Imha Reservoir is connected to Andong Reservoir via a diversion tunnel allowing water to pass between. The diversion tunnel is equipped with screens to exclude exotic largemouth bass due to their predatory impacts on prey assemblages resulting in a degradation of species richness of local fish fauna and extinction of local fish populations in Korea. Flow pattern changes resulting from the fish screens and trash racks were investigated using a computational fluid dynamics (CFD) model. Numerical simulations showed that the decrease in the discharge capacity of the tunnel is approximately 8.6% and the headloss coefficient for fish screen at Andong intake tower was determined to be 1.5. In order not to allow the small fishes enough to pass through the wire openings enter into Imha Reservoir through tunnel, the velocity in the tunnel should be greater than 1.48 m/s which is a critical ascending velocity of the bass. This study suggests that it can keep the velocity higher enough to exclude largemouth bass when a gate opens with the condition of 1.0m difference in water stage between two reservoirs.
This study represents the methodology of performance prediction for small hydro power(SHP) sites. Nine tunnel type SHP sites with diversion dam were selected and the performance characteristics were analyzed by using a developed model. Also, primary design specifications such as design flowrate, plant capacity, and operational rate were suggested and feasibility for tunnel-type SHP sites were estimated. It was found that the design flowrate was most important parameter to exploit SHP plant and the methodology developed in this study was useful tool to analyze the performance of SHP sites.
바쿤 수력발전 프로젝트에서 발전댐의 건설은 가배수로 터널의 완공에 따라 시작되믈 공사기간 측면에서 가배수로 터널의 완공시기는 전체 프로젝트에서 매우 중요한 요소이다. 바쿤 가배수로 터널의 내부단면은 물의 저항을 최대한 줄이기 위하여 원형으로 설계되었으며, 내부직경 12m 인 3개의 터널로 구성되어 있다. 일반적으로 터널 시공과정의 마무리 단계에서 수행되는 터널 라이닝 작업은 굴착 및 지반보강 공정과 더불어 시공비와 공사기간에 많은 영향을 끼치므로 적정한 수준의 라이닝 설계가 요구된다. 바쿤 가배수로 터널에 있어, 라이니으이 두께는현장여건에 따라 다소 차이가 있으나 500~700mm로 타설되었다. 가배수로 터널의 원설계안에 따르면 터널내 전체 라이닝에 필요한 보강콘크리트의 철근량은 5,985 ton 이었으나, 암반의 상태와 여러종류의 하중조건을 고려하여 5종류의 철근 보강 콘크리트 유형으로 구분한 후에 각각의 유형에 따른 상세설계를 통하여 최종적으로 소요 철근량을 2,178 ton으로 감소시킬 수 있었다. 감소된 양은 원설계에서 제시된 양의 절반에 해당되며, 이에 따라 공사기간 및 건설비용을 절감시킬 수 있었다.
Recently severe drought caused the water shortage around the western parts of Chungcheongnamdo province, South Korea. A Diversion tunnel from the Geum river to the Boryong dam, which is the water supply dam for these areas has been proposed to solve this problem. This study examined hydraulic impacts on the Geum river associated with the diversion plan assuming the severe drought condition of 2015 would persist for the simulation period of 2016. The hydraulic simulation model was verified using hydrologic and hydraulic data including hourly discharges of the Geum river and its 8 tributaries, fluctuation of tidal level at the mouth of the river, withdrawals and return flows and operation records of the Geum river barrage since Feb. 1, 2015 through May 31, 2015. For the upstream boundary condition of the Geum river predicted inflow series using the nonlinear regression equation for 2015 discharge data was used. In order to estimate the effects of uncertainty in inflow prediction to the results total four inflow series consisting of upper limit flow, expected flow, lower limit flow and instream flow were used to examine hydraulic impacts of the diversion plan. The simulation showed that in cases of upper limit and expected flows there would be no problem in taking water from the Geum river mouth with a minimum water surface level of EL(+) 1.44 m. Meanwhile, the simulation also showed that in cases of lower limit flow and instream flow there would be some problems not only in taking water for water supply from the mouth of the Geum river but also operating the diversion facility itself with minimum water surface levels of EL(+) 0.94, 0.72, 0.43, and 0.14 m for the lower limit flow without/with diversion and the instream flow without/with diversion, respectively.
