Fig. 1. Procedure of progress management in defense R&D project
Fig. 2. Example of project progress index
Fig. 3. Leveraging ESM concept
Fig. 4. SPI and SEAC over the entire duration of a specific project
Fig. 5. SPI quarterly comparison before project extension point
Fig. 6. MAPE quarterly comparison before project extension point
Table 1. Estimate formula in EVM
Table 2. Project schedule/budget adjustment status for last 5 years
Table 3. Schedule performance indicator
Table 4. Example of comparison between PPI and SPIPPM
Table 5. Schedule estimate at completion(SEAC)
Table 6. Performance factor of SEAC
Table 7. Number of delayed projects for verification
References
- Whitehouse, G. E., “Project Management Techniques,” Industrial Engineer, Vol. 5, No. 3, pp. 24-29, 1973.
- "Program Evaluation Research Task, Summary Report," Government Printing Office, Washington, D. C., USA, pp. 1-118, 1958.
- Q. W. Fleming and J. M. Koppelman, "Earned Value Project Management - 3rd edition," Project Management Institute Inc. USA, pp. 54-60, 2005.
- Jaewon Kim, et. al., "Proposal of the Project Management Procedure," Research & Development Report, RDPD-405-011428, Agency for Defense Development, Korea, pp. 138-142, 2001.
- "Yearly Project Planning Guidance," Regulation No. 297, Agency for Defense Development, Korea, October, pp. 1-11, 2008.
- "Quarterly Evaluation Analysis Task Guidance," Regulation No. 296, Agency for Defense Development, Korea, October, pp. 1-19, 2008.
- "Scientific Project Management Execution Guidance," Regulation No. 367, Defense Acquisition Program Administration, Korea, March, pp. 1-22, 2017.
- H. Jeon, et. al., "EVM Application Upgrade Plan," Security Management Institute, pp. 74-84, October, 2017.
- Walt Lipke, "Schedule is Different," The Measurable News, pp. 31-34, Summer, 2003.
- J. Cho and J. Lim, “An Analysis of Effect and Limitation when Adapting Earned Schedule Method for Schedule Management and Estimation in Korean Defense Research & Development Projects,” Journal of the Korea Institute of Military Science and Technology, Vol. 21, No. 3, pp. 396-402, 2018. https://doi.org/10.9766/KIMST.2018.21.3.396
- Jungho Cho and Jungyu Park, "A Comparison Analysis between SPI in EVM Techniques and Rate of Progress for Project in ADD," KIMST Annual Conference Proceedings, pp. 1508-1509, June, 2016.
- Suqrat Babar, et. al., "Estimated Cost at Completion: Integrating Risk into Earned Value Management," Journal of Construction Engineering and Management, Vol. 143, No. 3, 04016104, pp. 1-11, 2017.
- Jordy Batselier and Mario Vanhoucke, "Empirical Evaluation of Earned Value Management Forecasting Accuracy for Time and Cost," Journal of Construction Engineering and Management, Vol. 141, No. 11, 05015010, pp. 1-13, 2015.
- Stephan Vandevoorde and Mario Vanhoucke, “A Comparison of Different Project Duration Forecasting Methods using Earned Value Metrics,” International Journal of Project Management, Vol. 24, No. 4, pp. 289-302, 2006. https://doi.org/10.1016/j.ijproman.2005.10.004
- Steven Nahmias and Tava Lennon Olsen, "Production and Operations Analysis : 7th edition," Waveland Press Inc. USA, pp. 62-66, 2015.
- "Earned Value Management Systems EIA-748-D Intent Guide," National Defense Industrial Association, August, pp. 1-56, 2018.