• Title/Summary/Keyword: 공기지연분석

Search Result 139, Processing Time 0.033 seconds

The Process of Identifying the Responsibility Party of Caused Delay Claim by Ambiguity of the Conditions of the Contract (계약 조항의 애매모호성에 의해서 발생되는 공기지연 클레임의 책임 당사자 확인 프로세스)

  • Lee, Chijoo;Kwan, Taewook;Koh, Hoonsuk
    • Journal of the Korea Institute of Building Construction
    • /
    • v.20 no.6
    • /
    • pp.527-535
    • /
    • 2020
  • This study analyzed main causes of claims in EPC/Turnkey projects. For this purpose, this study referred to the FIDIC silver book, which lists the international standard contract conditions for EPC/Turnkey projects. The most frequent cause of claim was delay. A process was then proposed to determine whether the owner or contractor was the responsible party when the delay claim occurred. The proposed process was for damages for delay which is the conditions of contract for indemnities against delay claim. The process was based on conditions of the contract of two previous EPC/Turnkey projects that were constructed in 2010, the FIDIC silver book, as well as the obligations of owner and contactors. The proposed process is applicable depending on the conditions of the contract and the owner's meaning. Furthermore, by identifying the responsible party, this study will contribute in identifying the possible claim types before concluding a contract and writing the specific contract.

Analysis of Progress Schedule and Delay Element of Frame Works in Apartments (아파트 구체공사의 공정관리 및 공기지연요소 분석에 관한 연구)

  • 최은준;최민권;조형근
    • Proceedings of the Korean Institute of Building Construction Conference
    • /
    • 2003.05a
    • /
    • pp.157-160
    • /
    • 2003
  • In order to reduce the construction cost and period without degrading the quality, construction companies are making a lot of efforts to prefabricate and mechanize the construction process, and introducing and utilizing various techniques of construction time management in the process of construction. However, due to the various factors (such as weather conditions, labor factors, supply of equipment and materials, safety accident, etc) in the process of construction, construction projects are not frequently completed within the scheduled Period. This research is to examine the current status of construction time management and factors causing delay in construction with regard to the concrete work (such as form work, steel reinforcement, and concrete work) in building apartments.

  • PDF

Quantification of Schedule Delay Risk of Rain via Text Mining of a Construction Log (공사일지의 텍스트 마이닝을 통한 우천 공기지연 리스크 정량화)

  • Park, Jongho;Cho, Mingeon;Eom, Sae Ho;Park, Sun-Kyu
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.43 no.1
    • /
    • pp.109-117
    • /
    • 2023
  • Schedule delays present a major risk factor, as they can adversely affect construction projects, such as through increasing construction costs, claims from a client, and/or a decrease in construction quality due to trims to stages to catch up on lost time. Risk management has been conducted according to the importance and priority of schedule delay risk, but quantification of risk on the depth of schedule delay tends to be inadequate due to limitations in data collection. Therefore, this research used the BERT (Bidirectional Encoder Representations from Transformers) language model to convert the contents of aconstruction log, which comprised unstructured data, into WBS (Work Breakdown Structure)-based structured data, and to form a model of classification and quantification of risk. A process was applied to eight highway construction sites, and 75 cases of rain schedule delay risk were obtained from 8 out of 39 detailed work kinds. Through a K-S test, a significant probability distribution was derived for fourkinds of work, and the risk impact was compared. The process presented in this study can be used to derive various schedule delay risks in construction projects and to quantify their depth.

A Study on the Proper Methodology for Clauses of Delay Claim in the Accounting Regulation to Prevent Delay Claims (국내 회계예규상의 공기지연 클레임 관련사항의 개선방안)

  • Kim Jae-Wook;Lee Hak-Ki
    • Proceedings of the Korean Institute Of Construction Engineering and Management
    • /
    • autumn
    • /
    • pp.287-291
    • /
    • 2002
  • A construction claim is generally caused by several causes, and in the case of developed countries, the most fundamental problem in most claims is a delay claim. Also, it is predicted that the trouble will increase by this one in a domestic case as well. Even though the construction claims occurred by the delay claim are the most frequent ill construction project, it is very difficult to analyze due to the complexity of occurring forms. Therefore, the rational judgement and the solving method need to be concerned through the accurate understanding the clauses accepted in a international contract execution and a domestic contrail when the claim occurred. The purpose of this study is to present problems and improving methods by comparing FIDIC with a domestic accounting regulation in order to expand a general condition into the international contract condition.

