CM at Risk Case Study on Guaranteed Maximum Price Contract - Focused on Cases for USA -

책임형 CM 발주방식의 최대공사비보증계약 사례연구 - 미국 공공발주 프로젝트 사례 중심 -

  • Jeong, Jinhak (Department of Architectural Engineering, Hanyang University) ;
  • Han, Jonghoon (Department of Architectural Engineering, Hanyang University) ;
  • Lee, Joosung (Department of Architectural Engineering, Hanyang University) ;
  • Ahn, Yonghan (Department of Architecture, Hanyang University)
  • Received : 2018.11.14
  • Accepted : 2018.12.11
  • Published : 2019.05.31

Abstract

The purpose of this study is to derive basic data of the Guaranteed Maximum Price(GMP) process and to present specimens that can be used at the time of execution of CM at Risk project in South Korea. CM at Risk project is issued in South Korea, but the actual data is lack. On the other hand, CM at Risk project is universalized and the market of the CM at Risk is steadily growing. Because of that, in this study, The United States cases was selected as a sample. GMP consists of CM's fee, CM contingency, project direct cost, project indirect cost, allowance. GMP negotiations are performed before the end of design completion, and after 3 rounds of estimation comparison, preliminary GMP is confirmed. GMP can be multiple contract and it is useful for Procurement of long lead materials and early construction. If the actual cost is lower than expected GMP, sharing of the saving is an option since the conflict of interests between the client and the contractor can occur.

최근 건설 사업이 복잡해지고 대형화 되며 발주자의 요구사항 또한 다양해지고 있다. 그에 따라 책임형 CM 발주방식이 대두되었지만 국내 책임형 CM 프로젝트 수행사례는 민간 부분에서만 몇 차례 진행되었고 국내의 건설사의 프로젝트 경험 및 자료도 부족한 실정이다. 또한 건설 프로젝트는 다수의 프로젝트 주체들이 가시화 되지 않은 결과물에 대한 목적, 기간, 비용, 각 당사자의 권리와 책임, 이익 등을 합의하여 계약으로 명문화 하는 특성을 갖기 때문에 계약서의 작성 및 관리는 계약의 목적물인 프로젝트의 성공적 수행과 매우 밀접한 관계가 있다. 따라서 본 연구에서는 책임형 CM 발주방식이 보편화 되어있는 미국의 사례 중 GMP 계약 방식으로 수행된 프로젝트의 계약서에 대해 고찰하여 GMP 구성요소 및 프로세스에 대한 공통 요소를 도출하고 국내 책임형 CM 프로젝트 수행 시 이용 될 수 있는 기초자료를 제안 하였다. 본 연구에서 도출해 낸 GMP구성 요소 및 프로세스는 국내 시범사업이 완료된 이후에 국내와 해외 사례를 비교 분석하여 국내에 효과적인 적용 법에 대한 추후 연구가 진행 될 수 있을 거라 판단된다. 또한 건축물 종류별 GMP 요소를 비교하여 건물 종류별 적합한 적용 법에 대한 연구도 진행 될 수 있을 것이라 사료된다.

