Calculation and field measurement of earth pressure in shield tunnels under the action of composite foundation

  • Chi Zhang;Shi-ju Ma;Yuan-cheng Guo;Ming-yu Li;Babak Safaei
    • Geomechanics and Engineering
    • /
    • 제34권1호
    • /
    • pp.17-27
    • /
    • 2023
  • Taking a subway shield tunnel in a certain section of Zhengzhou Metro Line 5 as an example, the field tests of shield cutting cement-soil monopile composite foundation were carried out. The load and internal force of the tunnel lining under the action of composite foundation were tested on-site and the distribution characteristics and variation laws of earth pressure around the tunnel under the load holding state of the composite foundation were analyzed. Five different load combinations (i.e., overburden load theory + q0, Terzaghi's theory + q0, Bierbaumer's theory + q0, Xie's theory + q0, and the proposed method (the combination of compound weight method and Terzaghi's theory) + q0) were used to calculate the internal force of the tunnel structure and the obtained results were compared with the measured internal force results. The action mode of earth pressure on the tunnel lining structure was evaluated. Research results show that the earth pressure obtained by the calculation method proposed in this paper was more consistent with the measured value and the deviation between the two was within 5%. The distribution of the calculated internal force of the tunnel structure was more in line with the distribution law of field test data and the deviation between the calculated and measured values was small. This effectively verified the rationality and applicability of the proposed calculation method. Research results provided references for the design and evaluation of shield tunnels under the action of composite foundations.

3차원 수치해석을 이용한 연약대 방향에 따른 터널 거동 특성 평가 (Assessment of Tunnel Displacement with Weak Zone Orientation using 3-D Numerical Analysis)

  • 임성빈;정해근;서용석
    • 지질공학
    • /
    • 제19권1호
    • /
    • pp.43-50
    • /
    • 2009
  • 터널 굴착 중 지반에 존재하는 연약대의 방향 특성에 따른 거동 및 응력 분포 특성을 3차원 수치해석을 이용하여 정량적으로 평가하였다. 수치모델에서 연약대의 방향은 RMR의 취약 불연속면에 대한 보정인자를 기준으로 설정되었으며, 위치는 각 방향 조건에 대하여 연약대가 천단부 상부 1D, 천단부, 막장 중앙부를 지나는 경우로 설정되었다. 지반정수는 현장 계측변위를 기반으로 하는 역해석을 통해 산정하였다. 최종적으로 터널 천단부에서 발생하는 변위의 크기를 기반으로 연약대 방향 및 위치 조건에 따른 영향도를 평가하여 5등급으로 분류하였다.

회전발사체 롤댐핑 특성에 관한 고속 유동장 실험연구 (An Experimental Study on Roll-Damping Characteristics of a Spinning Projectile at High Speed Region)

  • 오세윤;이도관;김성철;김상호;안승기
    • 한국항공우주학회지
    • /
    • 제39권10호
    • /
    • pp.912-918
    • /
    • 2011
  • 본 연구의 목적은 풍동실험을 통해 회전발사체에서 발생하는 동적 롤댐핑 특성을 실험적으로 측정하는데 있었으며, 이를 위해 약 12,000 rpm으로 회전하는 회전발사체 실험모형에 작용하는 롤댐핑 특성의 측정을 위한 고속풍동실험을 국방과학연구소 삼중음속풍동에서 수행하였다. 실험시의 마하수는 0.7~1.05까지의 천음속 영역이었으며 이때의 받음각 구간은 -4~+10 deg이었다. 풍동실험 측정기법의 유효성 평가를 위해 동일형상 모형에 대해 기 수행하였던 롤댐핑 측정결과와의 비교검토를 수행하였다.

Main challenges for deep subsea tunnels based on norwegian experience

  • Nilsen, Bjorn
    • 한국터널지하공간학회 논문집
    • /
    • 제17권5호
    • /
    • pp.563-573
    • /
    • 2015
  • For hard rock subsea tunnels the most challenging rock mass conditions are in most cases represented by major faults/weakness zones. Poor stability weakness zones with large water inflow can be particularly problematic. At the pre-construction investigation stage, geological and engineering geological mapping, refraction seismic investigation and core drilling are the most important methods for identifying potentially adverse rock mass conditions. During excavation, continuous engineering geological mapping and probe drilling ahead of the face are carried out, and for the most recent Norwegian subsea tunnel projects, MWD (Measurement While Drilling) has also been used. During excavation, grouting ahead of the tunnel face is carried out whenever required according to the results from probe drilling. Sealing of water inflow by pre-grouting is particularly important before tunnelling into a section of poor rock mass quality. When excavating through weakness zones, a special methodology is normally applied, including spiling bolts, short blast round lengths and installation of reinforced sprayed concrete arches close to the face. The basic aspects of investigation, support and tunnelling for major weakness zones are discussed in this paper and illustrated by cases representing two very challenging projects which were recently completed (Atlantic Ocean tunnel and T-connection), one which is under construction (Ryfast) and one which is planned to be built in the near future (Rogfast).

다점식 피토관의 효율적인 교정에 대한 연구 (Investigation on the Effective Calibration of Annubar)

  • 최용문;최해만;최지철;홍경기;한상우;김웅선;전세종
    • 대한기계학회논문집B
    • /
    • 제30권4호
    • /
    • pp.373-380
    • /
    • 2006
  • Annubar is one of popular tools to measure the exhausted gas flow rate from the stacks. For the accurate monitoring of the amount of discharged pollutants, calibration of annubar is very important. Calibration of annubar has been carried out in a wind tunnel. When the length of annubar is longer than the test section size of wind tunnel, it is very difficult to find out typical value of annubar coefficients. So, a measurement technique to calibrate annubar longer than the size of the test section of wind tunnel must be developed. In the present study, an experiment is performed to measure the annubar coefficients in such a limited size of the wind tunnel. The experimental annubar coefficient by using a partial blocking technique is very close to the annubar coefficient of normal condition.

