• Title/Summary/Keyword: 노르웨이 터널

Search Result 21, Processing Time 0.025 seconds

Norwegian Rock Excavation Technology (노르웨이의 암석굴착 기술)

  • 김민규
    • Tunnel and Underground Space
    • /
    • v.10 no.4
    • /
    • pp.544-552
    • /
    • 2000
  • Norway has the geological of condition of hard bedrocks, high mountains, deep valleys and fjords. In this background many tunnels and rock caverns are developed. In this process of constructing tunnels and rock caverns Norway seems to have strong competitiveness in the construction of tunnels. In spite of high salaries to the tunnel workers, Norwegian contractors are probably producing the cheapest tunnels and rock caverns in the world. Besides benefit of hard-rock geology, Norwegian cost-saying is owing to the Norwegian excavation technique in hard rocks such as unlined pressure tunnels, air cushion chambers, underwater piercing, and reasonable contract system and organization of workers developed from the accumulated experience. Brief analytical description of them are given in this paper in order to stimulate the utilization of the underground spaces.

  • PDF

The $Mer{\aa}ker$ TBM Project in Norway (노르웨이 메로케르 수력발전소의 TBM 굴착)

  • Park Yeonjun;Park Chulwhan
    • Tunnel and Underground Space
    • /
    • v.15 no.1 s.54
    • /
    • pp.22-27
    • /
    • 2005
  • This paper presents an article explaining a TBM project overall in Norway. The paper which published in Norwegian TBM Tunnelling by Norwegian Soil and Rock Eng. Assoc. in 1998, contains most of the items considered in TBM tunnelling. New powerplants, tunnels and dams have been built at Meraker in Central Norway. A total of 44 km of tunnels with cross sections varying from $7\;m^2\;to\;32\;m^2$ have been excavated in hard rock formation. Tunnel of 10 km with the 3.5 m diameter was excavated by a HP TBM in a year. his project gives the special attention to the TBM drive and equipment selection, including planning, site organization and performance.

Norwegian Method of Tunnelling (노르웨이 터널 시공 방법)

  • 김치환;임경호;이석천
    • Proceedings of the Korean Society for Rock Mechanics Conference
    • /
    • 1994.03a
    • /
    • pp.1-11
    • /
    • 1994
  • 현재 국내 터널의 설계와 시공은 대부분 NATM의 원리를 적용하고 있다. 그러나 터널의 설계 접근방법과 시공의 상황을 살펴보면 NATM을 국내 지질에 적용하는 것이 항상 최적이 아니라는 것을 알수 있으며, 국내 터널의 시공에 있어서도 NATM과 다른 개념의 도입과 정확한 이해가 필요하다는 것을 많은 기술자가 느끼고 있다. 따라서 보다 경제적이고 안전한 터널 시공방법의 결정을 위해 NATM의 개념과 다른 터널 설계 및 시공방법으로 노르웨이 터널 시공법(Norwegian Method of Tunnelling, NMT)을 소개하고자 한다. (중략)

  • PDF

Improvement of Tunnelling Speed in Full-Face Mechanical Excavation (기계굴착에서 굴착속도의 발전경향분석)

  • Park, Chul-Whan;Park, Chan;Cheon, Dae-Sung;Synn, Joong-Ho
    • Tunnel and Underground Space
    • /
    • v.17 no.3 s.68
    • /
    • pp.225-233
    • /
    • 2007
  • Because of Norwegian topography as valleys and fjords, a large number of tunnels has been built and 59 of them have been excavated by TBM for last 30 years. Prognosis technology has been developed and improved through lots of TBM experiences, and the NTNU prediction model has been completed. This paper focuses the improvement of net penetration rate and advance rate in 14 Norwegian and 4 Koran TBM tunnelling sites of which data were reported. Through this period, net penetration rate as well as advance rate were increased to double with the improvement of disc cutter size and cutter arrangement in Norway. These rates in Korea were also increased for 15 years even though the rates were lower compared to Norwegian. It is estimated that these low rates were mainly caused by using disc cutters less than 17 inch diameter. It is expected that net penetration rate and advance rate can be increased by improvement of machine and tunnelling technology, especially by using 17 or 19 inch of the disc cutter size in the Korean full face mechanical tunnelling site.

