schedule behind due to equipment itself and related facilities have yet to be attempted in earnest. This study hence was aimed at evaluating the troubles and schedule slippage caused by mechanical elements such as shield TBM equipment and tools and ground conditions, making use of FMEA approach so as to analyze the risk of schedule delay by such elements, thereby proposing the preventive measures to deal with high-risk factors. So, this study suggest the solution to highly ranked trouble factor for the purpose of enhance the efficiency on Shield TBM.

A Numerical Study on the Rock Fragmentation by TBM Cutter Penetration (TBM 커터 관입에 의한 암석 파쇄의 수치해석적 연구)

  • 백승한;문현구
    • Tunnel and Underground Space
    • /
    • v.13 no.6
    • /
    • pp.444-454
    • /
    • 2003
  • Rock fragmentation technique by cutter penetration has widely been used in the mechanical tunnel excavation. Microcracks propagate and interact because of locally concentrated high stress induced by cutter penetration. which is caused by heterogeneity of rocks. In this study Weibull distribution function and degradation index are used to consider the strength heterogeneity of a rock and the degradation of rock properties after failure. Through the numerical analyses, it is shown that the lateral pressure has an important influence on the rock fragmentation. In the single cutter penetration, large chips are formed as lateral pressure increase. The cutter spacing is also an important factor that affects the rock fragmentation in the double cutter penetration. The fragmentation efficiency of the double cutter penetration is better when cutter spacing is 70 mm than 40 mm and 100 mm. From the results, it is expected that this study can be applied to a TBM tunnel design by understanding of chipping process and mechanism of rock due to cutter penetration.

Determination of Mode I Fracture Toughness of Rocks Using Wedge Splitting Test (쐐기 분열 시험을 이용한 암석의 모드 I 파괴인성 측정)

  • Ko, Tae Young;Kim, Taek Kon;Lee, Dae Hyuk
    • Tunnel and Underground Space
    • /
    • v.29 no.6
    • /
    • pp.523-531
    • /
    • 2019
  • In the applications of rock mechanics or rock engineering including drill and blast, drilling and mechanical excavation, the fracture toughness is an important factor. Several methods have been proposed to measure the fracture toughness of rocks. In this study, wedge splitting test specimen which is prepared with ease and tested under compression loading was used to obtain mode I fracture toughness of rocks. The equation of stress intensity factor through numerical analysis is proposed from the stress state of crack tip considering both vertical and horizontal loads due to the vertical load acting on the wedge. The validity of the wedge splitting test method was confirmed by comparing the mode I fracture toughness values obtained by the GD and SENB test specimens.

A Study on Earth Pressure Calculating Method about Shield TBM Tunnel Segments in the Rock (암반층에서 쉴드 TBM 터널 세그먼트의 작용하중 산정방법에 관한 연구)

  • Chun, Byungsik;Ki, Jungsu;Kang, Taehee;Kwag, Yunehyeong;Byun, Yoseph
    • Journal of the Korean GEO-environmental Society
    • /
    • v.15 no.5
    • /
    • pp.13-21
    • /
    • 2014
  • This study analyzed the differences in the analysis techniques through a comparative analysis of the various segment's modeling techniques of Shield TBM method and proposed reasonable modeling techniques. Also, this study suggested reasonable estimating methods of load to be applicable in the field through the load analysis and three-dimensional finite element analysis by estimating model of rock mass relaxation load. Estimating method of relaxation area by rock mass rating makes no odds of output in subgrade with high rock mass rating, but so the difference of output is large, that is judged to set conservative design off. In estimating result of rock mass relaxation area by three-dimensional analysis relaxation area of subgrade with low-grade soil was predicted to be positioned at medium-range of many methods, in case of designing segment in subgrade with low-grade soil it needs to actively review estimation of relaxation area through three-dimensional analysis reflecting mechanical tunnel excavation.