Identifying Construction Engineering Tasks at the Design Phase for Enhancing Constructability in High-rise Building Construction - Focused on Temporary Work -

고층 건축공사의 시공성 향상을 위한 설계단계의 시공엔지니어링 업무 도출 - 가설공사를 중심으로 -

  • Received : 2017.08.23
  • Accepted : 2017.09.12
  • Published : 2017.10.20

Abstract

Due to the increase in the size of buildings and scale, the importance of construction engineering that reflects the constructability from the design stage of the project is increasing. Especially, engineering efforts related to facilities, equipment and construction methods for temporary work at the design stage can significantly contribute to improvement of constructability and project performance. The purpose of this study is to derive construction engineering tasks on temporary work at the design phase of the high-rise building projects. 27 preliminary tasks were firstly investigated through literature review and experts' group interview, and the necessity and importance analysis of each tasks were then performed based on questionnaire survey. Most of the tasks related to plans on structural framework and lifting equipment were analyzed as relatively more important ones. Lastly, 21 engineering tasks, which are classified into 5 factors, were proposed through factor analysis. The factors were determined as 1) structural framework, measurement and circulation, 2) lifting equipment and pumping, 3) space zoning, 4) water supply, 5) temporary facility, electric power supply and lighting. The results of this study can be used as basic data for establishing efficient work process of construction engineering on temporary work at the design phase.

건물의 고층화와 규모의 증가로 인해 프로젝트 설계단계에서의 시공성을 반영한 엔지니어링 기술의 중요성이 점점 커지고 있다. 특히, 설계단계에서의 가설작업을 위한 설비, 장비 및 공법과 관련된 엔지니어링 기술적용의 노력은 시공성 및 프로젝트 성과 향상에 크게 기여할 수 있다. 이에 본 연구에서는 고층 건축공사의 시공성 향상을 위하여 가설공사를 중심으로 설계단계에 요구되는 시공엔지니어링 업무를 도출하고자 하였다. 우선, 문헌고찰과 전문가 집단면접을 통해 27개의 예비 업무를 도출하였으며, 그 후 설문조사를 통하여 각 업무의 필요성 및 중요도를 분석하였다. 분석 결과, 골조공사 및 양중장비 계획과 관련된 대부분의 업무가 상대적으로 중요한 것으로 분석되었다. 마지막으로 요인분석을 통해 21개의 엔지니어링 업무를 선정하였으며, 이들 업무는 크게 1)골조공사 및 측량/동선계획, 2)양중 및 콘크리트 압송계획, 3)공간구획계획, 4)용수계획, 5)가설건물 및 전력/조명계획의 5개 요인으로 분류되었다. 본 연구의 결과는 설계단계에서 시공엔지니어링 업무를 효과적으로 반영할 수 있는 프로세스 수립을 위한 기초 자료로 활용될 수 있을 것이다.

