• Title/Summary/Keyword: NPP communication

Search Result 28, Processing Time 0.024 seconds

DISTRIBUTED HMI SYSTEM FOR MANAGING ALL SPAN OF PLANT CONTROL AND MAINTENANCE

  • Yoshikawa, Hidekazu
    • Nuclear Engineering and Technology
    • /
    • v.41 no.3
    • /
    • pp.237-246
    • /
    • 2009
  • Digitalization of not only non-safety but also safety-grade I &C systems with full computerized Main Control Room (MCR) is the recent trend of I&C systems of nuclear power plants (NPP) around the world, while plant maintenance has been shifting from traditional time based maintenance to condition based maintenance. In order to cope with the new trend of operation and maintenance in NPP, a concept of online distributed diagnostic system for both plant operation and maintenance has been proposed in order to further improve both the plant efficiency and the work environment of plant operation staff members by organizational learning. In this respect, the research subjects of human machine interface (HMI) for the online distributed diagnostic system are also discussed for supporting the plant personnel at both MCR and local working places in the plant by the application of advanced ICT (Information and Communication Technologies).

Research on rapid source term estimation in nuclear accident emergency decision for pressurized water reactor based on Bayesian network

  • Wu, Guohua;Tong, Jiejuan;Zhang, Liguo;Yuan, Diping;Xiao, Yiqing
    • Nuclear Engineering and Technology
    • /
    • v.53 no.8
    • /
    • pp.2534-2546
    • /
    • 2021
  • Nuclear emergency preparedness and response is an essential part to ensure the safety of nuclear power plant (NPP). Key support technologies of nuclear emergency decision-making usually consist of accident diagnosis, source term estimation, accident consequence assessment, and protective action recommendation. Source term estimation is almost the most difficult part among them. For example, bad communication, incomplete information, as well as complicated accident scenario make it hard to determine the reactor status and estimate the source term timely in the Fukushima accident. Subsequently, it leads to the hard decision on how to take appropriate emergency response actions. Hence, this paper aims to develop a method for rapid source term estimation to support nuclear emergency decision making in pressurized water reactor NPP. The method aims to make our knowledge on NPP provide better support nuclear emergency. Firstly, this paper studies how to build a Bayesian network model for the NPP based on professional knowledge and engineering knowledge. This paper presents a method transforming the PRA model (event trees and fault trees) into a corresponding Bayesian network model. To solve the problem that some physical phenomena which are modeled as pivotal events in level 2 PRA, cannot find sensors associated directly with their occurrence, a weighted assignment approach based on expert assessment is proposed in this paper. Secondly, the monitoring data of NPP are provided to the Bayesian network model, the real-time status of pivotal events and initiating events can be determined based on the junction tree algorithm. Thirdly, since PRA knowledge can link the accident sequences to the possible release categories, the proposed method is capable to find the most likely release category for the candidate accidents scenarios, namely the source term. The probabilities of possible accident sequences and the source term are calculated. Finally, the prototype software is checked against several sets of accident scenario data which are generated by the simulator of AP1000-NPP, including large loss of coolant accident, loss of main feedwater, main steam line break, and steam generator tube rupture. The results show that the proposed method for rapid source term estimation under nuclear emergency decision making is promising.

Analysis on the EMC evaluating method for applying wireless communications in NPP (원전 내 무선통신 적용에 대한 전자파 적합성 평가방법 분석)

  • Kang, SeungSeok;Lim, Tae Heung;Choo, Jaeyul;Kim, HyungTae;Kim, DaeHee;Byun, Gangil;Park, Jong Eon;Lee, Jun-Yong;Choo, Hosung
    • Journal of the Korea Institute of Information and Communication Engineering
    • /
    • v.21 no.12
    • /
    • pp.2221-2231
    • /
    • 2017
  • In this paper, we surveyed previous cases, network protocols (such as Wi-Fi, Zigbee, Z-wave, and WirelessHart) and propagation characteristics on the application of maintaining equipments for instrumentation and control (I&C) using wireless communication techniques inside the nuclear power plant (NPP). In addition, we compared and analyzed the difference of detailed regulations with respect to the electromagnetic interference (EMI) and radio frequency interference (RFI) in the Regulatory Guide 1.180 rev. 1 (RG. 1.180) for adopting the wireless communication techniques inside the NPP, and other regulations, such as MIL-STD 461E and IEC 61000-4, that are recognized in the KINS/RG-N03.09 (Rev. 2). Furthermore, we investigated evaluating factors about electromagnetic properties by considering indoor environments, wave scattering, shielding effectiveness, and the indoor wave attenuation model that were not included in the current electromagnetic compatibility regulation.

