Construction Process Modelling Method Improving the Traceability of ICT Applications

ICT 적용 추적성 개선을 위한 시공관리 프로세스 모델링

  • Go, Taeyong (Intelligent Construction Automation Center, Kyungpook National University) ;
  • Lim, Taekyung (Intelligent Construction Automation Center, Kyungpook National University) ;
  • Lee, Dong-Eun (Sch. of Arch & Civil Engrg, Kyungpook National University)
  • 고태용 (경북대학교 지능형건설자동화연구센터) ;
  • 임태경 (경북대학교 지능형건설자동화연구센터) ;
  • 이동은
  • Received : 2018.10.08
  • Accepted : 2018.10.19
  • Published : 2019.01.31

Abstract

Tracking ICT applications on construction business processes is critical to the success of ICT-applied construction projects. Existing IDEF0 is a representative modeling method for visualizing and analyzing business processes. It defines a construction production process into a visual information model, hence, encouraging the project participant to understand the activities, their deliverable, and control flow of the process. However, IDEF0 dose not lend itself to ICT-applied construction processes, because it does not provide a mean to define how, in what order, by which each and every activity that ICT applied implements. This paper presents a new business modeling method that improves the traceability of ICT application (IAMB: ICT Application tracking Model for Business process) for construction management. The IAMB contributes to handle the sophisticated features of construction management processes to which ICT are applied. The method categorizes the process into three types: management, construction, and information exchange. The validity of IAMB was confirmed by analyzing the performance when it is used for tracking each modeling step of lift reservation process which making use of ICT. The test case provides an admissible evidence that the method encourage to define who, what, how, which order, and by which ICT tools the construction process exchanges production information.

ICT를 적용한 건설 프로젝트의 성공적 수행을 위해서는 건설 생산 프로세스를 시각정보모델로 정의하여 프로젝트 참여자들이 해당 프로세스 상에서 ICT가 담당(혹은 실행)하는 작업의 내용 및 절차를 이해할 수 있어야한다. 기존 IDEF0은 비즈니스 프로세스, 정보 시스템 등을 시각화 및 분석하는 대표적 모델링 방법이다. 반면, 조직(혹은 기업)이 수행하는 작업들에 대해서만 표현할 뿐 프로세스 상의 ICT가 적용되는 작업들 간의 순서, 정보전달 및 실행 방법에 대한 구체적 설계기법을 제공하지 않는다. 본 연구는 ICT 적용 추적가능성을 향상시킨 업무 모델링(IAMB) 기법을 개발하여, 업무프로세스에 적용되는 ICT의 특징을 명확하게 인식 및 정의할 수 있는 체제를 제공한다. IAMB 모델은 관리, 시공, 정보 등 3개 부분으로 구분되며, 육하원칙에 의거 누가, 언제, 어떤 ICT기법을 적용하여, 어떤 순서로 프로세스 정보를 처리하는지 규명하게 한다.

Keywords

GGRHC4_2019_v20n1_114_f0001.png 이미지

Fig. 1. Study flow diagram

GGRHC4_2019_v20n1_114_f0002.png 이미지

Fig. 2. The IDEF0 modeling component

GGRHC4_2019_v20n1_114_f0003.png 이미지

Fig. 3. Top-down function decomposition using IDEF0 model

GGRHC4_2019_v20n1_114_f0004.png 이미지

Fig. 4. The IAMB modeling component and definitions in process layers

GGRHC4_2019_v20n1_114_f0005.png 이미지

Fig. 5. Business processes for lift reservation and performance management using IDEF0 and IAMB modeling methods

