Abstract
Linear scheduling method limits to present works of work breakdown structure as a form of lines and was often developed manually. In other words, linear schedule could not utilize activity, work breakdown structure, and etc. information of network schedule such as CPM(Critical Path Method) and has been used only for reporting or confirming construction master plan. Therefore, it is necessary to develop system which can automatically generating the linear schedule based on the network schedule having many accumulated and useful construction schedule information. Thus, this research has an effort to establish data process model, data flow diagram, and data model in order to make linear schedule. In addition, this research addresses the system solution structure, user interface class diagram and logic diagram, and data type schema. The results of this paper can be used as a preliminary research for developing linear schedule generating system prototype by utilizing the network schedule information.
기존의 선형 공정계획은 마스터 스케쥴과 같이 작업분류체계의 대분류 레벨의 작업을 사선의 형태로 표현하는 데 국한하고 수작업으로 작성하였다. 즉, 네트워크 공정표의 정보를 활용하지 못하고 독립적으로 선형 공정표를 작성하여 보고용 또는 전체 공정계획 확인용으로 사용하고 있는 실정이다. 따라서 기존에 축적된 자료가 많은 네트워크 공정표를 기반으로 선형 공정표를 자동으로 생성할 수 있는 시스템 개발이 필요하다. 이에 본 연구는 선형 공정표 구현을 위한 데이터 프로세스 모델, 데이터 플로 다이어그램, 데이터모델을 구축하고 시스템 프로토 타입의 시스템 솔류션 구조, 클래스 다이어그램, 데이터 타입스키마를 개발하고자 한다. 즉, 네트워크 공정표를 선형 공정표로 변환하기 위한 시스템 프로토타입 개발의 선행 연구를 수행하는 것이 본 연구의 목적이다.