• Title/Summary/Keyword: RAFT

Search Result 226, Processing Time 0.019 seconds

Development of Design Method of Disconnected Piled Raft Foundation System (기초분리말뚝 공법의 설계기법 개발)

  • Choi, Jung-In;Min, Ki-Hoon;Kim, Sung-Ho;Kwon, Oh-Sung;Kim, Myoung-Mo
    • Proceedings of the Korean Geotechical Society Conference
    • /
    • 2008.10a
    • /
    • pp.691-699
    • /
    • 2008
  • In the design of a foundation, settlement of the foundation may exceed allowable design criteria even with a competent bearing stratum. In such a case, a piled-raft foundation system may be adopted using piles as settlement reducing component. In this paper, Disconnected Piled Raft Foundation (DPRF) system, which installs disconnected piles underneath the raft and uses the piles as ground reinforcements, is studied as a cost effective design method against the classical piled-raft foundation system. To this end, large size loading tests were carried out on weathered ground changing area replacement ratio and length of piles. The results indicated that the settlement of the reinforced ground was reduced by 34~87% and the allowable bearing pressure increased by 70% on average from those of the unreinforced original ground, respectively. The correlating formula between the area replacement ratio and the load bearing ratio of piles were derived from the test results and numerical analysis. From the correlation, a design method determining the size and the quantity of the disconnected piles to enhance the bearing capacity of original ground to the desired value was proposed based on one inch settlement criteria.

  • PDF

Measurements and analysis of load sharing between piles and raft in a pile foundation in clay

  • Watcharasawe, Kongpop;Jongpradist, Pornkasem;Kitiyodom, Pastsakorn;Matsumoto, Tatsunori
    • Geomechanics and Engineering
    • /
    • v.24 no.6
    • /
    • pp.559-572
    • /
    • 2021
  • This research presents the monitoring results and their interpretation on load sharing of the pile foundation during the construction of a high-rise (124 m in height) building in Bangkok, in soft clayey ground. Axial forces in several piles, pore water pressure and earth pressures beneath the raft in a tributary area were monitored through the construction period of the building. The raft of the pile foundation in soft clayey ground can share the load up to 10-20% even though the foundation was designed using the conventional approach in which the raft resistance is ignored. The benefit from the return of ground water table as the uplift pressure is recognized. A series of parametric study by 3D-FEA were carried out. The potential of utilizing the piled raft system for the high-rise building with underground basement in soft clayey ground was preliminarily confirmed.

Effect of groundwater level change on piled raft foundation in Ho Chi Minh City, Viet Nam using 3D-FEM

  • Kamol Amornfa;Ha T. Quang;Tran V. Tuan
    • Geomechanics and Engineering
    • /
    • v.32 no.4
    • /
    • pp.387-396
    • /
    • 2023
  • Ground subsidence, which is a current concern that affects piled raft foundations, has occurred at a high rate in Ho Chi Minh City, Viet Nam, due primarily to groundwater pumping for water supply. In this study, the groundwater level (GWL) change affect on a piled raft foundation was investigated based on the three-dimensional finite element method (3D-FEM) using the PLAXIS 3D software. The GWL change due to global groundwater pumping and dewatering were simulated in PLAXIS 3D based on the GWL reduction and consolidation. Settlement and the pile axial force of the piled raft foundation in Ho Chi Minh subsoil were investigated based on the actual design and the proposed optimal case. The actual design used the piled foundation concept, while the optimal case applied a pile spacing of 6D using a piled raft concept to reduce the number of piles, with little increased settlement. The results indicated that the settlement increased with the GWL reduction, caused by groundwater pumping and dewatering. The subsidence started to affect the piled raft foundation 2.5 years after construction for the actual design and after 3.4 years for the optimal case due to global groundwater pumping. The pile's axial force, which was affected by negative skin friction, increased during that time.

