A Case Study on the Prevention of Construction Delays Using the Delay Management Index in Program Level Construction Projects  

Yu, Jun-Hyeok (Department of Architectural Engineering, Chungbuk University)
Kim, Ok-Kyue (Department of Architectural Engineering, Chungbuk University)
Publication Information
Journal of the Korea Institute of Building Construction / v.21, no.4, 2021 , pp. 347-359 More about this Journal
Abstract
Recently, construction projects have emerged in the form of program management, which is complicated by the large-scale of construction, and requires astronomical construction costs. In particular, projects that absolutely require management at the program level, such as large-scale construction projects, require overall control of the planned schedule and cost as a set of various projects, including infrastructure. But in Korea, there is no specific management standard for delays in construction. In order to avoid the risk of cost increase and project delay in the program-level construction project, it is necessary to apply more systematic management standards to prevent delay and to take a more preemptive response in the construction process. Therefore, in this study, a delay management index (DMI) was developed to successfully carry out large-scale construction projects at the program level and prevent delays in advance. In addition, case studies were conducted for large-scale construction projects, and a delay prevention system was established for program-level construction projects.
Keywords
delay prevention; delay management index; program management; large-scale construction;
Citations & Related Records
Times Cited By KSCI : 4  (Citation Analysis)
연도 인용수 순위
1 Lee KC. Program management of the Incheon International Airport construction project(phase1). Korean Journal of Construction Engineering and Management. 2020 Jun;21(3):9-13.
2 Back MC, Yoon YD. Introduction to program management of the USFK base relocation project. Korean Journal of Construction Engineering and Management. 2019 Jun;20(3):9-13.
3 Ji KC, Yu JH, Kim CD. The root cause analysis process for schedule delay in construction. Korean Journal of Construction Engineering and Management. 2006 Oct;7(5):138-48.
4 Lim GJ, Son CB. An analysis on the delay influence factors in apartment construction site. Journal of the Architectural Institute of Korea Structure & Construction. 2017 Sep;33(9):43-50. https://doi.org/10.5659/JAIK_SC.2017.33.9.43   DOI
5 Ahn SH, Yu JH, Kim CD. An analysis on work delay factors in apartment house construction. Korean Journal of Construction Engineering ans Management. 2007 Dec;8(6):159-66.
6 Park CW, Yun SH. A case study on reason analysis for schedule delay of apartment house. Journal of the Korea Institute of Building Construction. 2009 Feb;9(1):89-94. https://doi.org/10.5345/JKIC.2009.9.1.089   DOI
7 Kim YJ, Hong JS, Kim KR, Shin DW. An analysis method for the concurrent delay using delay section concept. Journal of the Architectural Institute of Korea Structure & Construction. 2004 Jun;20(6):141-8.
8 Koo JM, Lee JS. Construction delay analysis method considering productivity. Journal of the Architectural Institute of Korea. 2004 Apr;20(4):147-54.
9 Kim YJ, Kim TK, Jo DS, Lee HK. A study on substantiation methodology for extension of time in international mega-project claims. Korean Journal of Construction Engineering and Management. 2015 May;16(3):165-76. https://doi.org/10.6106/KJCEM.2015.16.3.165   DOI
10 Yoo KH. Program management of the Sejong city construction. Korean Journal of Construction Engineering and Management. 2020 Jun;21(3):14-8.
11 Lee HC, Lee JH, Go SS. A study on the priority analysis of work delay factors in steal-frame work using FMEA. Korean Journal of Construction Engineering and Management. 2009 Jan;10(1):91-101.
12 Lee HC, Lim SY, Yeo SK, Go SS. A study on the work delay factors of reinforced concrete work in apartment house construction. Journal of the Korea Institute of Building Construction. 2009 Apr;9(2):55-61. https://doi.org/10.5345/JKIC.2009.9.2.055   DOI
13 Kim SG, Kwon SW. Case analysis on application of project delay analysis method in domestic construction project. Korean Journal of Construction Engineering and Management. 2019 Nov;20(6):98-106. https://doi.org/10.6106/KJCEM.2019.20.6.098   DOI
14 Ryu HG, Yu JH, Lee HS. A method of calculating schedule delay considering lost productivity. Journal of the Architectural Institute of Korea Structure & Construction. 2002 Oct;18(10):117-24.
15 Lee JS. Delay analysis using learning effect and linear scheduling in construction. Journal of the Architectural Institute of Korea Structure & Construction. 2008 May;24(5):185-92.
16 Lee SH, Kim YM, Kim JH, Kim JJ. Analysis of delay factors based on importance of construction subject-classified in apartment finishing works. Journal of the Korea Institute of Building Construction. 2011 Feb;11(1):73-81. https://doi.org/10.5345/JKIC.2011.02.1.073   DOI
17 Han JK, Chin SY, Kim YS. An analysis on delay factors of major trades in apartment housing projects. Journal of the Architectural Institute of Korea. 2003 Mar;19(3):163-70.