The ice damage occurs frequently in cold and dry region of western China in winter ice period and spring thaw period. In the drift ice condition, it is easy to form different extrusion force or impact force to damage tunnel lining, causing project failure. The failure project could not arrive the original planning and construction goal, giving rise to the water allocation pressure which influences diversion irrigation and farming production in spring. This study conducts the theoretical study on contact-impact algorithm of drift ices crashing diversion tunnel based on the symmetric penalty function in finite element theory. ANSYS/LS-DYNA is adopted as the platform to establish tunnel model and drift ice model. LS-DYNA SOLVER is used as the solver and LS-PREPOST is used to do post-processing, analyzing the damage degrees of drift ices on tunnel. Constructing physical model in the experiment to verify and reveal the impact damage mechanism of drift ices on diversion tunnel. The software simulation results and the experiment results show that tunnel lining surface will form varying degree deformation and failure when drift ices crash tunnel lining on different velocity, different plan size and different thickness of drift ice. The researches also show that there are damages of drift ice impact force on tunnel lining in the thawing period in cold and dry region. By long time water scouring, the tunnel lining surfaces are broken and falling off which breaks the strength and stability of the structure.
본 논문에서는 타이 방콕의 지하철 터널현장과 홍수방지용 터널현장에 대한 사례연구를 수행하였다. 첫 번째 사례연구는 복식터널인 방콕 MRT 지하철 현장으로써 터널연장이 대략 20 km이고 18개의 정거장으로 구성되어져 있다. 터널은 지표면으로부터 15~20m 깊이에 위치하는 첫 번째 단단한 실트성 점토층에 위치한다. 현장계측으로부터 얻어진 굴착에 의한 지반의 변위거동이 제시되었다. 평면변형율 유한요소해석을 통하여 역해석을 수행하였으며, 이로부터 나온 결과는 현장에서 계측된 결과와 일치하였다. 유한요소해석으로부터 산정된 전단변형율은 0.1~1.0%의 범위내에 존재하였으며, 자동보링 프래셔미터 시험으로부터 나온 결과와 비슷하였다. 한편, 두 번째 사례연구는 지하 장애물 밑으로 관통하는 EPB타입의 터널공사 현장과 관련이 있다. Premprachakorn 홍수방지용 터널은 장마시기에 홍수를 Choapraya강으로 전환하기 위한 지름길의 터널이다. 터널은 대략 지하 20~24m에 위치한 매우 단단한 실트성 점토층에 EPB타입 쉴드터널공법에 의하여 건설되었다. 터널이 이미 존재하고 있는 방콕의 주된 용수터널과 다리의 기초 아래에서 시공되는 동안에 현장계측이 수행되었으며, 이 계측결과를 유한요소해석으로부터 산정된 결과와 비교하였다. 또한 손상평가를 예측하기 위한 수단으로 방지 리스크 포텐셜 방법을 제시하고 논의하였다.
The 3th International Conference on Construction Engineering and Project Management
/
pp.168-172
/
2009
Shihmen reservoir was started in May 1963. The main purposes of Shihmen reservoir are for agriculture, power supply, flood control and tourism. Shihme Asn dam is an earth dam. Its crown height is 133m above mean sea level, with length 360 m, watershed 763.4 km2, and maximum volume 309 million cms. Turbidity in Shihmen dam was severely affected by typhoons Aere (2004) and Masa (2005). Increased deposition after Aere was 28 million cms. Turbidity at Shihmen Canal Inlet is 3000 NTU (Nephelometry Turbidity Unit). Sediment sluicing strategies for downstream channel are demanded. Therefore, diversionary sediment preventing channel is planned in the upstream of Shihmen reservoir. Finally, turbid flow in tunnel channel is bypassed and diverted its flow down to downstream.