Table 1. Case studies of ICT application for Construction Process

GGRHC4_2019_v20n1_114_t0001.png 이미지

References

  1. Choi, Y. G., Yoon, S. W., and Chin, S. Y. (2011). "Integrated Manpower Information Systems on Construction Site - Using RFID and QR-Code." Korean Journal of Construction Engineering and Management, KICEM, 12(4), pp. 106-116. https://doi.org/10.6106/KJCEM.2011.12.4.106
  2. Go, T. Y., and Yashiro, T. (2011). "A study on understanding the impact by introduction the information technology tools." Summaries of technical papers of Annual Meeting AIJ, AIJ, pp. 1301-1302.
  3. Go, T. Y. (2015). "Study on evaluation of IT application impact in construction management / implementation process." Thesis of doctoral, University of Tokyo.
  4. Hamada, K., Suzuki, M., Kaneko, T., Omoto, E., Doi, S., Takizawa, H., and Kashiwa, T. (2013). "Rationalization of Logistics for Super High-rise Building : Outline of Project and Control System for Construction Elevator." Summaries of technical papers of annual meeting 2013, AIJ, pp. 1281-1282.
  5. Jo, J. H., and Kwak, M. S. (2008). "Development of the Field Management System By Using PDA In Apartment Construction." Review of Architecture and Building Science, AIK, 52(5), pp. 83-86.
  6. Jung, S. W., Woo, H. S., Yoon, S. H., Moon, H. C., and Kim, C. H. (1998). "A Study on Dynamic IDEF0 Methodology." Proceeding of KIOIE 1998 Spring Conference, KIOIE, pp. 614-618.
  7. Kanba, K., and Watanabe, K. (2009). "Development of Collision Prevention System (Alarm System) of Crawler Crane Using GPS." Construction machinery and equipment, 45(9), pp. 33-35.
  8. Kazuki, H., Handa, M., Mizukami, O., and Nakashima, T. (2006). "Development of Building Site System of Administration with Personal Digital Assistants : Development of Reinforcement Quality Inspection System." Summaries of technical papers of annual meeting 2013, AIJ, pp. 827-828.
  9. Kim, J. I. (1996). "IDEF0 Models of the FCIM system for CALS Implementation." The Jounal of Society for e-Business Studies, Society for e-Business Studies, 1(2), pp. 117-131.
  10. Kim, J. S., Chin, S. Y., and Yoon, S. W. (2014). "A Study on the Applicability of Character Recognition Technology for Construction Supply Chain Management of Structural Steel Components and Precast Concrete Works." Korean Journal of Construction Engineering and Management, KICEM, 15(4), pp. 20-29. https://doi.org/10.6106/KJCEM.2014.15.4.020
  11. Lee, H. S., Lee, K. P., Park, M. S., Kim, H. S., and Lee, S. B. (2009). "A Construction safety management system based on Building Information Modeling and Real-time Locating System." Korean Journal of Construction Engineering and Management, KICEM, 10(6), pp. 135-145.
  12. Lee, S. H., and Ryu, K. Y. (2009). "c-IDEF*:A comprehensive modeling methodology for collaborative processes of manufactures" Proceeding of KORMS 2009 Fall Conference, KORMS, pp. 1441-1448.
  13. Oh, S. W., Kim, Y. S., Lee, J. B., and Kim, H. S. (2004). "Collection and Utilization of the Construction Labor Information Using PDA and Barcode." Korean Journal of Construction Engineering and Management, KICEM, 5(5), pp. 65-75.
  14. Ross, D. T. (1977). "Structured Analysis(SA):A Language for Communicating Ideas," IEEE Transactions on Software Engineering, 3(1), pp 16-34. https://doi.org/10.1109/TSE.1977.229900
  15. Yim, D. S., Kim, C. H., Woo, H. S., and Kim, J. I. (1998). "Integration od Business Process Modeling Methodologies : IDEF0, IDEF3, and Petri Net." The Jounal of Society for e-Business Studies, Society for e-Business Studies, 3(2), pp. 141-160.
  16. Yoon, S. W., Song, J. H., Shin, T. H., and Chin, S. Y. (2010). "A Gate Sensor for Effective and Efficient Entering / Taking Management of Vehicles for Construction Logistics." Korean Journal of Construction Engineering and Management, KICEM, 12(1), pp. 85-96. https://doi.org/10.6106/KJCEM.2011.12.1.85