The Impacts of Reduced Labor Hours on the Construction Period and Cost of Tunnel Project

근로시간 단축에 따른 터널 공사의 표준 공기 및 공사비 영향 분석

  • Park, Taeil (Korea Institute of Civil Engineering and Building Technology) ;
  • Kim, Kyunghoon (Korea Institute of Civil Engineering and Building Technology) ;
  • Shin, Eun-Young (Korea Institute of Civil Engineering and Building Technology)
  • Received : 2018.10.18
  • Accepted : 2018.11.04
  • Published : 2019.03.31

Abstract

After the new standards for labor hours has been released, various problems come up in construction field, such as income reduction of employees, extension of construction period and increased construction cost. Although it is expected that the impact of the new standard on the construction industry is more worse than other industries form the view of productivity, not much works have been done to identify those impacts. Thus, this research proposes the standard construction processes, excavation cycle, and unit construction period for NATM tunnel project based on 'Construction Standard Production Rates.'The study also investigated the impact of reduced labor hours on the management of work crews, construction periods and costs of tunnel projects. The results showed that under the 52 labor hour standard, the construction periods for the excavation work and whole project was increased by 20% and 8.9%, respectively, but the construction costs for the excavation work and whole project was decreased by 1.4% and 0.6%, respectively.

주당 최장 법정 근로시간을 단축하는 내용의 '근로기준법 개정안'이 통과됨에 따라 근로시간 단축에 따른 근로자 소득감소, 공사기간 연장, 공사비 증가 등 다양한 문제가 발생하고 있다. 특히 다른 산업과 비교할 때, 생산성을 중시하는 건설 프로젝트의 경우 공종에 따라 주 52시간 근무제에 따른 영향의 정도가 더 클 것으로 예상되나 이에 대한 연구는 미흡한편이다. 이에 본 연구에서는 NATM 터널 공사를 대상으로 표준품셈 기반의 표준공정과 굴착 사이클 타임 그리고 공종별 단위 공기를 제시하고, 이를 통해 주 52시간 근무 적용에 따른 실제 작업조의 변화와 이에 따른 표준 공기 및 공사비의 영향을 분석하였다. 분석결과 굴착 공기와 총 공기는 각각 20%, 8.9% 증가하였으나, 굴착공사비와 총 공사비는 오히려 각각 1.2%, 0.5% 감소하는 것으로 확인되었다.

Keywords

GGRHC4_2019_v20n2_37_f0001.png 이미지

Fig. 1. Double shift based on 20 hours operation

GGRHC4_2019_v20n2_37_f0002.png 이미지

Fig. 2. Double shift based on 16 hours operation

Table 1. Construction processes of tunnel project

GGRHC4_2019_v20n2_37_t0001.png 이미지

Table 2. Designed one time length of drilling (MOLIT, 2016)

GGRHC4_2019_v20n2_37_t0002.png 이미지

Table 3. Drilling cycle time for each support type

GGRHC4_2019_v20n2_37_t0003.png 이미지

Table 4. One day length of drilling for 20 and 16 hour cases

GGRHC4_2019_v20n2_37_t0004.png 이미지

Table 5. Unit construction period for each processes

GGRHC4_2019_v20n2_37_t0005.png 이미지

Table 6. Application of proposed method to real world project

GGRHC4_2019_v20n2_37_t0006.png 이미지

Table 7. Comparison of construction period after labor hour reduction

GGRHC4_2019_v20n2_37_t0007.png 이미지

Table 8. The impacts of reduced labor hours on the construction period and cost

GGRHC4_2019_v20n2_37_t0008.png 이미지

References

  1. Lee, B.S., Kim, K.N., and Lee, M.J. (2015). "A Study on Normal Project Duration for Water Resource Project." Korean Journal of Construction Engineering and Management, KICEM, 16(1), pp. 35-43. https://doi.org/10.6106/KJCEM.2015.16.1.035
  2. Yoon, J.S., and Yu, I.H. (2017). "A Study on Estimating Normal Project Duration of Apartment Remo deling Project." Korean Journal of Construction Engineering and Management, KICEM, 18(2), pp. 12-20. https://doi.org/10.6106/KJCEM.2017.18.2.012
  3. Bae, K.W. (2017). "A Study on Standard Construction Process Management System fo rPrediction of Proper Construction Period of Subsea Tunnel." Korean Journal of Construction Engineering and Management, KICEM, 18(4), pp. 36-47. https://doi.org/10.6106/KJCEM.2017.18.4.036
  4. Kim, H.N., Kim, D.Y., Kim, D.Y., Jeong, S.C., and Huh, Y.K. (2018). "Optimum Construction Duration for Road Tunnel Excavation Works." JAIKSC, 34(4), pp. 59-64.
  5. Kim, K.H., and Lee, Y.L. (2018). "Trends and Prospects of Construction Engineers." Construction & Human Research Institute of Korea, pp. 1-13.
  6. Kwon, O.H., and Lee, J.S. (2002). "Introduction of 5 working days in construction industry." Construction Journal, pp. 19-20.
  7. Kim. H.R., Yu, I.H., Kim, K.R., and Shin, D.W. (2003). "An Influence Analysis of the Reduction of Working Time in Construction Sites." Journal of the Architectural Institute of Korea, 19(4), pp. 161-168.
  8. Lee, J.S. (2005). "The Analysis for Effects of the 40 Hours Workweek System on the Specialty Construction Industry." Journal of the Architectural Institute of Korea, 21(3), pp. 145-152.
  9. Ministry of Land, Infrastructure and Transport (2016). 'Guideline for designing national highway.'