The object of this study is the safety insurance of the dam to provide for the extraordinary flood. The safety insurance of the reservoir was taken by the preparatory discharge using the temporary division tunnel used during the reservoir construction. In this study, the Sungju reservoir was simulated. The existing discharge facilities of the intake tower of the Sungju reservoir could nat have influence on the flood control. When the Sungju reservoir operated to begin preparatory discharge for 48 hrs by the temporary diversion tunnel that have discharge of an 20-years frequency, the water level was lowered about 20 cm. When the Sungju reservoir operated to begin the continuous discharge after the preparatory discharge, the water level was lowered over 1m but the downstream at risk was caused by the resulted. If it is possible to operate to begin the preparatory discharge of the reservoir for 24 hrs by the temporary diversion tunnel, that will improve the flood control faculty of the reservoir without other hydraulic structure and safety of the Sungju reservoir will be higher.
Several remedial works were attempted to stabilize the collapsed area of the inlet slopes of diversion tunnel, but prevention of any further movement was being only carried out at beginning stage by filling the area with aggregates and rock debris, after several cracks had been initiated and developed around the area. The extra specialty developed folding zone is consisted with highly weathered Greywacke and Black shale. The suggested solution is to improve the properties of the rock mass of failed area by choosing the optimum level of reinforcement through the increment of slope rock support design so as to control the movement of slopes during the re-excavation. The Bakun hydroelectric project includes the construction of a hydroelectric power plant with an installed capacity of 2,520MW and a power transmission system connecting to the existing transmission networks in Sarawak and Western Malaysia. The power station will consist of a 210m height Concrete Faced Rockfill Dam. During the construction of the dam and the power facilities the Balui River has to be diverted of the tunnels is 12m and the tunnel width is 16m at the portal area. This paper describes the stability analysis and design methods for the open cut rock slopes in the inlet area of the diversion tunnels. The geotechnical parameters employed in stability calculations were given as a function of four defined Rock Mass Type (RMT) which were based on RMR system from Bieniawski. The stability calculations procedure of the rock slopes are divided into two stages. In the first stage, it is calculated for the stability of each "global" slope without any rock support and shotcrete system. In the second stage, it is calculated for each "local" slope stability with berms and supported with rock bolts and shotcrete. The monitoring instrumentation was performed continuously and some of the design modification was carried out in order to increase the safety of failed area based on the unforeseen geological risks during the open cut excavation.
국내에는 약 18,000여개의 댐이 있는 것으로 보고되고 있다. 이 중에서 대댐으로 분류되는 1,200여개의 대댐은 비교적 양호하게 운영 관리되고 있으나, 지자체 등에서 관리하는 소규모의 댐들은 대부분 제체를 관통하는 복통을 갖고 있으며, 제도적 장치의 미비와 전문 인력의 부족으로 체계적인 유지관리가 거의 이루어지지 않고 있는 실정이다. 본 연구에서는 소규모 댐들에서 자주 발생하는 결함의 유형에 대해서 고찰하고, 결함의 보수보강을 통하여 소규모 댐의 안전을 확보할 수 있는 방법을 제시하고자 한다. 또한, 전기비저항 탐사를 통하여 결함의 진행정도를 파악하고, 보수보강 이후의 보수보강 효과를 판정하는 방법론을 제시하고자 하였다.
본 웹사이트에 게시된 이메일 주소가 전자우편 수집 프로그램이나
그 밖의 기술적 장치를 이용하여 무단으로 수집되는 것을 거부하며,
이를 위반시 정보통신망법에 의해 형사 처벌됨을 유념하시기 바랍니다.
[게시일 2004년 10월 1일]
이용약관
제 1 장 총칙
제 1 조 (목적)
이 이용약관은 KoreaScience 홈페이지(이하 “당 사이트”)에서 제공하는 인터넷 서비스(이하 '서비스')의 가입조건 및 이용에 관한 제반 사항과 기타 필요한 사항을 구체적으로 규정함을 목적으로 합니다.
제 2 조 (용어의 정의)
① "이용자"라 함은 당 사이트에 접속하여 이 약관에 따라 당 사이트가 제공하는 서비스를 받는 회원 및 비회원을
말합니다.
② "회원"이라 함은 서비스를 이용하기 위하여 당 사이트에 개인정보를 제공하여 아이디(ID)와 비밀번호를 부여
받은 자를 말합니다.
③ "회원 아이디(ID)"라 함은 회원의 식별 및 서비스 이용을 위하여 자신이 선정한 문자 및 숫자의 조합을
말합니다.