Evaluation of GSICS Correction for COMS/MI Visible Channel Using S-NPP/VIIRS

  • Jin, Donghyun;Lee, Soobong;Lee, Seonyoung;Jung, Daeseong;Sim, Suyoung;Huh, Morang;Han, Kyung-soo
    • Korean Journal of Remote Sensing
    • /
    • v.37 no.1
    • /
    • pp.169-176
    • /
    • 2021
  • The Global Space-based Inter-Calibration System (GSICS) is an international partnership sponsored by World Meteorological Organization (WMO) to continue and improve climate monitoring and to ensure consistent accuracy between observation data from meteorological satellites operating around the world. The objective for GSICS is to inter-calibration from pairs of satellites observations, which includes direct comparison of collocated Geostationary Earth Orbit (GEO)-Low Earth Orbit (LEO) observations. One of the GSICS inter-calibration methods, the Ray-matching technique, is a surrogate approach that uses matched, co-angled and co-located pixels to transfer the calibration from a well calibrated satellite sensor to another sensor. In Korea, the first GEO satellite, Communication Ocean and Meteorological Satellite (COMS), is used to participate in the GSICS program. The National Meteorological Satellite Center (NMSC), which operated COMS/MI, calculated the Radiative Transfer Model (RTM)-based GSICS coefficient coefficients. The L1P reproduced through GSICS correction coefficient showed lower RMSE and Bias than L1B without GSICS correction coefficient applied. The calculation cycles of the GSICS correction coefficients for COMS/MI visible channel are provided annual and diurnal (2, 5, 10, 14-day), but long-term evaluation according to these cycles was not performed. The purpose of this paper is to perform evaluation depending on the annual/diurnal cycles of COMS/MI GSICS correction coefficients based on the ray-matching technique using Suomi-NPP/Visible Infrared Imaging Radiometer Suite (VIIRS) data as reference data. As a result of evaluation, the diurnal cycle had a higher coincidence rate with the reference data than the annual cycle, and the 14-day diurnal cycle was the most suitable for use as the GSICS correction coefficient.

A Systems Engineering Approach to Implementing Hardware Cybersecurity Controls for Non-Safety Data Network

  • Ibrahim, Ahmad Salah;Jung, Jaecheon
    • Journal of the Korean Society of Systems Engineering
    • /
    • v.12 no.2
    • /
    • pp.101-114
    • /
    • 2016
  • A model-based systems engineering (MBSE) approach to implementing hardware-based network cybersecurity controls for APR1400 non-safety data network is presented in this work. The proposed design was developed by implementing packet filtering and deep packet inspection functions to control the unauthorized traffic and malicious contents. Denial-of-Service (DoS) attack was considered as a potential cybersecurity issue that may threaten the data availability and integrity of DCS gateway servers. Logical design architecture was developed to simulate the behavior of functions flow. HDL-based physical architecture was modelled and simulated using Xilinx ISE software to verify the design functionality. For effective modelling process, enhanced function flow block diagrams (EFFBDs) and schematic design based on FPGA technology were together developed and simulated to verify the performance and functional requirements of network security controls. Both logical and physical design architectures verified that hardware-based cybersecurity controls are capable to maintain the data availability and integrity. Further works focus on implementing the schematic design to an FPGA platform to accomplish the design verification and validation processes.

Development of Work Breakdown Structure for Nuclear Power Plant (원자력발전소 Work Breakdown Structure 개발)

  • Cho, Yeong-Heock;Yang, Myung-Duck
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2014.05a
    • /
    • pp.52-53
    • /
    • 2014
  • The Work Breakdown Structure (WBS) is a primary tool which provides a framework that defines clear scope of all deliverables throughout the project life cycle. Once the WBS is established in projects, it should allow project team members to measure and manage work performances by the WBS; further, it should provide a reference point when any work scope needs to be redefined. Based on the project information in the Progress and Performance Measurement System (PPMS) of UAE's Barakha Nuclear Power Plant (BNPP) projects, an attempt was made to develop a new WBS which provides hierarchical and systematical decomposition of the total work scope of NPP construction projects while avoiding from the preexistence concept in Korean NPP projects that the WBS is a combination of Physical Breakdown Structure (PBS) and Functional Breakdown Structure (FBS). The unique features of the new WBS are as follows: (1) defined the definition of each level of the WBS, (2) subdivided the WBS into 5 hierarchical levels, and (3) adopted globally used general coding structure. The new WBS provides a basic hierarchical structure for the project scope and can be used as a basic tool for schedule control, performance measurement, project status monitoring, and communication among project participants. In addition, by putting the Work Package (WP) under the WBS, the Earned Value Management System (EVMS) per WP can be utilized for the project.

