Abstract
In construction project, an error in quantity information immediately leads to an error in the quotation, highly reliable quantity calculation is required for successful performance of a project. But there is a difficulty in the current situation for the person in charge to review all calculation sheets for quantity review as the quotation work has to be performed in a short period of time. Accordingly, it is thought that a review plan is required to secure reliability on calculated results and the review plan should be able to be carried out within insufficient quotation periods. In the present paper, it is intended to present a plan that enables quantity to be reviewed with the minimum number of persons within the shortest period of time through an algorithm of calculating a verification quantity. The suggested algorithm allows the result of quantity calculation work carried out earlier based on 2-dimensional drawing to be compared, not with an accurate quantity, but within an error range.
견적업무는 공사비를 산출하는 것을 목적으로 수행되며, 단가정보와 물량정보의 곱으로 산출되므로 성공적인 건설 프로젝트의 수행을 위해 정확한 물량산출이 선행되어야 한다. 또한 현재 견적 전문가를 대상으로 한 설문조사에 의하면, 물량산출 성과물에 대한 만족도가 높음에도 불구하고 이에 대한 검증작업이 필요하다는 의견이 다수이다. 그러나 현재는 견적 작업자의 경험도에 의존하는 등 객관적인 검증방안이 미비한 실정이다. 따라서 본 연구는 작업자 개개인의 업무능력에 의존하지 않고 검증할 수 있는 검증방안을 제안하였다. 제안하는 검증방안은 산출서 물량과 비교하여 ±5%의 오차를 가지는 검증물량을 산출하여 산출한 물량에 대한 가이드 라인을 제시하였다. 이를 위해 기존에 수행된 프로젝트 데이터를 활용하여 도면 및 산출서를 분석하고, 도면으로부터 정보를 추출하여 검증물량을 산출할 수 있는 산식을 개발하여 검증물량산출 산식이라고 정의하였다. 본 연구의 결과인 검증물량산출 산식은 최단기간 내에 최소인원으로 물량산출 성과물에 대한 검증업무를 수행할 수 있게 하는 것을 목적으로 한다. 이로 인해 작업자가 산출한 물량에 대한 신뢰도를 확보할 수 있을 것으로 생각되며, 오류가 발생한 항목에 대한 검토가 수행됨에 따라 효율적인 견적업무가 가능하게 될 것으로 기대된다.