Productivity Analysis of Reinforced Concrete Works and Tower Crane Working Ratio for High-rise Apartment Buildings  

Kwon, Jihun (POSCO E&C)
Huh, Youngki (Department of Architectural Engineering, Pusan National University)
Publication Information
Korean Journal of Construction Engineering and Management / v.22, no.1, 2021 , pp. 55-62 More about this Journal
Abstract
The productivity of rebar-work and form-work was analyzed with data collected from an actual high-rise construction project, and the actual utilization rates of three tower cranes were also investigated. It was found that the average productivity of the form-work increased from 12.00~8.71(㎡/man·day) in the underground and above-ground/lower-floor to 11.94~20.73(㎡/man·day) in the standard floor. Comparing the productivity of core area to outer, the former was found to be about 11% higher. Moreover, the rebar-work productivity of the outer area(1.12 ton/man·day) was approximately 9.6% higher than that of the core area for the standard floor. The average utilization rates of three TC were surveyed to be about 63.49%, and it was revealed that rainy weather(6.1%), strong winds(6.1%), holidays(17.8%), TC lifting work(5.8%), and other failures and repairs(0.07%) were the causes of non-operation. These research results are expected to be beneficial data in planning and managing the process of high-rise RC construction works in the future.
Keywords
Productivity; High-rise Building; RC Work; Tower Crane Utilization Rate; Factor;
Citations & Related Records
연도 인용수 순위
  • Reference
1 Jang, J.S., Shin, Y.S., and Kang, K.I. (2005) "A Work Process for Productivity Improvement of Concrete Structural Frame Work in Tall Building." Proceedings of the Korea Institute of Building Construction, pp. 161-164.
2 Kim, T.H., Shin, Y.S., Cho, S.S., and Kang, K.I. (2007). "The Productivity Analysis by Slab Formwork of Structural Frame Work in Tall Building Construction - Focused on 3 Day Cyce-." Proceedings of the Korea Institute of Building Construction, pp. 115-118.
3 Kim, Y.S. (1994). "Analysis of the Factors Influencing Construction Productivity." Korean Journal of Construction Engineering and Management, KICEM, 1(10), pp. 65-74.
4 Lee, K.J., and Kim, Y.S. (2010). "An Importance Analysis for the Major Schedule Management Factors Classified by Construction Participants in High-rise Building Reinforced Concrete Work." Journal of the Architectural Institute of Korea Structure & Construction, 26(12), pp. 185-192.
5 Son, C.B., and Lee, D.C. (2005). "An Analysis on the Selection and Application of Productivity Improving Factors in Apartment Building Construction." Journal of the Architectural Institute of Korea Structure & Construction, 21(4), pp. 133-140.
6 Son, C.B., and Lee, D.C. (2002). "An Analysis on the Factors Decreasing Productivity of Building Construction." Journal of the Architectural Institute of Korea Structure & Construction, 18(12), pp. 125-132.
7 Son, J.W., Yoon, J.S., and Paek, J.H. (2003). "A Study on Construction Productivity Measurement Method." Journal of the Architectural Institute of Korea Structure & Construction, 19(10), pp. 101-108.