A Case Study on the Prevention of Construction Delays Using the Delay Management Index in Program Level Construction Projects

프로그램 수준 건설사업에서 지연관리지수(Delay Management Index)를 활용한 공사지연 예방 사례연구

  • Yu, Jun-Hyeok (Department of Architectural Engineering, Chungbuk University) ;
  • Kim, Ok-Kyue (Department of Architectural Engineering, Chungbuk University)
  • Received : 2021.07.20
  • Accepted : 2021.08.10
  • Published : 2021.08.20

Abstract

Recently, construction projects have emerged in the form of program management, which is complicated by the large-scale of construction, and requires astronomical construction costs. In particular, projects that absolutely require management at the program level, such as large-scale construction projects, require overall control of the planned schedule and cost as a set of various projects, including infrastructure. But in Korea, there is no specific management standard for delays in construction. In order to avoid the risk of cost increase and project delay in the program-level construction project, it is necessary to apply more systematic management standards to prevent delay and to take a more preemptive response in the construction process. Therefore, in this study, a delay management index (DMI) was developed to successfully carry out large-scale construction projects at the program level and prevent delays in advance. In addition, case studies were conducted for large-scale construction projects, and a delay prevention system was established for program-level construction projects.

최근 건설공사는 초대형화로 단일 공사규모가 복잡해지고 천문학적인 공사비가 소요되는 프로그램 관리 형태의 성격을 지니는 사업이 등장하고 있다. 특히, 대규모 건설사업과 같이 프로그램 수준에서 관리가 절대적으로 필요한 사업은 계획된 일정 및 비용에 대한 전제적인 관리가 필요하다. 하지만 국내의 경우 구체적인 공사지연에 관한 관리기준이 부재한 현실이다. 이에 본 연구에서는 대규모, 장기간 진행되는 프로그램 수준의 대규모 건설사업을 성공적으로 수행하고 공정지연 및 부진사업을 사전에 방지하기 위한 지연관리지수(Delay Management Index, DMI)를 개발하였다. 이를 통해 대규모 복합건설 프로젝트를 대상으로 사례연구를 수행하였으며, 프로그램 수준 건설사업을 위한 지연예방체계를 구축하였다.

Keywords

References

  1. Lee KC. Program management of the Incheon International Airport construction project(phase1). Korean Journal of Construction Engineering and Management. 2020 Jun;21(3):9-13.
  2. Back MC, Yoon YD. Introduction to program management of the USFK base relocation project. Korean Journal of Construction Engineering and Management. 2019 Jun;20(3):9-13.
  3. Yoo KH. Program management of the Sejong city construction. Korean Journal of Construction Engineering and Management. 2020 Jun;21(3):14-8.
  4. Han JK, Chin SY, Kim YS. An analysis on delay factors of major trades in apartment housing projects. Journal of the Architectural Institute of Korea. 2003 Mar;19(3):163-70.
  5. Ji KC, Yu JH, Kim CD. The root cause analysis process for schedule delay in construction. Korean Journal of Construction Engineering and Management. 2006 Oct;7(5):138-48.
  6. Lee HC, Lee JH, Go SS. A study on the priority analysis of work delay factors in steal-frame work using FMEA. Korean Journal of Construction Engineering and Management. 2009 Jan;10(1):91-101.
  7. Lim GJ, Son CB. An analysis on the delay influence factors in apartment construction site. Journal of the Architectural Institute of Korea Structure & Construction. 2017 Sep;33(9):43-50. https://doi.org/10.5659/JAIK_SC.2017.33.9.43
  8. Ahn SH, Yu JH, Kim CD. An analysis on work delay factors in apartment house construction. Korean Journal of Construction Engineering ans Management. 2007 Dec;8(6):159-66.
  9. Lee HC, Lim SY, Yeo SK, Go SS. A study on the work delay factors of reinforced concrete work in apartment house construction. Journal of the Korea Institute of Building Construction. 2009 Apr;9(2):55-61. https://doi.org/10.5345/JKIC.2009.9.2.055
  10. Park CW, Yun SH. A case study on reason analysis for schedule delay of apartment house. Journal of the Korea Institute of Building Construction. 2009 Feb;9(1):89-94. https://doi.org/10.5345/JKIC.2009.9.1.089
  11. Lee SH, Kim YM, Kim JH, Kim JJ. Analysis of delay factors based on importance of construction subject-classified in apartment finishing works. Journal of the Korea Institute of Building Construction. 2011 Feb;11(1):73-81. https://doi.org/10.5345/JKIC.2011.02.1.073
  12. Ryu HG, Yu JH, Lee HS. A method of calculating schedule delay considering lost productivity. Journal of the Architectural Institute of Korea Structure & Construction. 2002 Oct;18(10):117-24.
  13. Kim YJ, Hong JS, Kim KR, Shin DW. An analysis method for the concurrent delay using delay section concept. Journal of the Architectural Institute of Korea Structure & Construction. 2004 Jun;20(6):141-8.
  14. Koo JM, Lee JS. Construction delay analysis method considering productivity. Journal of the Architectural Institute of Korea. 2004 Apr;20(4):147-54.
  15. Lee JS. Delay analysis using learning effect and linear scheduling in construction. Journal of the Architectural Institute of Korea Structure & Construction. 2008 May;24(5):185-92.
  16. Kim YJ, Kim TK, Jo DS, Lee HK. A study on substantiation methodology for extension of time in international mega-project claims. Korean Journal of Construction Engineering and Management. 2015 May;16(3):165-76. https://doi.org/10.6106/KJCEM.2015.16.3.165
  17. Kim SG, Kwon SW. Case analysis on application of project delay analysis method in domestic construction project. Korean Journal of Construction Engineering and Management. 2019 Nov;20(6):98-106. https://doi.org/10.6106/KJCEM.2019.20.6.098