Risk Classification and Relational Database Schema in Overseas Power Plant Construction (해외 발전플랜트 리스크 분류체계 및 관계형 데이터베이스 구축 방안)

  • Kim, Min;Jung, Youngsoo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 한국건축시공학회 2014년도 춘계 학술논문 발표대회
    • /
    • pp.192-193
    • /
    • 2014
  • Due to the decreasing domestic construction market since 2007, Korean construction companies are expanding overseas market. As a result, the international market share by Korea has been continuously increased and achieved 65.2 billion dollars in 2013. Despite of such visible results, profitability concerns are constantly arising. It is pointed out that the low-priced bid competition between Korean construction companies and various unpredictable risks are the most crucial factors which aggravate the profitability in the overseas projects. From this point of view, predicting the risks in advance and controling them could be the most important tasks to improve the profitability. This research proposed 202 risk factors with a hierarchy and relational database schema for power plant construction, which is based on the 24 risk classifications in previous research (Kim & Jung 2013). Proposed risk classification and relational database schema could be utilized as the basic data in risk management system.

  • PDF

A Domestic Power Companies' Strategy to Enter Asian Thermal Power Plant Market (국내 발전기업의 아시아 화력발전플랜트 시장 진출전략)

  • Park, Chang-Hyun;Moon, Seung-Jae
    • Plant Journal
    • /
    • 제7권4호
    • /
    • pp.58-66
    • /
    • 2011
  • The power plant companies reached the culmination for growth in the domestic market. Besides, we have faced many challenges such as an electricity opening market trend for overseas, banning the use of coal due to the United nations framework convention on climate change, and the meticulous attention regarding the government's electricity charge plan. On the other hand, the overseas business has been a critical issue since China and many other developing countries expanded their projects abroad. Another factor is that power plant industry is being privatized, and it made the market regulation a bit loose. Thus, the market environment became favorable toward those companies which planned many overseas businesses. In this research, the power plant company's current condition for construction and operation as well as its technical competitiveness were analyzed, and an alternative plan using SWOT analysis for entering an oversea market was made. It dealt with both internal and external factors. Also, examined was the current situation under the power plant industry dealing with restructure for electric industry, lack of fossil fuel, and the United nations framework convention on climate change. From the research, it was suggested that many successful strategies to enter the overseas business by using the market trend I researched.

  • PDF

Promotion of the Overseas Biomass Plant Business for a Domestic Power Company (국내 발전기업의 해외 바이오매스 플랜트 사업진출 방향)

  • Kim, Yeongsang;Moon, Seungjae;Yoo, Hoseon
    • Plant Journal
    • /
    • 제7권3호
    • /
    • pp.42-47
    • /
    • 2011
  • One of domestic power generation companies, Korea East-West Power Corporation(EWP) had no performance in overseas business just two short years ago. However, EWP has accomplished breakthrough results with the profit of KRW 17.8 billion in 2010, only overseas business part. With overseas power plant growing fast, there is a possibility that EWP may face the limitation of sustainable growth with the current low income structure, which is mainly focused on commissioning and power plant management. Accordingly, this study was made on overseas biomass plant business participation plan through the establishment of joint venture. The characteristics of a joint venture establishment was searched, choosing business partner; the ideas of how to organize a joint venture was drawn, what the role of each partner in joint venture is, and what proper capital share is; and chose business field, considering changing global energy mix, renewable energy market scale, and growth prospects. Considering government policy for renewable energy vitalization and renewable energy market share, We chose the European union as a market to which our business entered.

  • PDF

A Study on the Cost Hierarchical System of Nuclaer Power Plant Construction Project for Introcusting Earned Vaule Management System (성과관리시스템(EVMS) 도입을 위한 원전 건설사업비 관리체계 세분화 방안에 관한 연구)

  • Lee, Sang-Hyun;Kim, Woo-Joong
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 한국건축시공학회 2019년도 춘계 학술논문 발표대회
    • /
    • pp.230-231
    • /
    • 2019
  • The nuclear power plant construction project is large-scale, has various stakeholders and computer system, and is produced and managed a large amount of information. The domestic nuclear power plant construction project has accumulated data based on many years of experience in the system. It has the competitiveness to suggeest alternatives that meet the requirement of the client in the overseas nuclear power plant project. Earned value management, which integrates schedule and cost, is possible to risk management. It was developed the earned value management system considering the the actual data properties and types of the preceding nuclear power plant construction projects. It will be able to increase the nuclaer power plant export competieiveness. Therefore, it was palned to carry out future stuies so that it be able to complement the measure to integrate cost and schedule in consideration of actual data(quantity of activity, etc.).

  • PDF

Development and Application of Integrated Management System in Nuclear Power Plant Construction Project

  • Lee, Sang Hyun;Byon, Su Jin
    • International conference on construction engineering and project management
    • /
    • The 6th International Conference on Construction Engineering and Project Management
    • /
    • pp.700-701
    • /
    • 2015
  • Nuclear power plant construction project can be called essential to establish a systematic project management system compared to other construction projects, taking into account the size and complexity and safety. To develop into a project management system for the Korea situation with the ongoing construction of the nuclear power plant was directed to promote nuclear power project management. In this paper, we introduce a comprehensive project management system for nuclear power projects. Currently considering the nuclear life cycle design, construction, and was developed by considering the flow of information to operate, and test each step linkage. The systems in English were developed to meet owner's requirements for advancing into overseas projects. Another point is that the systems were developed by management module, so that functions of each area can be selectively applied. It is expected that the system will establish itself as one that can be used for the entire lifecycle of nuclear power plants through gradual and systematic establishment of necessary data.