Keywords

Table 1. Literature Review

GGRHC4_2019_v20n3_22_t0001.png 이미지

Table 2. Sample Case Summary

GGRHC4_2019_v20n3_22_t0002.png 이미지

Table 3. CM Fee Case Study

GGRHC4_2019_v20n3_22_t0003.png 이미지

Table 4. CM Contingency Case Study

GGRHC4_2019_v20n3_22_t0004.png 이미지

Table 5. Allowance Case Study

GGRHC4_2019_v20n3_22_t0005.png 이미지

Table 6. Negotiation phase and alternative negotiation

GGRHC4_2019_v20n3_22_t0006.png 이미지

Table 7. Advantage and Consideration of Multiple GMP

GGRHC4_2019_v20n3_22_t0007.png 이미지

Table 8. GMP Contract Method

GGRHC4_2019_v20n3_22_t0008.png 이미지

Table 9. Savings Sharing and incentive

GGRHC4_2019_v20n3_22_t0009.png 이미지

Table 10. GMP component and process of Case

GGRHC4_2019_v20n3_22_t0010.png 이미지

Table 11. Suggestion of GMP

GGRHC4_2019_v20n3_22_t0011.png 이미지

References

  1. Ahn, Y.H. (2013). "CM at Risk Delivery Method in US Public Construction." Construction Enginerring and Management, pp. 69-72.
  2. Byambadorj, T. (2012). "A Study of Factors that Caused 'CM at Risk's Inactivity and Proposal for the System Improvement." M.S. Dissertation, Department of Architecture, Soongsil University, pp. 1-44.
  3. Colin, R. (2002). Real World Research. 2nd ed, Blackwell Publishers, pp. 220-223.
  4. Gustafsson, H., Kentta, G., Hassmen, P., Lundqvist, C., and Durand, N. (2007). "The Process of burnout : A Multiple Case Study of Three Elite Endurance Athletes." International Journal of Sport Psychology, EDIZIONE L POZZI, 38(4), pp. 388-416.
  5. Hyun, C.T., Go, G.H., and Kim, Z.H. (2018). "Probabilistic Earlier GMP Calculation Method for Apartment Using CM at Risk." Building Construction, The Korea Institute of Building Construction, 18(3), pp. 295-303.
  6. Jang, C.K., Lee, B.N., Choi, S.I., and Lee, D.K. (2006). "Understanding of CM at Risk and Diagnosis of introduction Possibility." Research Report, Consruction and Economy Research Institute of Korea, 2006(5), pp. 1-130.
  7. Kim, S.R., Lee, S.H., and Ahn, Y.H. (2016). "GMP Process of Cm at Risk Delivery Method for Construction Company of USA." Proceeding of Annual Conference, Architectural Institute of Korea, 36(2), pp. 1058-1059.
  8. Kim, E.J., and Yu, I.H., (2015). "Suggestions to Improve the System for Introducing CM at Risk System of Specialty Construction Contractors." Journal of the Regional Association of Architectural Institute of Korea, Architectural Institute of Korea, 17(2), pp. 129-136.
  9. Kim, J.H. (2010). "An Analysis about Factors Affecting Inactiveness of CM at Risk at Korean Construction Industry." M.S. Dissertation, Department of Construction Management, Hanyang University, pp. 1-4.
  10. Kim, J.G., Jung, J.H., and Lee, H.K. (2009). "The Corresponding Plan of Construction Enterprise for the Introduction of CM at Risk." Journal of the Regional Association of Architectural Institute of Korea, Architectural Institute of Korea, 11(1), pp. 159-166.
  11. Koo, S.K. (2017). "Risk Factor Assessment for Guaranteed Maximum Price Contract in CM at Risk." M.S. Dissertation, Graduate School, University of Seoul, pp. 1-94.
  12. Lee, S.H., and Ahn, Y.H. (2016). "Valuing the Guaranteed Maximum Price(GMP) Contract of the Cm at Risk." AIK 2016 Proceeding, Architectural Institute of Korea, 36(2), pp. 1054-1055.
  13. Lee, I.H. (2008). "A Study on Application Plan of Separate Procurement Concept through CM at Risk." M.S. Dissertation, International School of Urban Science, University of Seoul, pp. 10-13.
  14. Matt, F., Scott, G., and Caroline, M. (2015). "Benefits of Owner mandated CM/GC Contract Amendment Templates." Journal of Facilities Management, Heads of Facilites and Corporate Real Estate, 13(3), pp. 282-296.
  15. Ministry of Land infrastructure and Transport (Molit). (2011). "Framework Act on the Construction Industry." (Aug, 20, 2018).
  16. Park, K.M., and Kim, C.D. (2016). "Improvement through Analysis of Current Open Book Policy for the Korean CM at Risk." Korean Journal of Construction Engineering and Management, KICEM, 17(2), pp. 3-11. https://doi.org/10.6106/KJCEM.2016.17.2.003
  17. Seo, S.J., Kim, Y.H., Lyu, H.S., and Chung, J.B. (2011). "The Establishment and Operation of the National Public Architecture Center." Reserach Report, Architecture and Urban Research Institute, pp. 22-41.
  18. Son, K.N. (2018). "Importance analysis of obstacle factors on the Cm at Risk project using AHP method." M.S Dissertation, Department of Construction Management, Hanyang University, pp. 1-78.
  19. Song, B.K., and Kim, H.S. (2001). "Understanding of Cm at Risk and Major Implication." Construction Trend Briefing, 2001, pp. 2-15.
  20. Yoo, S.K., Choi, S.I., and Son, C.B. (2009). "An Analysis of Capability of CM at Risk in Major Construction Company." Korean Journal of Construction Engineering and Management, KICEM, 10(5), pp. 85-94.
  21. AGC of America (2011). Recommended Best Practices for the Use of Construction Management/General Contractor on Highway and Transportation Projects in the Public Sector, 1-5, Retrieved July 24, 2018 from .