Analysis of Delay Factors Based on Importance of Construction Subject-classified in Apartment Finishing Works

공동주택 마감공사 공사주체별 작업지연 요인 분석

  • Lee, Seung-Hoon (Department of Sustainable Architectural Engineering, HanYang University) ;
  • Kim, Yong-Man (Department of Architectural Engineering, HanYang University) ;
  • Kim, Ju-Hyung (Department of Architectural Engineering, HanYang University) ;
  • Kim, Jae-Junn (Department of Architectural Engineering, HanYang University)
  • Received : 2011.01.19
  • Accepted : 2011.02.16
  • Published : 2011.02.20

Abstract

The ultimate goal of construction is to complete the given work in the most economical and safest way within the required construction period while meeting the quality standards specified in the design drawing. There are a few characteristics of finish work. First, executed in subdivided processes, finish work involves a very diverse and complex structure. Second, there are no criteria for each segmented process with regard to the appropriate time of input. Third, it is not very necessary to set priorities for lead and lag works. This study intends to provide information on the completion of a project in accordance with the required duration by setting priorities in the delay of each detailed process of finish work to minimize delay in finish work. In this study, finish work is divided into wet work and other types of finish work, and the importance of each process is classified based on the given details of each process. In addition, the study employs a survey to analyze delay factors of a designer, a constructor, and a supplier. Using the survey results, the study sets priorities in delay of final work to provide information on the completion of an apartment project within the planned construction period.

건설 공사의 궁극적인 목표는 주어진 공사를 요구된 공사기간내에 설계도서에 명시된 품질 기준을 만족시키면서 가장 경제적이고 안전하게 완성하는데 있다. 마감공사는 공종이 세분화되어 매우 다양하고 복잡한 구조를 가지고 있으며 적정 투입 시점에 대한 세부 공종별 기준이 없고, 선후행 작업간의 우선 순위의 정립의 필요성이 약한 것이 특징이다. 본 연구는 마감공사 작업지연을 최소화하기 위하여 마감공사 세부 공종별 작업지연 우선 순위를 선정하여 소요 공기에 맞추어 프로젝트를 완료할 수 있는 정보를 제공하는 것이 목적이다. 본 연구에서 마감공사를 습식공사와 기타 마감공사로 나누어 각 공종별 내역을 기반으로 중요도를 분류하고, 설문을 통해 설계자, 시공자, 협력업체의 작업지연 요인을 분석하여 최종 작업지연 우선 순위를 선정하여 계획 공사기간 내에 공동주택 프로젝트를 완료할 수 있는 정보를 제공하는데 목적이 있다.

Keywords

References

  1. Kim MS, Kwon OC, Kim KH. Time Management of Construction, Ki Moon Dang Publishing;2001.
  2. Lee JD. A Work Interference Management Model for Apartment Building Finish Works[MA dissertation]. Seoul: Chung-Ang University;2009.
  3. Kim YJ, Han JY, Shin DW, Kim KR, Kim CD, Seo SW. A Tact Planning and Scheduling Process Model for Reduction of Finishing Work Duration in Building Construction Projects, Journal of the Architectural Institute of Korea 2003;19(1):161-7.
  4. Lee WS. A Development Management and Analysis of Delay Claim Risk Factor for Finish Work Schedule in Apartment Housing Projects[MA dissertation]. Seoul: Han-Yang University;2004.
  5. Bramble, B. B. and Callahan, N. T. Construction Delay Claim, 2nd, John Wiley & Sons; 1992.
  6. Park CW, Yun SH. A Case Study on Reason Analysis for Schedule Delay of Apartment House, Journal of the Korea Institute of Building Construction 2009;9(1):89-6. https://doi.org/10.5345/JKIC.2009.9.1.089
  7. Han JK, Chin SY, Kim YS. An Analysis on Delay factors of Major Trades in Apartment Housing Projects, Journal of the Architectural Institute of Korea 2003;19(3):163-8.
  8. Ji KC, Yu JH, Kim CD. The Schema of Work Delay Analysis by Input Factor in Construction, Journal of the Architectural Institute of Korea 2006;22(11):181-8.
  9. Jung JH, Lee G, Hong GH, Lee CH. An Analysis on Difficulties and Delay Factor for the Development and Application of Technologies for Reduction of Construction Duration, Journal of the Architectural Institute of Korea 2010;26(1):121-8.
  10. Kim SJ, Shin KC, Kim JJ. Analyzing Influential Factors in the Procurement Process of Finishing Materials for Building Construction Site, Journal of the Architectural Institute of Korea 2003;19(9):155-8.
  11. Han JG, Kwon SW, Cho MY. Development of Material Management System and Field Tests Using RFID Technology on High-Rise Building Construction, Journal of the Architectural Institute of Korea 2006;22(10):121-8.
  12. Han JH, Kim DY, Lee HK. A Study on Constraint Analysis Checklist of Constrcution Project, Proceeding of Annual Conference of the Architectural Institute of Korea Structure & Construction 2008;(1):437-6.
  13. Said A. Assaf, Mohammed Al-Khalil, Muhammad Al-Hazmi. Cause of Delay in Large Building Construction Projects, ASCE, Journal of Construction Engineering and Management 1995;11(2):45-6.
  14. Saied Kartam. Generic Methodology for Analyzing Delay Claims, ASCE, Journal of Construction Engineering and Management 1999;125(6):409-11 https://doi.org/10.1061/(ASCE)0733-9364(1999)125:6(409)

Cited by

  1. A Study on the Accuracy of BIM-based Quantity Take-Off of Apartment Interior vol.14, pp.1, 2013, https://doi.org/10.6106/KJCEM.2013.14.1.012
  2. Developing a construction duration estimation model to ensure the safety in apartment housing construction sites 2018, https://doi.org/10.1007/s12205-017-0605-y