Analysis of Piled Raft Bearing Capacity Increase with Centrifuge Test (원심모형시험을 통한 Piled Raft 기초의 지지력증가 특성 분석)

  • Park, Dong-Gyu;Choi, Kyu-Jin;Kim, Dong-Wook;Chung, Moon-Kyung;Lee, Jun-Hwan
    • Journal of the Korean Geotechnical Society
    • /
    • v.28 no.8
    • /
    • pp.43-53
    • /
    • 2012
  • In the conventional design of a piled raft, the axial resistance offered by the raft itself is typically neglected and only that of the group pile is accounted in estimating the total axial resistance of the piled raft. As a consequence, piled rafts are usually designed conservatively by neglecting the raft resistance. In this study, a series of centrifuge model tests have been performed to compare the axial behavior of a group pile with that of a piled raft (both having 16 component piles with an array of $4{\times}4$) in sands with different relative densities and in clays with different preconsolidated pressures. The test results revealed that, with respect to the allowable settlement of 25 millimeters for bridge foundations, the piled raft resistances were greater than those of the group pile by 13% for dense sand, by 22% for loose sand, by 30% for stiff clay, and by 22% for soft clay. Furthermore, the ratio of piled raft resistance to group pile resistance increased as the settlement increased.

The Vertical and Lateral Ordering of PDMA-b-PS Block Copolymer Thin film via Control of Relative Humidity (습도의 영향에 따른 PDMA-b-PS 친수성 블록공중합체 박막의 패턴 조절)

  • Jung, Hyun-Jung;Kim, Tae-Joon;Bang, Joon-A
    • Korean Chemical Engineering Research
    • /
    • v.49 no.3
    • /
    • pp.352-356
    • /
    • 2011
  • In this paper, we prepared new type of hydrophilic block copolymers that exhibit the long-ranged lateral ordering in thin film. It was previously demonstrated that poly(ethyleneoxide-b-styrene) and poly(ethyleneoxide-b-metharylate-b-styrene) block copolymer thin films have a high degree of lateral ordering after solvent annealing process. In these cases, the relative humidity plays an important role in long-ranged lateral ordering. However, the origin of the humidity effect on the orders of these hydrophilic block copolymers is not fully understood. To investigate the effect of the humidity further, we prepared other hydrophilic poly(N,N-dimethylacrylamide-b-styrene)(PDMA-b-PS) block copolymers via RAFT polymerization. As with PEO-containing block copolymers, PDMA-b-PS block copolymers exhibit the long-ranged lateral ordering after solvent annealing process.

Numerical investigation of responses of a piled raft to twin excavations: Role of sand density

  • Karira, Hemu;Kumar, Aneel;Ali, Tauha Hussain;Mangnejo, Dildar Ali;Yaun, Li
    • Geomechanics and Engineering
    • /
    • v.31 no.1
    • /
    • pp.53-69
    • /
    • 2022
  • In densely built areas, the development of underground transportation systems often involves twin excavations, which are sometimes unavoidably constructed adjacent to existing piled foundations. Because soil stiffness degrades with induced stress release and shear strain during excavation, it is vital to investigate the piled raft responses to subsequent excavation after the first tunnel in a twin-excavation system. The effects of deep excavations on existing piled foundations have been extensively investigated, but the influence of twin excavations on a piled raft is seldom reported in the literature. In this study, three-dimensional numerical analyses were carried out to investigate the influence of sand density on an existing piled raft (with a working load on top of the raft) due to twin excavations. A wide range of relative density (Dr) from loosest (30%), loose to medium (50% and 70%), and densest (90%) were selected to investigate the effects on settlement and load transfer mechanism of the piled raft during twin excavations. An advanced hypoplastic sand model (which can capture small-strain stiffness and stress-state dependent dilatancy of sand) was adopted. The model parameters are calibrated against centrifuge test results in sand reported in the literature. From the computed results, it is found that twin excavations in loose sand (Dr=30%) caused the most significant settlement. This is because of the higher stiffness of denser sand (Dr=90%) than that of loose sand. In contrast, a much larger tilting (maximum magnitude=0.18%) was computed in dense sand than in loose sand after the completion of the first excavation. As far as the load transfer mechanism along the piles is concerned, an upward load transfer to mobilize shaft resistance is observed in loose sand. On the contrary, a downward load transfer is observed in dense sand.

