Orders Status Analysis on the Successful Bidder Decision Method of Civil Turnkey.Alternative Tendering Construction

개선된 낙찰자 결정방식에 의한 토목 턴키.대안입찰공사 수주현황 분석

  • Park, Hong Taea (Department of Civil Engineering, Kongju National University) ;
  • Lee, Yang Kyu (Department of Civil Environmental Daelim University)
  • Published : 2013.06.30

Abstract

From 2010 years to 2013, the selection method of successful bidder has been changed design suitable lowest method, comprehensive evaluation method(bid price adjustment, design score adjustments, weight standards), fixed amount best design method. Therefore this study was presented by analyzing the impact on the domestic construction industry according the way to determine the successful bidder, the evaluation order method and the operational issues through the analysis of order status, order number, results of acceptance an order, success rate range, results of acceptance an order according to weight success rate, results of acceptance an order by work type and order institution of a turnkey alternative tendering construction performed in domestic civil part.

2010년부터 2013년까지 낙찰자 선정방식이 설계적합 최저가방식, 종합평가방식(입찰가격 조정, 설계점수조정, 가중치기준), 확정금액 최상 설계방식으로 변경되었다. 따라서 이 연구는 국내에서 시행된 변경된 방식에 의한 토목부분 턴키 대안입찰공사의 발주현황, 건수, 수주실적, 낙찰률 범위, 공종별 발주기관별 수주실적, 가중치 낙찰자 수주실적 등의 분석을 통해 국내 낙찰자 결정방식이 건설산업에 미치는 영향, 심의 발주방식 및 운영상의 문제점을 분석하여 제시하였다.

Keywords

References

  1. Adrian, James J.(1981), The Construction Management Process. Reston Publihing Co. Inc.
  2. Construction & Economy Research Institute (2011), turnkey alternative bid accept ratio. Resources
  3. Jang HS (2012), A Study on Strategies for Enhancing Transparency of Domestic Construction Industry
  4. Lee SH (2004), the correlation .of the government construction pass rate and profitability, Construction and Transportation, pp.50-57
  5. Lee YK, Kang LS, Park JH, Jeon SC (2005), Improvement of Turn-key Contract System through the Analysis of Present Ordering Condition in Civil Engineering Projects, Journal of the Korean Society for Railway, No. 8, pp.460-469
  6. Foreign Cases. Journal of the Korean Society of Civil Engineers, No.3, pp.235-237
  7. Lee YK, Kang LS (2007), Improvement of Bidding Procedure and Design Review System of Turnkey and Alternative-design Contracts. Journal of the Korean Society of Civil Engineers, No. 2, pp.491-497
  8. Lee YK, Park HT (2011), Improvement of Procedures on Design Deliberation System for Turnkey and Alternative-Design Contracts. Journal of the Korean Society for Railway, No.14, pp31-38
  9. Lee SH(2005), turnkey alternative Tendering Market Trends, Construction Industry Institute
  10. Lee YS(2011), turnkey bid adequacy, Korean Construction News
  11. Molenaar, K. R.(1999) Public-Sector Design/Build Evolution and Performance. Journal of Management in Engineering, Vol. 15, No.2, pp.54-62
  12. Ministry of Land, Transport and Maritime Affairs (2009(b)), criteria of large-bidding method deliberation. Technology Security Administration, the construction environment
  13. Ministry of Land, Transport and Maritime Affairs (2009), business tips on turnkey alternative bid Institution. Technology Security Administration, the construction environment
  14. Ministry of Land, Transport and Maritime Affairs (2009(c)), Batch bid designed eligible deliberation and valuation plan, echnology Security Administration, the construction environment