  • PDF

Management in the EPC Business for Overseas Power Plant Projects (해외 발전플랜트 EPC 사업의 리스크 분석 및 관리방안)

  • Park, Euiseung;Yoo, Hoseon;Lee, Jae-Heon
    • Plant Journal
    • /
    • 제7권3호
    • /
    • pp.48-64
    • /
    • 2011
  • In this work, risks in EPC project for overseas power plant projects are analyzed and risk management methods are suggested to reduce cost and to shorten time. 79% of risks occurred in the engineering phase for S project located in South-East Asia. The impact scales of risks on major project objectives which are cost, time, scope, and quality are analyzed as 3.5, 3.8, 2.7, and 3.7, respectively. The level of impact scales is very similar to each other except the impact scale of scope. The risk management methods suggested in this study have to be applied at the appropriate time to manage risks effectively. After that, risks are managed continuously by monitoring.

  • PDF

Process Model for development of EVMS in Nuclear Power Plant Project (원전건설 성과관리시스템(EVMS) 개발을 위한 프로세스 모델 연구)

  • Kim, Yun-Myung;Won, Seo-Kyung;Shin, Il-Sub
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 한국건축시공학회 2014년도 춘계 학술논문 발표대회
    • /
    • pp.58-59
    • /
    • 2014
  • EVM(Earned Value Management) is a management methodology for integrating scope, schedule and resources, and for objectively measuring project performance and progress. EVMS(Earned Value Management System) has been used for the performance measurement of R&D and construction projects in developed countries such as United States, United Kingdom and Australia. The nuclear power plant (NPP) projects in Korea have not applied EVMS. However, EVMS has come into request for overall schedule and cost risk management and performance measurement in overseas project of the nuclear power plant as a contractor. In this paper, based on the global EVMS guidelines, EVMS per unit processes have been developed for NPP projects. Moreover, using Business Process Management (BPM), it proposes an integrated process model with tasks, roles, and procedures for EVMS for NPP construction projects.

  • PDF

Penetration of Korean EPC Companies into International Market for Nuclear Power Plant (플랜트 EPC 기업의 해외 원자력 발전 프로젝트 진출방안)

  • Cho, Chan-Hyoung;Moon, Seung-Jae;Yoo, Hoseon
    • Plant Journal
    • /
    • 제5권3호
    • /
    • pp.66-73
    • /
    • 2009
  • This study aims to develop a strategy for South Korean companies to penetrate into the global NPP(nuclear power plant) market with their strength as the sixth biggest nuclear power generator in the world. With 20 nuclear plants in commercial operation and 6 more in construction, South Korea has the best technology in construction and operation of NPP. Despite these capabilities as demonstrated on its domestic market, Korean companies' constraint to enter and play a key role in global NPP market would be the lack of experience in overseas NPP projects, original technologies, and diplomatic effectiveness. This study analyzes the competitiveness of Korean standardized nuclear power plant, construction management skills, construction technologies, manufacturing equipment and materials and operation skills. In this research the current status of existing NPP and the forecast of building NPP according to countries was analyzed in order to work out strategies with technology, cost-effectiveness, and diplomatic consideration.

  • PDF

A Fundamental Study on the Comparison and Analysis of Overseas Design Orders of Korea, China and Japan (한중일 해외설계수주액의 비교·분석 기초 연구)

  • Park, Hwan-Pyo;Han, Jae-Goo
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 한국건축시공학회 2019년도 추계 학술논문 발표대회
    • /
    • pp.195-196
    • /
    • 2019
  • The purpose of this study is to analyze the scale of overseas design orders in Korea, China and Japan by region and type of work, and to draw implications. As a result of analyzing the overseas design sales market of Korea, China and Japan, all three countries have the highest percentage of overseas sales in the Asian market, and the overseas design sales are the highest in power generation, chemical plant and transportation sectors. In addition to the Middle East and Asian markets, Japan and China have also diversified their strategies to diversify their markets by taking orders in various regions such as Europe, Africa and the United States. In particular, China is promoting the "New Silk Road Project" (One belt, One road), linking land and sea to a total of 25 countries and actively supporting aid projects in Africa and Asia, have. In addition, Japan has been actively supporting the government's expansion of ODA projects to expand overseas market entry. Therefore, it is necessary for Korea to increase its market share through diversification of overseas design market and diversification of industrial type, and to participate in overseas design market by expanding customized R&D investment.

  • PDF

Assessment and Management System for Various Risks in Plant Projects (플랜트 프로젝트 리스크의 평가 및 관리시스템에 관한 연구)

  • An, Seung Kyoo;Cho, Dong-Hwan;Hur, Jin-Huek;Moon, Seung-Jae;Yoo, Hoseon
    • Plant Journal
    • /
    • 제6권1호
    • /
    • pp.56-63
    • /
    • 2010
  • While the local plant market is reducing its volume, the plant market over the world since 2000s is rapidly expanding. The nation's construction companies, aggressively dedicated in launching out overseas plant market, increase the volume of orders in that sector, but there also are much difficulty in the project management as those projects ordered are gradually large scaled with more cutting-edge high-tech requirements along with comparatively higher risk. Though the local construction companies have developed their own types of measures to analyze the risk evaluation putting into practice, the specialized decision-making model for the overseas plant market or the risk measure understandable easily and applicable practically is not yet shown. This paper aims at providing the methodology to evaluate the risk by way of constructing the risk evaluation process in order to induce risk measuring elements through appropriate indexing system. Furthermore, through studying the risk management system, it aims to seek for a thorough risk management method from beginning of the project to the end.

  • PDF