FLAC을 이용한 직접법 역해석 소프트웨어의 개발과 검증 (Verification of Direct Back Analysis Software Using FLAC as a Subroutine)

  • 김치환
    • 터널과지하공간
    • /
    • 제15권5호
    • /
    • pp.344-351
    • /
    • 2005
  • 터널 시공 중 계측한 변위 등으로 터널의 안정성을 재평가하기 위해 심플렉스 이론을 기초로 직접법 역해석 소프트웨어를 개발하고 그 정확성을 12 가지 조건에서 검증하였다. 이 소프트웨어는 FLAC을 부프로그램(subroutine)으로 하고 그것에 내장된 전산언어를 이용한 것이다. 변위 수 3-240개로 구성된 여러 가지 변위조합에 대한 역해석 검증결과 터널 주변의 계측위치와 입력변위의 개수에 관계없이 암반의 탄성계수와 초기응력 비를 구할 수 있었고 반복계산을 위한 출발값의 탄성계수와 초기응력 비에 관계없이 정해에 안정적으로 수렴되는 것을 확인하였다.

저속풍동 시험부 속도교정에 관한 실험적 연구 (An Experimental Study of Test Section Velocity Calibration for Low-Speed Wind Tunnel)

  • 오세윤;이종건;김성철;김상호;안승기
    • 한국항공우주학회지
    • /
    • 제40권3호
    • /
    • pp.230-236
    • /
    • 2012
  • 본 연구의 목적은 풍동 시험부의 속도산출에 필요한 속도측정시스템용 교정계수를 실험적으로 결정하는데 있었다. 교정실험은 국방과학연구소 저속풍동에서 표준 피토관을 이용하여 수행되었으며 이때의 교정속도 영역은 약 10~100 m/s이었다. 풍동교정실험결과의 유효성 평가를 위해 기존의 교정계수 측정결과와의 비교검토를 수행하였으며, 기존 교정 결과들과 잘 부합됨을 확인하였다.

곡선 터널 내에서 전파특성 분석 (Analysis of Radio-Wave Propagation Characteristics in Curved Tunnel)

  • 김영문;정민석;진용옥;이범선
    • 한국전자파학회논문지
    • /
    • 제13권10호
    • /
    • pp.1017-1024
    • /
    • 2002
  • 터널 내 직선구간과 곡선구간에 대한 전파특성을 분석하였다. 전파특성 분석모델로는 직선구간에서는 Ray-tracing 기법을 사용하였고, 곡선구간에서는 혼합도파관 모드와 Geometrical Optic(GO)을 결합하여 해석하는 모델을 이용하였다. 단면적이 3.5 m $\times$ 6 m이고 , 벽치 두께가 유한한 구조의 터널 내 송ㆍ수신 안테나 사이의 거리에 따른 수신전력 측정값을 회귀 분석한 결과 직선구간의 경로손실은 0.19 dB/m이었고, 곡선구간의 경로손실은 0.68 dB/m이다. 터널 내 수신전력 측정값은 터널전파 모델의 시뮬레이션 결과와 잘 일치함을 알 수 있었다.

Current-in-plane Tunneling Measurement through Patterned Contacts on Top Surfaces of Magnetic Tunnel Junctions

  • Lee, Ching-Ming;Ye, Lin-Xiu;Lee, Jia-Mou;Lin, Yu-Cyun;Huang, Chao-Yuan;Wu, J.C.;Tsunoda, Masakiyo;Takahashi, Migaku;Wu, Te-Ho
    • Journal of Magnetics
    • /
    • 제16권2호
    • /
    • pp.169-172
    • /
    • 2011
  • This study reports an alternative method for measuring the magnetoresistance of unpatterned magnetic tunnel junctions similar to the current-in-plane tunneling (CIPT) method. Instead of using microprobes, a series of point contacts with different spacings are coated on the top surface of the junctions and R-H loops at various spacings are then measured by the usual four-point probe method. The values of magnetoresistance and resistance-area products can be obtained by fitting the measured data to the CIPT theoretical model. The test results of two types of junctions were highly similar to those obtained from standard CIPT tools. The proposed method may help to accelerate the process for evaluating the quality of magnetic tunnel junctions when commercial CIPT tools are not accessible.

초기계측치를 이용한 경암 지반내 터널의 최총변위량 예측 (Estimation of Final Deformation of Hard Rock Tunnel Using Early Measured Deformation)

  • 송승곤;양형식;임성식;정소걸
    • 터널과지하공간
    • /
    • 제12권2호
    • /
    • pp.99-106
    • /
    • 2002
  • 터널의 초기 변형결과를 역해석에 적용하기 위하여 초기 값들과 최종변위의 상관관계를 연구하였다. Panet의 지수함수와 분수함수는 경암 터널의 내공변위 예측에 잘 맞았다. ID 지점의 초기 계측변위는 선형적으로 적합시 킬 수 있으나 계측 전 변형의 추정식으로는 부적합하였다. 초기 계측 결과들과 최종 변형결과는 선형적인 비례관계를 보였으며 이로써 초기 계측결과로부터 추정한 최종변형치를 이용한 역해석이 가능함을 보였다.