Risk Factors Influencing the Delays on the Remodeling Construction Works - Focused on Office Building Projects -

리모델링 공사의 공기지연을 야기하는 리스크 요인 - 오피스 건축물을 중심으로 -

  • Received : 2018.04.26
  • Accepted : 2018.06.11
  • Published : 2018.08.20

Abstract

There have been frequent reports of schedule delays due to various risks of remodeling projects, which are different from new construction. Therefore, this study was carried out to analyze the risk factors inherent in the remodeling project and the likelihood of schedule delay occurrence in the remodeling construction work. To analyze the relationship between the risk factors and the likelihood of schedule delays of remodeling projects, (1) a prototype of the office building remodeling work was developed through the analysis of existing case and literature, (2) a questionnaire survey was conducted on 29 construction managers who have been or are currently conducting remodeling projects, and (3) after evaluating the reliability of the collected questionnaire results, the relationship between the two elements, which denotes (i) likelihood of schedule delays per each work, (ii) importance of risk factors, and (iii) risk factors affecting schedule delay in remodeling work, was suggested. Using the results of this study, it is expected to develop a plan for preventing the schedule delay of the office building remodeling work through control the risk factors that may cause schedule delays.

오피스 건축물의 리모델링 사업에서, 신축과는 다른 리모델링 사업의 다양한 리스크로 인해 공기가 지연되는 사례가 빈번하게 보고되고 있다. 이에 본 연구에서는 리모델링 프로젝트의 리스크 요인들과 리모델링 공사의 작업별 공기지연 발생가능성의 관계를 분석하고자 수행되었다. 리모델링 사업의 경험이 있는 29명의 전문가 면담결과의 과학적 통계적 분석을 통해, 리모델링 사업의 리스크 요인과 그로 인한 작업별 공기지연 가능성을 크게 3가지 측면에서 분석하였다. 즉, (i) 리모델링 공사의 작업별 공기지연 가능성, (ii) 리모델링 공사의 리스크 요인별 중요도, (iii) 리모델링 공사의 공기지연에 영향을 미치는 리스크 요인 등 세가지 분석결과를 제시하였다.

Keywords

References

  1. Cho KM, Yoon YJ. Decision support model for determining cost-effective renovation time. Journal of Management in Engineering. 2016 May;32(3):04015051-1-9.
  2. Shin YS, Cho KM, Kim JY. Decision support process model for energy efficient remodeling projects focused on building envelope and renewable energy systems. Korean Journal of Construction Engineering and Management. 2015 May;16 (3):91-100. https://doi.org/10.6106/KJCEM.2015.16.3.091
  3. Kim JW, Cho KM, Kim TH, Yoon YJ. Predicting the monetary value of office property post renovation work. Journal of Urban Planning and Development. 2018 Jun;144(2):04018007-1-9.
  4. Kim JS, Cho KM, Kim TH. Factors determining the price of remodeled multi-family housing. Korean Journal of Construction Engineering and Management. 2016 May;17(3):13 -22. https://doi.org/10.6106/KJCEM.2016.17.3.013
  5. Junghans, L. Sequential equi-marginal optimization method for ranking strategies for thermal building renovation. Energy and Buildings. 2013 Oct;65:10-18. https://doi.org/10.1016/j.enbuild.2013.05.028
  6. Lee SB, Son BS. An analysis on characteristics and risk factors of the remodeling project. Korean Journal of Facility Management. 2013 Dec;8(2):5-11.
  7. Lee D. Cha H. A probabilistic risk-based cost estimation model for initial-stage decision making on apartment remodeling projects. Korean Journal of Construction Engineering and Management. 2016 Mar;17(2):70-9. https://doi.org/10.6106/KJCEM.2016.17.2.070
  8. Hong SW, Ahn YS. A study on countermeasures for the strategic risk management of remodeling in construction projects. Journal of the Architectural Institute of Korea Structure & Construction. 2004 Nov;20(11):153-60.
  9. Cho KM, Kim TH. Effect of office building remodeling project characteristics on the occurrence of schedule delay risk factors. Korean Journal of Construction Engineering and Management. Forthcoming 2018.
  10. Hair J, Black W, Babin B, Anderson R, Tatham R. Multivariate data analysis. 6th ed. New Jersey: Pearson Education, Inc.; 2005. 816 p.