Case Studies: Schedule Delay Factors and Delay Prevention Program for Concrete Frame Works in Apartment Construction Project

사례분석을 통한 아파트 골조공사의 공기지연 요인 도출 및 개선방안

  • Cho, Tae-Jea (Department of Architectural Engineering, Dongguk University) ;
  • Choi, Jong-Soo (Department of Architectural Engineering, Dongguk University)
  • Received : 2010.10.29
  • Accepted : 2010.12.01
  • Published : 2011.02.20

Abstract

Project delay is one of the most crucial impact factors in the construction process from a schedule and cost management perspective. This study focused on analyzing the causes of concrete frame work delay in the apartment construction project. According to the analysis of project cost composition, the direct cost of concrete works was highest in most samples. Actual delays of concrete works were analyzed for the six different construction components. Causes of delay were grouped into two categories; preconstruction and construction phases and these two groups were further divided into sub-groups. Analysis results revealed that the most significant delay was occurred in the 1st. floor concrete skeleton work. For each delay factor, implications of delay as well as suggestion(s) for reducing the possibility of schedule delay are provided.

건설프로젝트에서 공기지연은 공정 및 공사비 관리 측면에서 핵심 관리사항에 해당된다. 본 연구는 아파트 건설공사에서 직접비의 상당부분을 차지하는 골조공사를 대상으로 공사부위별 공기지연 수준을 분석하고 대책을 제시한 실증연구로 10개 현장의 공사비 비중분석 결과에 기반하여 골조공사에서 지연이 발생하는 부위의 순위, 원인 등을 분석하였다. 분석결과 1층 골조공사에서 가장 큰 지연이 발생하는 것으로 나타났으며 지연원인을 다양한 분류에 의거하여 분석하고 대책을 제시하였다.

Keywords

References

  1. Kim TW, Lee JS. Construction delay analysis utilizing system thinking approach. Journal of the architectural institute of Korea(structure & construction). 2006;22(9):131-138.
  2. Korean commercial arbitration board. Case book of arbitration precedents Vol. 13. KR, Seoul:Korean commercial arbitration board editors; 2003.
  3. Koo JM, Lee JS. Construction delay analysis method considering productivity. Journal of the architectural institute of Korea(structure & construction). 2004;20(4);153-160.
  4. AURIC(Architecture & Urban Research Information Center) [Internet]. The dictionary constructional terms. Available from; http://www.auric.or.kr/User/Dict/DictMain.aspx
  5. Callahan MT, Quackenbush DG, Rowings JE. Construction project scheduling. NY. McGraw-Hill; 1992
  6. Kartman S. Generic methodology for analyzing delay claims. Journal of construction engineering and management. 1999;125(6):409-419. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:6(409)
  7. Han SH, Yun SM, Lee SH. Exploring delays of the mega construction project : the case of korea high speed railway. The KSCE journal of civil engineering 2006;26(5):839-848.
  8. Chan DWM, Kumaraswamy MM. A comparative study of causes of time overruns in Hong Kong construction projects. International journal of project management. 1997;15(1):55-63. https://doi.org/10.1016/S0263-7863(96)00039-7
  9. Nasir D, Mccabe B, Hartono L. Evaluating risk in construction-schedule model(eric-s):construction schedule risk model. Journal of construction engineering and management, 2003;129(5):518-527. https://doi.org/10.1061/(ASCE)0733-9364(2003)129:5(518)
  10. Assaf SA, Al-Khalil M, Al-Hazmi M. Cause of delay in large building construction projects. Journal of construction engineering and management. 1995;11(2):45-50.
  11. Elinwa AU, Joshua M. Time-overrun factors in Nigerian construction industry. Journal of construction engineering and management. 2001;127(5):419-425. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:5(419)
  12. Majid MZ, Mccaffe R. Factors of non-excusable delays that influence contractors' performance. Journal of management in engineering. 1998;14(3):42-49.
  13. Jung JH, Lee K, Hong KH, Lee CH. An analysis on difficulties and delay factors for the development and application of technologies for reduction of construction duration. Journal of the architectural institute of Korea(structure & construction). 2010;26(10):121-128.
  14. Lee JS. Delay analysis using learning effect and linear scheduling in construction. Journal of the architectural institute of Korea(structure & construction). 2008;24(5):185-192.
  15. Kim KH, Kim KH, Lee YS, Kim JJ. A study about influence of risk factors in relation to construction cost increase and schedule delay on the reinforced concrete construction. Journal of the architectural institute of Korea(structure & construction). 2008;24(5):165-172.
  16. Lee JS. Delay analysis using linear schedule in construction. Journal of the architectural institute of Korea(structure & construction). 2007;23(8):213-220.
  17. Lee JS. Modified delay analysis considering production rates. Journal of the architectural institute of Korea(structure & construction). 2006;22(5);203-210.
  18. Kim YJ, Hong JS, Kim KR, Shin DW. An analysis method for the concurrent delay using delay section concept. Journal of the architectural institute of Korea(structure & construction). 2004;20(6):141-148.
  19. Kim YJ, Lee WC, Hong JS, Kim KR, Shin DW. A case study on delay analysis methods in the construction project. Korea journal of construction engineering and management 2004;15(6):129-137.
  20. Kwon JM, Lee JS. Construction delay analysis method; hierarchical planning process approach, Journal of the architectural institute of Korea(structure & construction). 2003;19(8):121-128.
  21. Lee SB, Lee YM. Improvement for liquidated damages according to the delay of domestic construction project. Journal of the architectural institute of Korea(structure & construction). 2003;19(5):145-152.
  22. Han JK, Chin SY, Kim YS. An analysis on delay factors of major trades in apartment housing projects. Journal of the architectural institute of Korea(structure & construction). 2003;19(3):163-170.
  23. Lyu HG, Yu JH, Lee HS. A method of calculating schedule delay considering lost productivity. Journal of the architectural institute of Korea(structure & construction). 2002;18(10):117-125

Cited by

  1. Developing a construction duration estimation model to ensure the safety in apartment housing construction sites 2018, https://doi.org/10.1007/s12205-017-0605-y
  2. Integrated CO2, cost, and schedule management system for building construction projects using the earned value management theory vol.103, 2015, https://doi.org/10.1016/j.jclepro.2014.05.031