  • PDF

A Case Study of Delay Analysis for E.P.B Shield TBM Method in Construction Site (E.P.B(Earth Pressure Balance) Shield TBM 공사의 공기지연 사례연구)

  • Kwak, Jun-Hwan;Park, Hyung-Keun
    • KSCE Journal of Civil and Environmental Engineering Research
    • /
    • v.29 no.6D
    • /
    • pp.737-743
    • /
    • 2009
  • Shield TBM, since it was employed for Suyoungman Bay riverbed tunnel of Busan Subway in 2000,has been increasingly adopted in Korea, and in line with growing popularity, the study on Shield TBM has been expanded. However the studies mostly focus on ground condition in a bid to estimate the advancement rate and develop the model for calculating the excavation efficiency, whereas the efforts to analyze the cause of delay and to develop the improvement measures have been neglected. Thus the studies were mostly intended to analyze the schedule slippage focusing on ground conditions, while the study on schedule behind due to equipment itself and related facilities have yet to be attempted in earnest. This study hence was aimed at evaluating the troubles and schedule slippage caused by mechanical elements such as shield TBM equipment and tools and ground conditions, making use of FMEA approach so as to analyze the risk of schedule delay by such elements, thereby proposing the preventive measures to deal with high-risk factors. So, this study suggest the solution to highly ranked trouble factor for the purpose of enhance the efficiency on Shield TBM.

A Case Study on Reason Analysis for Schedule Delay of Apartment House (공동주택의 공기지연 원인분석 사레 연구)

  • Park, Chang-Wook;Yun, Seok-Heon
    • Journal of the Korea Institute of Building Construction
    • /
    • v.9 no.1
    • /
    • pp.89-94
    • /
    • 2009
  • A study was performed the analysis for the schedule delay of the public housing. To perform this study, the first study existing research literature on the cause of the schedule delay was considered. The based on existing study, this study selected the cause of schedule delay. For check of the schedule delay, this study was compared the monthly schedule and the work diary. Survey was conducted for using the selected cause of schedule delay. And the importance was calculated for using the AHP method. In a case site, the cause of the schedule delay was analyzed. The last, the delay cause was presented the map of cause of effect the based on the delay cause of a case site.

A Liquidated Damages Calculation Method Based on Owner's Substantial Loss (발주자 손실기반 지체상금 산정 개선방안)

  • Jang, Bong-Jo;Shim, Jae-Young;Koo, Jeong-San;Jung, Dae-Won;Koo, Kyo-Jin;Hyun, Chang-Taek
    • Korean Journal of Construction Engineering and Management
    • /
    • v.8 no.1 s.35
    • /
    • pp.150-158
    • /
    • 2007
  • The delay of construction is one of the most frequent and complicated elements of the claim. And the liquidated damages cause many disputes during the judgement. The liquidated damages should be a compensation for owner's substantial loss, but actually be applied as a damage for breach of contract. These damages are different from owner's loss and give constructors a excessive burden. So we need a more reasonable system than a lump application system. In this study, we make a Improvement System, that based on owner's substantial loss, and suggest the new liquidated damages calculation method.

The Calculation Method for Prolongation cost of Sub-Constract in Domestic Public Construction Project (국내 공공 공사 하도급계약 공기연장 추가간접비 산정방안)

  • Jeong, Kichang;Lee, Jaeseob
    • Korean Journal of Construction Engineering and Management
    • /
    • v.19 no.4
    • /
    • pp.61-69
    • /
    • 2018
  • Research on additional indirect cost due to construction period extension in general contracts has continuously been active whereas the same for the subcontract operations has not been. In this research, we review previous research on evaluation methods for additional indirect costs which are widely being used on construction sites as well as previously proposed methods altogether, applying them to analyze model-cases for comparison. We acknowledge that this pattern for construction cost fluctuation over the construction period demonstrates an S-curve. This S-curve shaped indirect cost occurrence is then used to generate model-cases that are used throughout the research which models we applied previous evaluation methods on. Finally in pursuit of finding out some problems of evaluation methods, we came to derive a conclusion that the "Average Actual Cost Evaluation Method on Extended Duration," which, in turn, were proved to be valid for application on general contracts, was also valid for general application on subcontractor operations.

A Numerical Analysis of Acoustic-Pressure Response of H2-Air Diffusion Flames with Application of Time-Lag Model (시간지연 모델의 적용을 통한 수소/공기 확산화염의 음향파 응답 분석)

  • Sohn, Chae-Hoon;Lim, Jun-Seok
    • Journal of the Korean Society of Propulsion Engineers
    • /
    • v.16 no.1
    • /
    • pp.1-8
    • /
    • 2012
  • Acoustic-pressure response of diluted hydrogen-air diffusion flames is investigated numerically by adopting a fully unsteady analysis of flame structures in low and high pressure regimes. As acoustic frequency increases, finite-rate chemistry is enhanced through a nonlinear accumulation of heat release rate for any pressure regime, leading to a high amplification index. Same numerical results are analyzed with application of a pressure-sensitive time lag model, and thereby, interaction index and time lag are calculated for each pressure regime. The interaction index has the largest value in each pressure regime at an acoustic frequency near 1000 Hz. In a high-pressure regime, flames are more unstable than in a low-pressure regime. The interaction index shows a good agreement with the amplification index.