Design of the Oslofjord Subsea Tunnel: A Case Study (노르웨이 Oslofjord 해저터널의 설계경향)

  • Shin, Hee-Soon;Park, Eui-Sub
    • Tunnel and Underground Space
    • /
    • v.17 no.1 s.66
    • /
    • pp.1-8
    • /
    • 2007
  • In Norway, about 30 subsea tunnels have been constructed over the last 20 years. The minimum depth of 17 subsea tunnels is 56 m and rock cover are between 23 and 49 m. As the project areas for subsea tunnel are covered by water, special investigation techniques need to be applied and the investigation results are more uncertain than that of most conventional tunnel projects. The indefinite potential of water inflow and the salinic character of ingress water represent considerable problems for tunnel equipment and rock support materials. The least stable conditions are represented by major faults or weakness zones containing heavily crushed rock and clay gouge. This paper introduces the Oslofjord subsea tunnel project including minimum rock cover requirement, risk of water inflow, investigation costs, construction costs, and traffic & operation costs.

Norwegian Underwater Tunnel Piercing (노르웨이의 수중수로관통 발파 기술)

  • 김민규
    • Explosives and Blasting
    • /
    • v.20 no.1
    • /
    • pp.67-75
    • /
    • 2002
  • 수중수로관통 발파는 수로터널을 호수 바닥에 근접하도록 터널을 뚫고 최종적으로 플러그를 발파하여 수로와 호수 바닥을 연결시키는 발파 기술로서 수력발전에서 경비와 공기를 단축시킬 수 있는 매우 유용한 기술이다. 이 기술은 본질적으로는 수중발파와 동일하지만 완벽한 성공을 보장하기 위한 별도의 조치를 해야하고 수갱의 수문과 여타의 설비를 보전할 수 있는 대책을 강구하여야 한다. 논문에서는 노르웨이에서는 보편화되어 있는 이 기술의 핵심 내용과 적용의 예를 실어 소개하고자 한다.

A Study on the Seismic Performance Evaluation and the Seismic Analysis Method for Pre-Cast Concrete Lining (조립식 터널 라이닝(PCL)의 내진성능 평가 및 해석기법에 대한 고찰)

  • 정형식;배규진;이용준
    • Journal of the Korean Geotechnical Society
    • /
    • v.17 no.5
    • /
    • pp.197-207
    • /
    • 2001
  • 1980년대 이래 국내 터널의 시공법은 원지반의 강성을 활용한 NATM이 주를 이루고 있다. 그러나 NATM은 터널내부에 설치되는 내부라이닝의 여러 가지 문제점을 내포하고 있기 때문에 노르웨이에서는 조립식 터널 라이닝(Pre-Cast Concrete Lining, PCL)을 개발하여 현장타설 콘크리트 라이닝의 문제점을 해결하고자 하였다. 그러나 노르웨이와 같은 북유럽지역에서는 지진이 거의 발생되지 않고 있기 때문에 PCL공법 개발당시에 지진에 대한 영향을 고려하지 못하였다. 따라서 PCL공법을 국내에 도입하기 위해서는 먼저 지진에 대한 영향을 분석하여야 할 것으로 판단되므로 본 연구에서는 PCL공법 적용시 지진에 대한 안정성 평가 및 합리적 내진해석을 위한 연구를 수행하고자 하였다. PCL의 내진성능을 판단하기 위하여 먼저 국내에서 주로 많이 사용되고 있는 해석기법인 유사정적해석법과 응답스펙트럼해석법을 이용하여 분석하였으며 지반과 구조물의 상호작용에 대한 영향을 분석하기 위해 시간이력해석을 수행하여 터널심도별 PCL의 내진성능을 분석하였다. 이와 같은 방법으로 PCL의 내진해석을 수행한 결과, 부재에 발생된 응력이 허용응력 이내에서 발생되어 PCL의 내진성능을 확보된 것으로 판단된다. 또한 시간이력해석에 의한 지반-구조물 해석을 수행한 결과에 의하면 PCL의 내진성능을 확보하기 위한 터널의 최소 토피고가 터널직경에 2배 이상인 것으로 확인되었다. 또한 단순 구조물의 내진해석만으로는 PCL의 내진성능을 과소평가할 우려가 있는 것으로 나타났다.

  • PDF