Abstract
The productivity of rebar-work and form-work was analyzed with data collected from an actual high-rise construction project, and the actual utilization rates of three tower cranes were also investigated. It was found that the average productivity of the form-work increased from 12.00~8.71(㎡/man·day) in the underground and above-ground/lower-floor to 11.94~20.73(㎡/man·day) in the standard floor. Comparing the productivity of core area to outer, the former was found to be about 11% higher. Moreover, the rebar-work productivity of the outer area(1.12 ton/man·day) was approximately 9.6% higher than that of the core area for the standard floor. The average utilization rates of three TC were surveyed to be about 63.49%, and it was revealed that rainy weather(6.1%), strong winds(6.1%), holidays(17.8%), TC lifting work(5.8%), and other failures and repairs(0.07%) were the causes of non-operation. These research results are expected to be beneficial data in planning and managing the process of high-rise RC construction works in the future.
초고층 건설사업의 골조 공사를 대상으로 철근, 형틀 작업의 생산성을 분석하고 타워 크레인(Tower Crane; TC)의 실질적인 가동률을 조사하였다. 코어부의 형틀작업 생산성은 지하 및 지상·저층부(1~7F) 구간에서는 평균 12.0~8.7(㎡/인·일)로, 기준층 구간(8~75F) 으로 진행될수록 11.9~20.7(㎡/인·일)로 생산성이 향상되는 것으로 분석되었다. 코어와 외주부의 기준층 생산성을 비교해보면 코어 생산성이 약 11% 정도 높은 것으로 나타났다. 또한 기준층의 코어부위 철근작업 생산성(평균 1.02 ton/인·일) 대비 외주부(기준층 평균 1.12 ton/인·일)의 생산성은 대략 9.6% 높은 결과가 도출되었다. 또한, TC 세 대의 평균 가동률은 63.49%로 조사되었으며, 비가동일의 원인으로는 우천 6.1%, 강풍 6.1%, 휴무 17.8%, TC 인상작업 5.8%, 기타 고장 및 수리 등이 0.07% 인 것으로 분석되었다. 이러한 연구결과는 향후 초고층 골조 공사의 공정을 계획하고 관리함에 있어 유용한 자료가 될 것으로 기대된다.