A Study on the Prediction of the Construction Cost in Planning Stage of Local Housing Union Project

지역주택조합사업 기획단계의 공사비 예측에 관한 연구

  • Lee, Jin-Kyu (Department of Civil and Environmental Engineering, Graduate School, Daejin University)
  • 이진규 (대진대학교 대학원 토목환경공학과)
  • Received : 2018.09.14
  • Accepted : 2018.12.07
  • Published : 2018.12.31

Abstract

The accurate prediction of construction cost is a key factor in a project's success. However, it is hard to predict the construction costs in the planning stages rapidly and precisely when drawings, specifications, construction cost calculation statements are incomplete, among other factors. Accurate construction-cost prediction in the planning stage of a project is also important for project feasibility studies and successful completion. Therefore, various techniques have been applied to accurately predict construction costs at an early stage when project information is limited. There are many factors that affect the construction cost prediction. This paper presents a construction-cost prediction method as multiple regression model with seven construction factors as independent variables. The method was used to predict the construction cost of a local housing union project, and the error rate was 4.87%. It is not possible to compare the cost of the project at the planning stage of the local housing union project, but it has high prediction accuracy compared to the unit price of an existing unit area. It is likely to be applied in construction-cost calculation work and to contribute to the establishment of the budget for the local housing union project.

공사비의 정확한 예측은 프로젝트 성공의 핵심 요소이다. 그러나 도면, 시방서, 공사비 산출내역서 등이 아직 불완전한 기획단계의 경우 신속하고 정확하게 공사비를 산출하기가 용이하지 않다. 또한 프로젝트의 기획단계에서 정확한 공사비 예측은 프로젝트의 타당성 조사 및 성공적인 완료에 중요하다. 따라서 프로젝트 정보가 제한적 일 때 사업 초기에 공사비를 정확하게 예측하기 위해 다양한 기법(회귀분석, 인공신경망, 사례기반추론, 유전자알고리즘, 몬테카를로시뮬레이션, 빌딩정보모델링)이 적용되고 있다. 공사비 예측에 영향을 미치는 많은 요소가 있다. 본 논문에서는 7개(대지면적, 연면적, 지하층수, 지상층수, 주동수, 전체세대수, 공사기간)의 건축개요를 독립변수로 사용하는 다중회귀모델(후진제거법)로 공사비 예측치를 제시한다. 다중회귀모델을 이용한 지역주택조합사업 공사비의 예측 결과 오차율은 4.87%로 나타났다. 이는 지역주택조합사업의 기획단계에서 공사비 예측에 관한 연구가 없어 비교가 불가능하나, 기존에 사용하던 단위면적에 대한 단가산정방식에 비하여 높은 예측 정확도를 가짐으로써, 향후 지역주택조합사업의 기획단계에서 공사비 산출업무에 적용 가능성이 높고, 지역주택조합사업의 사업예산 수립에 기여할 수 있을 것으로 판단된다.

Keywords

Table 1. Fluctuation of construction cost index(Housing)

SHGSCZ_2018_v19n12_653_t0001.png 이미지

Table 2. Literature review

SHGSCZ_2018_v19n12_653_t0002.png 이미지

Table 3. Analysis of location and cases

SHGSCZ_2018_v19n12_653_t0003.png 이미지

Table 4. The configuration of variables

SHGSCZ_2018_v19n12_653_t0004.png 이미지

Table 5. Statistics of variables

SHGSCZ_2018_v19n12_653_t0005.png 이미지

Table 6. The result of pearson correlation analysis

SHGSCZ_2018_v19n12_653_t0006.png 이미지

Table 7. Results of regression analysis

SHGSCZ_2018_v19n12_653_t0007.png 이미지

Table 8. Verification results of regression model

SHGSCZ_2018_v19n12_653_t0008.png 이미지

References

  1. Korea ON-line e-Procurement System, Available From: http://www.g2b.go.kr (accessed July., 11, 2018)
  2. Korea Institute of Civil Engineering and Building Technology, Fluctuation of construction cost index (Housing), Available From: http://cost.kict.re.kr/gnu/ (accessed July., 11, 2018)
  3. S. H. Ji, M. S. Park, H. S. Lee, K. H. Seong, Y. S. Yoon, "Method of Quantity Data Analysis for Building Construction Cost Estimation", Korean Journal of Construction Engineering and Management, vol.9, no.6, pp. 235-243, 2008.
  4. M. S. Park, K. H. Seong, H. S. Lee, S. H. Ji, S. Y. Kim, "Schematic Cost Estimation Method using Case-Based Reasoning", Korean Journal of Construction Engineering and Management, vol.11, no.4, pp. 22-31, 2010. https://doi.org/10.6106/KJCEM.2010.11.4.22
  5. J. H. Kim, "Stochastic Hybrid Cost Prediction Model of Construction Project in Early Stage", Graduate School University of Seoul, Master's Thesis, 2014.
  6. N. Jun, J. U. Choi, H. M. Choi, J. H. Kim, "A Study on Estimating Construction Cost of Apartment Housing Projects Using Genetic Algorithm-Support Vector Regression", Korean Journal of Construction Engineering and Management, vol.15, no.4, pp. 68-76, 2014. DOI: http://doi.org/10.6106/KJCEM.2014.15.4.068
  7. J. H. Yim, J. M. Park, O. K. Kim, "Cost Estimating Method of Public Building Construction through Construction Scale", Journal of the Korea Institute of Building Construction, vol.15, no.3, pp. 307-316, 2015. DOI: http://doi.org/10.5345/JKIBC.2015.15.3.307
  8. C. T. Hyun, G. H. Go, J. Zhengxun, "Probabilistic Earlier GMP Calculation Method for Apartment Using CM at Risk", Journal of the Korea Institute of Building Construction, vol.18, no.3, pp. 295-303, 2018. DOI: http://doi.org/10.5345/JKIBC.2018.18.3.295
  9. K. S. Ha, J. K. Lee, "A Study on the Prediction of Civil Construction Cost on Apartment Housing Projects at the Early Stage", Journal of the Korea Academia-Industrial cooperation Society, vol.13, no.9, pp. 4286, 2012. DOI: http://doi.org/10.5762/KAIS.2012.13.9.4284
  10. S. M. Ji, C. T. Hyun, H. S. Moon, "Cost Prediction Model using Qualitative Variables focused on Planning Phase for Public Multi-Housing Projects", Korean Journal of Construction Engineering and Management, Vol.13, No.2, pp. 97, 2012.