Modelling and integrity assessment of shear connectors in precast cast-in-situ concrete bridges

  • Moyo, Pilate;Sibanda, Bongani;Beushausen, Hans
    • Structural Engineering and Mechanics
    • /
    • v.42 no.1
    • /
    • pp.55-72
    • /
    • 2012
  • Precast-cast insitu concrete bridge construction is widely practiced for small to medium span structures. These bridges consist of precast pre-stressed concrete beams of various cross-sections with a cast in-situ reinforced concrete slab. The connection between the beams and the slab is via shear links often included during the manufacturing process of the beams. This form of construction is attractive as it provides for standardisation, reduced formwork and construction time. The assessment of the integrity of shear connectors in existing bridges is a major challenge. A procedure for assessment of shear connectors based on vibration testing and finite element model updating is proposed. The technique is applied successfully to a scaled model bridge model and an existing bridge structure.

Performance Evaluation of the Stair Joints Constructed with Partial Precast Concrete System (프리캐스트 콘크리트 계단 접합부의 접합방식에 따른 성능평가)

  • Chang, Kug-Kwan;Lee, Eun-Jin;Jin, Byung-Chang
    • Journal of the Korea Concrete Institute
    • /
    • v.20 no.6
    • /
    • pp.833-840
    • /
    • 2008
  • The time and cost can be reduced when applying partial precast concrete to the stair system in comparison to the cast-in-place or precast method. Because the performance of staircase which is used for evacuation can be largely different from connection types of precast concrete member, we tried to know structural behavior and performance evaluation according to each type of stair joints by experimental study. In the cast-in-place rigid joint, much reinforcement is needed in the end portion because much stress is concentrated in the middle portion. Also, in the pin joint which is used in the connection point, the maximum stress occurs in the middle point, so not only the amount of re-bar is increased but also the serviceability is largely decreased. The bolt type of semi-rigid joints proposed in this study had been increased strength and serviceability which is similar to the rigid joints. Also, its ductility was shown about 0.7 times in comparison to the rigid type and was about 2.8 times for the pin joint type. According to the classification of joint in Eurocode, it can be considered that it is one of the semi-rigid joints which are in the semi-rigid-full strength, and the structural behavior can be expected by using a model which applied to stiffness value decreased by 40 percent.

Numerical Simulation of Prestressed Precast Concrete Bridge Deck Panels Using Damage Plasticity Model

  • Ren, Wei;Sneed, Lesley H.;Yang, Yang;He, Ruili
    • International Journal of Concrete Structures and Materials
    • /
    • v.9 no.1
    • /
    • pp.45-54
    • /
    • 2015
  • This paper describes a three-dimensional approach to modeling the nonlinear behavior of partial-depth precast prestressed concrete bridge decks under increasing static loading. Six full-size panels were analyzed with this approach where the damage plasticity constitutive model was used to model concrete. Numerical results were compared and validated with the experimental data and showed reasonable agreement. The discrepancy between numerical and experimental values of load capacities was within six while the discrepancy of mid-span displacement was within 10 %. Parametric study was also conducted to show that higher accuracy could be achieved with lower values of the viscosity parameter but with an increase in the calculation effort.

An Experimental Study III on the Bolted Connection between H-Beam and Precast-Concrete Column (PC 기둥-H형강보의 볼트접합부에관한 실험적 연구III)

  • Yeo, In-Seok;Park, Soon-Kyu
    • Proceedings of the Korea Concrete Institute Conference
    • /
    • 2005.11a
    • /
    • pp.307-310
    • /
    • 2005
  • The PCS system, which consists of precast concrete column and steel beam, has been under development. Experimental test has been carried out to investigate the structural performance of the system under earthquake. Two types of test specimens of beam-column joints are designed in order to compare the performances. One is the system with reinforced concrete slab and the other is without slab. It is found that the system with slab could satisfy all of the requirements from ACI Criteria such as strength, stiffness degradation and energy dissipation capacity except initial stiffness. It is also investigated that the stiffness of the joint is belong to rigid joint type according to Bjorhovde criterion. And it is observed that the partial-composite system between beam and slab is more effective than full-composite system in the respect of the energy dissipation capacity of the system.

  • PDF

Effect of vertical reinforcement connection level on seismic behavior of precast RC shear walls: Experimental study

  • Yun-Lin Liu;Sushil Kumar;Dong-Hua Wang;Dong Guo
    • Earthquakes and Structures
    • /
    • v.26 no.6
    • /
    • pp.449-461
    • /
    • 2024
  • The vertical reinforcement connection between the precast reinforced concrete shear wall and the cast-in-place reinforced concrete member is vital to the performance of shear walls under seismic loading. This paper investigated the structural behavior of three precast reinforced concrete shear walls, with different levels of connection (i.e., full connection, partial connection, and no connection), subjected to quasi-static lateral loading. The specimens were subjected to a constant vertical load, resulting in an axial load ratio of 0.4. The crack pattern, failure modes, load-displacement relationships, ductility, and energy dissipation characteristics are presented and discussed. The resultant seismic performances of the three tested specimens were compared in terms of skeleton curve, load-bearing capacity, stiffness, ductility, energy dissipation capacity, and viscous damping. The seismic performance of the partially connected shear wall was found to be comparable to that of the fully connected shear wall, exhibiting 1.7% and 3.5% higher yield and peak load capacities, 9.2% higher deformability, and similar variation in stiffness, energy dissipation capacity and viscous damping at increasing load levels. In comparison, the seismic performance of the non-connected shear wall was inferior, exhibiting 12.8% and 16.4% lower loads at the yield and peak load stages, 3.6% lower deformability, and significantly lower energy dissipation capacity at lower displacement and lower viscous damping.