④ "비밀번호(패스워드)"라 함은 회원이 자신의 비밀보호를 위하여 선정한 문자 및 숫자의 조합을 말합니다.
제 3 조 (이용약관의 효력 및 변경)
① 이 약관은 당 사이트에 게시하거나 기타의 방법으로 회원에게 공지함으로써 효력이 발생합니다.
② 당 사이트는 이 약관을 개정할 경우에 적용일자 및 개정사유를 명시하여 현행 약관과 함께 당 사이트의
초기화면에 그 적용일자 7일 이전부터 적용일자 전일까지 공지합니다. 다만, 회원에게 불리하게 약관내용을
변경하는 경우에는 최소한 30일 이상의 사전 유예기간을 두고 공지합니다. 이 경우 당 사이트는 개정 전
내용과 개정 후 내용을 명확하게 비교하여 이용자가 알기 쉽도록 표시합니다.
제 4 조(약관 외 준칙)
① 이 약관은 당 사이트가 제공하는 서비스에 관한 이용안내와 함께 적용됩니다.
② 이 약관에 명시되지 아니한 사항은 관계법령의 규정이 적용됩니다.
제 2 장 이용계약의 체결
제 5 조 (이용계약의 성립 등)
① 이용계약은 이용고객이 당 사이트가 정한 약관에 「동의합니다」를 선택하고, 당 사이트가 정한
온라인신청양식을 작성하여 서비스 이용을 신청한 후, 당 사이트가 이를 승낙함으로써 성립합니다.
② 제1항의 승낙은 당 사이트가 제공하는 과학기술정보검색, 맞춤정보, 서지정보 등 다른 서비스의 이용승낙을
포함합니다.
제 6 조 (회원가입)
서비스를 이용하고자 하는 고객은 당 사이트에서 정한 회원가입양식에 개인정보를 기재하여 가입을 하여야 합니다.
제 7 조 (개인정보의 보호 및 사용)
당 사이트는 관계법령이 정하는 바에 따라 회원 등록정보를 포함한 회원의 개인정보를 보호하기 위해 노력합니다. 회원 개인정보의 보호 및 사용에 대해서는 관련법령 및 당 사이트의 개인정보 보호정책이 적용됩니다.
제 8 조 (이용 신청의 승낙과 제한)
① 당 사이트는 제6조의 규정에 의한 이용신청고객에 대하여 서비스 이용을 승낙합니다.
② 당 사이트는 아래사항에 해당하는 경우에 대해서 승낙하지 아니 합니다.
- 이용계약 신청서의 내용을 허위로 기재한 경우
- 기타 규정한 제반사항을 위반하며 신청하는 경우
제 9 조 (회원 ID 부여 및 변경 등)
① 당 사이트는 이용고객에 대하여 약관에 정하는 바에 따라 자신이 선정한 회원 ID를 부여합니다.
② 회원 ID는 원칙적으로 변경이 불가하며 부득이한 사유로 인하여 변경 하고자 하는 경우에는 해당 ID를
해지하고 재가입해야 합니다.
③ 기타 회원 개인정보 관리 및 변경 등에 관한 사항은 서비스별 안내에 정하는 바에 의합니다.
제 3 장 계약 당사자의 의무
제 10 조 (KISTI의 의무)
① 당 사이트는 이용고객이 희망한 서비스 제공 개시일에 특별한 사정이 없는 한 서비스를 이용할 수 있도록
하여야 합니다.
② 당 사이트는 개인정보 보호를 위해 보안시스템을 구축하며 개인정보 보호정책을 공시하고 준수합니다.
③ 당 사이트는 회원으로부터 제기되는 의견이나 불만이 정당하다고 객관적으로 인정될 경우에는 적절한 절차를
거쳐 즉시 처리하여야 합니다. 다만, 즉시 처리가 곤란한 경우는 회원에게 그 사유와 처리일정을 통보하여야
합니다.
제 11 조 (회원의 의무)
① 이용자는 회원가입 신청 또는 회원정보 변경 시 실명으로 모든 사항을 사실에 근거하여 작성하여야 하며,
허위 또는 타인의 정보를 등록할 경우 일체의 권리를 주장할 수 없습니다.