  • PDF

Systems Engineering Approach to develop the FPGA based Cyber Security Equipment for Nuclear Power Plant

  • Kim, Jun Sung;Jung, Jae Cheon
    • Journal of the Korean Society of Systems Engineering
    • /
    • v.14 no.2
    • /
    • pp.73-82
    • /
    • 2018
  • In this work, a hardware based cryptographic module for the cyber security of nuclear power plant is developed using a system engineering approach. Nuclear power plants are isolated from the Internet, but as shown in the case of Iran, Man-in-the-middle attacks (MITM) could be a threat to the safety of the nuclear facilities. This FPGA-based module does not have an operating system and it provides protection as a firewall and mitigates the cyber threats. The encryption equipment consists of an encryption module, a decryption module, and interfaces for communication between modules and systems. The Advanced Encryption Standard (AES)-128, which is formally approved as top level by U.S. National Security Agency for cryptographic algorithms, is adopted. The development of the cyber security module is implemented in two main phases: reverse engineering and re-engineering. In the reverse engineering phase, the cyber security plan and system requirements are analyzed, and the AES algorithm is decomposed into functional units. In the re-engineering phase, we model the logical architecture using Vitech CORE9 software and simulate it with the Enhanced Functional Flow Block Diagram (EFFBD), which confirms the performance improvements of the hardware-based cryptographic module as compared to software based cryptography. Following this, the Hardware description language (HDL) code is developed and tested to verify the integrity of the code. Then, the developed code is implemented on the FPGA and connected to the personal computer through Recommended Standard (RS)-232 communication to perform validation of the developed component. For the future work, the developed FPGA based encryption equipment will be verified and validated in its expected operating environment by connecting it to the Advanced power reactor (APR)-1400 simulator.

NPP I&C Architecture Design and Its Traffic Load Analysis

  • Lee, Cheol-Kwon;Kim, Dong-Hoon;Oh, In-Seok;Shin, Jae-Hwal;Yun, Jae-Hee;Sur, Joong-Surk
    • Proceedings of the KIEE Conference
    • /
    • 2005.05a
    • /
    • pp.75-77
    • /
    • 2005
  • An integrated I&C architecture for nuclear power plants is designed by the systems and devices being developed in a project. Its design reference is the APR1400 that was design certified in Korea. Digital equipment and several kinds of data communication networks (DCN) are used. To confirm the validity of DCN based architecture design, the traffic loads fur each network were calculated assuming the anticipated maximum traffic condition. The analysis showed that the utilizations of all networks satisfied the design requirements.

  • PDF

NuSEE: AN INTEGRATED ENVIRONMENT OF SOFTWARE SPECIFICATION AND V&V FOR PLC BASED SAFETYCRITICAL SYSTEMS

  • Koo, Seo-Ryong;Seong, Poong-Hyun;Yoo, Jun-Beom;Cha, Sung-Deok;Youn, Cheong;Han, Hyun-Chul
    • Nuclear Engineering and Technology
    • /
    • v.38 no.3
    • /
    • pp.259-276
    • /
    • 2006
  • As the use of digital systems becomes more prevalent, adequate techniques for software specification and analysis have become increasingly important in nuclear power plant (NPP) safety-critical systems. Additionally, the importance of software verification and validation (V&V) based on adequate specification has received greater emphasis in view of improving software quality. For thorough V&V of safety-critical systems, V&V should be performed throughout the software lifecycle. However, systematic V&V is difficult as it involves many manual-oriented tasks. Tool support is needed in order to more conveniently perform software V&V. In response, we developed four kinds of computer aided software engineering (CASE) tools to support system specification for a formal-based analysis according to the software lifecycle. In this work, we achieved optimized integration of each tool. The toolset, NuSEE, is an integrated environment for software specification and V&V for PLC based safety-critical systems. In accordance with the software lifecycle, NuSEE consists of NuSISRT for the concept phase, NuSRS for the requirements phase, NuSDS for the design phase and NuSCM for configuration management. It is believed that after further development our integrated environment will be a unique and promising software specification and analysis toolset that will support the entire software lifecycle for the development of PLC based NPP safety-critical systems.