Girder Section of Continuous Bridges Spliced by Partial Post-Tensioning (부분 포스트텐션닝 방법에 의해 연속화된 교량의 주형단면)

  • 이환우;곽효경;송영용
    • Journal of the Korea Concrete Institute
    • /
    • v.12 no.6
    • /
    • pp.43-50
    • /
    • 2000
  • In this paper, a new splicing method was applied to design the girder section of bridges with the span length of 25m, 30m, 35m, 40m and 45m. A U-type precast prestressed section was also determined for each bridge. Additionally, the sectional area, beam depth and Guyon's efficiency factor of the spliced U-type sections in each span were analyzed in comparison with the present I-type PSC bridges. As a result, in spite of an increase of 31%∼50% in the sectional areas compared with the I-type precast girders, the spliced U-type the beam depth of the spliced U-type girder was designed as 2,050 mm compared with the I-type precast girder of 2,600mm in a 40m span bridge. The sectional efficiency factors of the spliced U-type sections were analyzed as 0.76∼0.99. It shows that the spliced U-type sections ar of a superior structural efficiency in contrast to the average sectional efficiency factor of 0.66 value in the I-type girders.

Design of Shear connection in Full-Depth Precast Concrete Deck Bridge (프리캐스트 콘크리트 바닥판 교량의 전단연결부 설계)

  • Chang, Sung Pil;Shim, Chang Su;Kim, Jong Hee;Kim, Young Jin
    • Journal of Korean Society of Steel Construction
    • /
    • v.10 no.4 s.37
    • /
    • pp.759-767
    • /
    • 1998
  • Full-depth precast concrete deck bridge has shear pockets for shear connectors that give composite action with steel girder. Strength and shear stiffness of shear connection that is needed to design shear connectors in case that shear pockets are filled with nonshrink mortar are investigated. In case that simple span full-depth precast concrete deck bridge is designed by allowable stress design, distribution of shear connector is suggested and details of precast panel that is placed on the support are proposed. Appropriate distribution of shear connectors in strength design and fatigue design is investigated through parameter analyses using partial interaction theory. The effects of nonshrink mortar strength is studied using the results of experiments and analyses and adequate strength is proposed.

  • PDF

Experimental study on shear behaviors of Partial Precast Steel Reinforced Concrete beams

  • Yang, Yong;Li, Hui
    • Steel and Composite Structures
    • /
    • v.37 no.5
    • /
    • pp.605-620
    • /
    • 2020
  • An innovative Partially Precast Steel Reinforced Concrete (PPSRC) beam is presented in this paper. To study the shear behavior of PPSRC beams, static loading experiments were conducted on 10 specimens, including 4 T-beam specimens and 4 PPSRC inverted T-beam specimens together with 2 PPSRC rectangular section beams. In the tests, the shear behaviors of the PPSRC beams were emphasized. On the basis of the experiments, the failure mode and ultimate bearing capacity were thoroughly examined. The calculation methods for shear capacity are also presented in this paper. The analysis of mechanical behavior and the calculation methods presented can be used as a reference to design these innovative composite PPSRC beams and provide a significant foundation for further research.

A Reliability Analysis on the To-Box Reinforcement Method of PSC Beam Bridges (PSC보의 박스화 보강방법의 신뢰성해석)

  • Bang, Myung-Seok
    • Journal of the Korean Society of Safety
    • /
    • v.21 no.3 s.75
    • /
    • pp.94-100
    • /
    • 2006
  • The goal of this study is to show the way to increase the safety of deteriorated PSC beam bridges by the to-box reinforcing method. This method is to change the open girder section into the closed box section by connecting bottom flanges of neighboring PSC girders with the precast panels embedding PS tendons at the anchor block. The box section is composed of three concrete members with different casting ages, RC slab, PSC beam, precast panel. This different aging requires a time-dependent analysis considering construction sequences. Reliability index and failure probability are produced by the AFOSM reliability analysis. Transversely five schemes and longitudinally two schemes are considered. The full reinforcing scheme, transversely and longitudinally, shows the highest reliability index, but it requires more cost for retrofit. The partial reinforcing scheme 4, 4-1 are recommended in this study as the economically best scheme.

Spliced Two Span Bridge with the U-Type Precast Girders by Using the Secondary Moment (2차 모멘트를 이용한 U형 프리캐스트 거더의 연속화)

  • 이환우;조은래;김광양
    • Proceedings of the Computational Structural Engineering Institute Conference
    • /
    • 1998.10a
    • /
    • pp.193-200
    • /
    • 1998
  • The precast prestressed concrete girders of I-type section are frequently employed to design the short-to-medium span bridge. However, its beam depth is greatly increased as its span length is increased over than about 30m. Therefore, the economic and aesthetic effectiveness are rapidly decreased in case of the span length over 30m. The purpose of this paper is to verify the structural safety on the new spliced two span bridge and analyze the variation of member forces and stress distribution according to the construction stages and time. The new spliced technique is performed by partial post tensioning and release in the U-type girders. The structural characteristics of this technique is the introduction of secondary moment to reduce the bending moment by self weight of precast U-type girders constructed in simply supported beam type. So, it is expected that the structural efficiency of this spliced bridge may be improved more than other techniques.

  • PDF