② 당 사이트가 관계법령 및 개인정보 보호정책에 의거하여 그 책임을 지는 경우를 제외하고 회원에게 부여된
ID의 비밀번호 관리소홀, 부정사용에 의하여 발생하는 모든 결과에 대한 책임은 회원에게 있습니다.
③ 회원은 당 사이트 및 제 3자의 지적 재산권을 침해해서는 안 됩니다.
제 4 장 서비스의 이용
제 12 조 (서비스 이용 시간)
① 서비스 이용은 당 사이트의 업무상 또는 기술상 특별한 지장이 없는 한 연중무휴, 1일 24시간 운영을
원칙으로 합니다. 단, 당 사이트는 시스템 정기점검, 증설 및 교체를 위해 당 사이트가 정한 날이나 시간에
서비스를 일시 중단할 수 있으며, 예정되어 있는 작업으로 인한 서비스 일시중단은 당 사이트 홈페이지를
통해 사전에 공지합니다.
② 당 사이트는 서비스를 특정범위로 분할하여 각 범위별로 이용가능시간을 별도로 지정할 수 있습니다. 다만
이 경우 그 내용을 공지합니다.
제 13 조 (홈페이지 저작권)
① NDSL에서 제공하는 모든 저작물의 저작권은 원저작자에게 있으며, KISTI는 복제/배포/전송권을 확보하고
있습니다.
② NDSL에서 제공하는 콘텐츠를 상업적 및 기타 영리목적으로 복제/배포/전송할 경우 사전에 KISTI의 허락을
받아야 합니다.
③ NDSL에서 제공하는 콘텐츠를 보도, 비평, 교육, 연구 등을 위하여 정당한 범위 안에서 공정한 관행에
합치되게 인용할 수 있습니다.
④ NDSL에서 제공하는 콘텐츠를 무단 복제, 전송, 배포 기타 저작권법에 위반되는 방법으로 이용할 경우
저작권법 제136조에 따라 5년 이하의 징역 또는 5천만 원 이하의 벌금에 처해질 수 있습니다.
제 14 조 (유료서비스)
① 당 사이트 및 협력기관이 정한 유료서비스(원문복사 등)는 별도로 정해진 바에 따르며, 변경사항은 시행 전에
당 사이트 홈페이지를 통하여 회원에게 공지합니다.
② 유료서비스를 이용하려는 회원은 정해진 요금체계에 따라 요금을 납부해야 합니다.
제 5 장 계약 해지 및 이용 제한
제 15 조 (계약 해지)
회원이 이용계약을 해지하고자 하는 때에는 [가입해지] 메뉴를 이용해 직접 해지해야 합니다.
제 16 조 (서비스 이용제한)
① 당 사이트는 회원이 서비스 이용내용에 있어서 본 약관 제 11조 내용을 위반하거나, 다음 각 호에 해당하는
경우 서비스 이용을 제한할 수 있습니다.
- 2년 이상 서비스를 이용한 적이 없는 경우
- 기타 정상적인 서비스 운영에 방해가 될 경우
② 상기 이용제한 규정에 따라 서비스를 이용하는 회원에게 서비스 이용에 대하여 별도 공지 없이 서비스 이용의
일시정지, 이용계약 해지 할 수 있습니다.
제 17 조 (전자우편주소 수집 금지)
회원은 전자우편주소 추출기 등을 이용하여 전자우편주소를 수집 또는 제3자에게 제공할 수 없습니다.
제 6 장 손해배상 및 기타사항
제 18 조 (손해배상)
당 사이트는 무료로 제공되는 서비스와 관련하여 회원에게 어떠한 손해가 발생하더라도 당 사이트가 고의 또는 과실로 인한 손해발생을 제외하고는 이에 대하여 책임을 부담하지 아니합니다.
제 19 조 (관할 법원)
서비스 이용으로 발생한 분쟁에 대해 소송이 제기되는 경우 민사 소송법상의 관할 법원에 제기합니다.
[부 칙]
1. (시행일) 이 약관은 2016년 9월 5일부터 적용되며, 종전 약관은 본 약관으로 대체되며, 개정된 약관의 적용일 이전 가입자도 개정된 약관의 적용을 받습니다.