• 제목/요약/키워드: PRD (Percussion Rotary Drill) Pile

검색결과 5건 처리시간 0.013초

PRD 강환 말뚝의 연직지지력 특성에 관한 사례 연구 (Case Study on the Characteristics of Vertical Bearing Capacity for Steel Pipe Pile Installed by PRD)

  • 최용규;정창규;정성기;김동철;정태만
    • 한국지반공학회:학술대회논문집
    • /
    • 한국지반공학회 1999년도 봄 학술발표회 논문집
    • /
    • pp.225-232
    • /
    • 1999
  • Construction case of PRD (Percussion Rotary Drill) pipe pile and matters to be attended in construction of PRD pile were reviewed. The compressive and uplifting static pile load tests for PRD piles were performed and, also, analysis by Pile Driving Analyzer was done. Based on these results, bearing components in each resisting part (that is: steel toe, external skin, and internal skin) were measured separately. The measured resisting force was compared to the value calculated by the estimated formula. The pile capacity was mobilized in steel toe area and the external skin friction and the internal friction were not produced. Thus, it could be considered that toe of PRD pile should be supported in hard bearing stratum (for example, the fresh soft rock).

  • PDF

PRD시공시 H-PILE 대체 자재로 원가절감 할수 있는 공법 사례 (Downward Method of H-PILE Alternative Materials of Percusion Rotary Drill)

  • 이왕희;이일재;임시내
    • 한국건축시공학회:학술대회논문집
    • /
    • 한국건축시공학회 2014년도 추계 학술논문 발표대회
    • /
    • pp.199-202
    • /
    • 2014
  • In recent years the downtown, Top-down method has been applied in a major method to solve the complaints due to noise, vibration, dust and safety issues such as cracking due to settlement when the excavation close to the building. Until it is installed underground permanent foundation, the Pre-founded Column is a pile foundation as well as a column to bear the upper construction load. The Pre-founded Column is constructed by PRD method generally. The EnP(Enlarging Pile) method can be expanded locally boring diameter of the embedment zone as compared to the PRD method existing general. Since the bearing capacity is increased by the boring diameter is expanded, the embedment length is reduced, the construction cost is reduced.

  • PDF

PRD Pile Driving공법의 진동저감 평가를 위한 실험적 연구 (Experimental Study on Vibration Reduction Estimation of PRD Pile Driving Method)

  • 강성후;박선준;정석규
    • 한국소음진동공학회논문집
    • /
    • 제18권7호
    • /
    • pp.775-782
    • /
    • 2008
  • In this study, ground vibrations and aero space noises that is produced by the PRD(percussion rotary drill) were analyzed by work processes. Ground vibration equations were suggested by $2.798(SD)^{-0.793}$, $3.485(SD)^{-0.793}$, $3.705(SD)^{-0.793}$, according to experiment result, and these equations have reliability of 50%, 90%, 95%, respectively. Ground vibration values by the PRD method correspond to level of $5{\sim}34%$ of values that are assumed by the Attewell & Farmer's equation, and these result compares in reliability 50%. Also, those values were analyzed that correspond to level of $12{\sim}26%$ of ground vibration values by the Prof. Park etc.'s equations. But, the aero space noise was evaluated that is assumed by 88.9 dB(A) at separated distance 50m and is not satisfied even 85dB(A) that is the most negative noise value that present in domestic noise standard. The PRD method was analyzed that noise decrease effect exists hardly comparing with general pile driving method of construction. When is based in these results, the PRD method is judged that it is desirable that classify by the Low-vibration method more than the Non-violation noise method.

MSG공법에 의한 PRD강관말뚝 보강에 관한 사례 연구 (An Experimental Study on the MSG Reinforcement of Steel Pipe Pile Installed by PRD)

  • 천병식;강희진;공진영
    • 한국지반환경공학회 논문집
    • /
    • 제8권6호
    • /
    • pp.5-12
    • /
    • 2007
  • 이암은 건조 조건에서는 일정한 강도와 강성을 가지나, 지하수 침투 등에 의한 습윤, 포화 시 고유의 강도 및 강성이 저하되어 급속히 풍화되는 특성을 가지며, 포항지역에서 자주 발생하는 절취사면의 활동은 주로 이암이 풍화되어 전단강도가 급격히 저하되는 것으로 볼 수 있다. 본 연구는 시추조사시 강성이 충분한 것으로 평가된 이암층에 PRD강관말뚝을 시공한 후 정재하 시험을 실시한 결과 소요지지력이 부족하여, 이를 보강하기 위한 가장 우수한 방법을 찾기 위하여 여러 가지 공법을 검토하였다. 말뚝지지력 증대에 가장 효과적인 방법을 찾기 위해 말뚝주변 및 선단부에 MSG공법, 마이크로파일 보강후 주변그라우팅공법, 선단보강 그라우팅 및 콘크리트 속채움 등의 방법으로 시험시공을 실시하였고, 시험말뚝에 대한 정재하시험 결과 MSG공법으로 보강한 말뚝의 지지력이 가장 우수함을 알 수 있었다.

  • PDF

도심지 토공사 PRD (Percussion Rotary Drill) 공법의 천공작업 소요시간 산정 방안에 관한 연구 (A Study on Estimating Time for PRD (Percussion Rotary Drill) Piling Work)

  • 김용규;최창훈;한충희;이준복
    • 한국건설관리학회논문집
    • /
    • 제19권3호
    • /
    • pp.3-10
    • /
    • 2018
  • 근래에 공사의 대형화, 복잡화 등으로 인해 기계화시공은 보편화되었으며, 건설기계는 성공적인 시공을 위한 주요소이다. 그러나 건설기계가 차지하는 비중이 높아지고 있음에도 불고하고 건설기계의 작업능력에 대한 분석은 미미한 실정이다. 또한 현재 품셈에서 모든 건설기계에 대한 기준이 정의되어 있지 않음으로 인해 시공계획 시 작업자에 따라 공사기간을 자의적으로 적용하고 있어 실제 시공 간 공사기간이 부족하여 돌관작업이나 공기지연이 발생된다. 따라서 본 연구에서는 PRD공법에서 사용되는 항타기의 천공작업 공사기간을 기존 방법보다 정확하게 산출할 수 있도록 작업일보를 현장 실사를 통해 천공시간 데이터를 수집하여 항타기의 천공 작업 소요시간을 산정하는 식을 정립하였다. 본 연구 결과를 바탕으로 천공작업의 정확한 공사기간을 산정한다면 공사기간이 부족하여 발생하던 돌관작업이나 공기지연을 방지할 수 있을 것으로 사료된다.