송전선철탑의 Raft 기초설계

  • 이재숙
    • 전기의세계
    • /
    • v.31 no.11
    • /
    • pp.749-757
    • /
    • 1982
  • 본고의 내용은 다음과 같다. 1. Raft기초의 비전도의 원리 2. 상판 Beam설계 3. 배근계산 4. 계산예

  • PDF

An Experimental Study on the Load-settlement Behavior and Settlement-reducing Effect of the Disconnected Piled Raft Foundation (말뚝보강기초의 하중-침하량 거동 및 침하감소효과에 대한 실험적 연구)

  • Lee Yeong-Saeng;Hong Seung-Hyeun
    • Journal of the Korean Geotechnical Society
    • /
    • v.22 no.4
    • /
    • pp.95-104
    • /
    • 2006
  • For the interests in the economical and safe design of foundation system, the concern on the piled raft or disconnected piled raft foundation system is increasing now. In this study, the behavior and the effects of the disconnected piled raft foundation not studied actively in this country were examined using the triaxial compression tests in place of laboratory model tests. The triaxial test samples were prepared with Jumunjin standard sand and the carbon rods, which simulate the ground soil and piles respectively. After the sample in which carbon rods were arranged was laid inside the triaxial chamber, the confining pressure was applied and then loading test was conducted. To analyze the reinforcing effects of the disconnected piled raft foundation, a few number of tests were carried out by changing the number, the diameter and the length of the model piles. As a result of this study, in the disconnected piled raft foundation system, even though the number of pile is few and the diameter of pile is small, the settlement of the foundation system decreased greatly.

A Practical Analysis Method for the Design of Piled Raft Foundations (말뚝지지 전면기초의 설계를 위한 실용적 해석방법에 관한 연구)

  • Lee, Seung-Hoon;Park, Young-Ho;Song, Myung-Jun
    • Journal of the Korean Geotechnical Society
    • /
    • v.23 no.12
    • /
    • pp.83-94
    • /
    • 2007
  • Piled raft foundations have been highlighted as an economical design concept of pile foundations in recent years. However, piled raft foundations have not been widely used in Korea due to the difficulty in estimating the complex interaction effects among rafts, piles and soils. The authors developed an effective numerical program to analyze the behavior of piled raft foundations for practical design purposes and presented it briefly in this paper. The developed numerical program simulates the raft as a flexible plate consisting of finite elements with eight nodes and the raft is supported by a series of elastic springs representing subsoils and piles. This study imported another model to simulate pile groups considering non-linear behavior and interaction effects. The apparent stiffnesses of the soils and piles were estimated by iterative calculations to satisfy the compatibility between those two components and the behavior of piled raft foundations can be predicted using these stiffnesses. For the verification of the program, the analysis results about some example problems were compared with those of rigorous three dimensional finite element analysis and other approximate analysis methods. It was found that the program can analyze non-linear behaviors and interaction effects efficiently in multi-layered soils and has sufficient capabilities for application to practical analysis and design of piled raft foundations.

Evaluation of performance of piled-raft foundations on soft clay: A case study

  • Khanmohammadi, Mohammadreza;Fakharian, Kazem
    • Geomechanics and Engineering
    • /
    • v.14 no.1
    • /
    • pp.43-50
    • /
    • 2018
  • Applicability of constructing piled raft foundations on soft clay has been given attention in recent years. Lack of sufficient stiffness for soil and thus excessive settlements to allow higher contribution of piles is the major concern in this regard. This paper presents a numerical investigation of performance of piled-raft foundations on soft clay with focusing on a case study. A 3D FEM numerical model is developed using ABAQUS. The model was calibrated by comparing physical and numerical modeling results of other researchers. Then the possibility of using piled-raft system in construction of foundation for a water storage tank in Sarbandar, Iran is assessed. Soil strength parameters in the numerical model were calibrated using the instrumentation data of a heavily instrumented preloading project at the construction site. The results indicate that choosing the proper combination of length and spacing for piles can lead to acceptable differential and total settlements while a high percentage of total bearing capacity of piles can be mobilized, which is an efficient solution for the project. Overall, the construction of piled-rafts on soft clays is promising as long as the total settlement of the structure is not imposing restrictions such as the common 25 mm allowable settlement. But instead, if higher allowable settlements are adopted, for example in the case of rigid steel tanks, the method shall be applicable with considerable cost savings.