Risk Factors Influencing the Delays on the Remodeling Construction Works - Focused on Office Building Projects -  

Cho, Kyu-Man (School of Architecture, Chosun University)
Kim, Tae-Hoo (School of Architecture, Chosun University)
Publication Information
Journal of the Korea Institute of Building Construction / v.18, no.4, 2018 , pp. 385-394 More about this Journal
Abstract
There have been frequent reports of schedule delays due to various risks of remodeling projects, which are different from new construction. Therefore, this study was carried out to analyze the risk factors inherent in the remodeling project and the likelihood of schedule delay occurrence in the remodeling construction work. To analyze the relationship between the risk factors and the likelihood of schedule delays of remodeling projects, (1) a prototype of the office building remodeling work was developed through the analysis of existing case and literature, (2) a questionnaire survey was conducted on 29 construction managers who have been or are currently conducting remodeling projects, and (3) after evaluating the reliability of the collected questionnaire results, the relationship between the two elements, which denotes (i) likelihood of schedule delays per each work, (ii) importance of risk factors, and (iii) risk factors affecting schedule delay in remodeling work, was suggested. Using the results of this study, it is expected to develop a plan for preventing the schedule delay of the office building remodeling work through control the risk factors that may cause schedule delays.
Keywords
office building remodeling projects; risk factors of remodeling project; schedule delays of remodeling work;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 Cho KM, Yoon YJ. Decision support model for determining cost-effective renovation time. Journal of Management in Engineering. 2016 May;32(3):04015051-1-9.
2 Shin YS, Cho KM, Kim JY. Decision support process model for energy efficient remodeling projects focused on building envelope and renewable energy systems. Korean Journal of Construction Engineering and Management. 2015 May;16 (3):91-100.   DOI
3 Kim JW, Cho KM, Kim TH, Yoon YJ. Predicting the monetary value of office property post renovation work. Journal of Urban Planning and Development. 2018 Jun;144(2):04018007-1-9.
4 Junghans, L. Sequential equi-marginal optimization method for ranking strategies for thermal building renovation. Energy and Buildings. 2013 Oct;65:10-18.   DOI
5 Lee SB, Son BS. An analysis on characteristics and risk factors of the remodeling project. Korean Journal of Facility Management. 2013 Dec;8(2):5-11.
6 Lee D. Cha H. A probabilistic risk-based cost estimation model for initial-stage decision making on apartment remodeling projects. Korean Journal of Construction Engineering and Management. 2016 Mar;17(2):70-9.   DOI
7 Hong SW, Ahn YS. A study on countermeasures for the strategic risk management of remodeling in construction projects. Journal of the Architectural Institute of Korea Structure & Construction. 2004 Nov;20(11):153-60.
8 Cho KM, Kim TH. Effect of office building remodeling project characteristics on the occurrence of schedule delay risk factors. Korean Journal of Construction Engineering and Management. Forthcoming 2018.
9 Hair J, Black W, Babin B, Anderson R, Tatham R. Multivariate data analysis. 6th ed. New Jersey: Pearson Education, Inc.; 2005. 816 p.
10 Kim JS, Cho KM, Kim TH. Factors determining the price of remodeled multi-family housing. Korean Journal of Construction Engineering and Management. 2016 May;17(3):13 -22.   DOI