Keywords

References

  1. Kim MH. Management and organization of the building construction. Seoul(Korea): Kimoondang; 2006. 425 p. Korean.
  2. Pulaski MH, Horman MJ. Organizing constructability knowledge for design. Journal of Construction Engineering and Management. 2005 Aug;131(8):911-9. https://doi.org/10.1061/(ASCE)0733-9364(2005)131:8(911)
  3. Arditi D, Elhassan A, Toklu YC. Constructability analysis in the design firm. Journal of Construction Engineering and Management. 2002 Apr;128(2):117-26. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:2(117)
  4. Peurifoy RL, Oberlender GD. Formwork for Concrete Structures. 4th ed. United Stated of America: McGraw-Hill; 2011. p. 35-132.
  5. Fischer M, Tatum CB. Characteristic of design-relevant constructability knowledge. Journal of Construction Engineering and Management. 1997 Sep;123(3):253-60. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(253)
  6. Othman AAE. Improving building performance through Integrating constructability in the design process. Organization, Technology and Management in Construction. 2011 Feb;3(2):333-47.
  7. Lam PTI, Wong FWH, Chan APC. Contributions of designers to improving buildability and constructability. Design Studies. 2006 Jul;27(4):457-79. https://doi.org/10.1016/j.destud.2005.10.003
  8. Fisher DJ, Anderson SD, Rahman SP. Integration constructability tools into constructability review process. Journal of Construction Engineering and Management. 2000 Mar/Apr;126(2):89-96. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:2(89)
  9. Oh JW, Song KR, Ahn YS. A study on the application of constructability in construction project process. Journal of The Architectural Institute of Korea Structure & Construction. 2002 Dec;18(12):157-64.
  10. Park M, Ham Y, Lee HS, Kim WY. Development of design process management model using dependency structure matrix for constructability. Korean Journal of Construction Engineering and Management. 2010 Sep;11(5):65-74. https://doi.org/10.6106/KJCEM.2010.11.5.65
  11. Yoon H, Kim YS. Analysis of constructability factors affecting on the productivity of tall building construction : with focus on the area of steel work. Korean Journal of Construction Engineering and management. 2014 Jul;15(4):30-8. https://doi.org/10.6106/KJCEM.2014.15.4.030
  12. Kim DS, Choi HM, Kim JH. A proposal BIM work process to support construct-ability analysis from practitioners viewpoint. Journal of The Korea Institute of Building Construction. 2014 Oct;14(6):561-9. https://doi.org/10.5345/JKIBC.2014.14.6.561
  13. Park JS, Hyun CT, Hong TH, Park SH, Moon HS. Development of checklist for improving constructability in steel structure construction. Journal of The Architectural Institute of Korea Structure & Construction. 2009 Dec;25(12):197-206.
  14. Jang JS, Park SH, Lee DH, Song SH, Choi MS, Lee JK. Method of construction stability for the curved concrete pylon of cable stayed bridge by the construction engineering. Proceeding of the Korea Concrete Institute Conference; 2016 May 11; Yeosu, Korea. Seoul (Korea): Korea Concrete Institute; 2016. p. 691-2.
  15. Son Y, Hong HS, Paik H, Cho N. Construction engineering of the 3rd bosphorus bridge. Journal of The Korean Society of Civil Engineering. 2016 Oct;64(10):74-8.
  16. Kim SI, Lee GJ, Yang GJ, Kim KS. Review on the behavior and construction method changing of steel composite stayed-cable bridge by the construction engineering. Korea Society of Steel Construction article. 2009 Sep;21(5):35-43.
  17. Shon YJ, Jang KS. Understanding temporary work engineering. The Korean Structure Engineers Association. 2008 Sep;15(3):80-5.
  18. Lee JW, Cho K, Kim T. Basic research on applying temporary work engineering at the design phase. International Journal of Civil, Environmental, Structural, Construction and Architectural Engineering. 2017 Feb;11(2):214-7.
  19. Lee JS, Kwon W, Chun JY. Web-based knowledge database of temporary facility site-layout planning for high-rise buildings. Proceeding of the Architectural Institute of Korea Conference; 2003 Apr 12; Samcheok, Korea. Seoul (Korea): Architectural Institute of Korea; 2003. p. 427-30.
  20. Ahn BJ, Kim JJ, Kim K, Kim SG. A study on the optimization of site layout in the high-rise building construction. Journal of The Architectural Institute of Korea Structure & Construction. 1999 Dec; 15(12):107-18.
  21. Kim T. Advanced system formwork and construction planning model for tall building construction [dissertation]. [Seoul (Korea)]: Korea University; 2013. 1-3 p.
  22. Jung YC. Lee BY, Kim GH. Application possibility of folding pre-fabricated rebar cage in domestic construction fields. Journal of the Korea Institute of Building Construction. 2010 Apr;10(2):125-32. https://doi.org/10.5345/JKIC.2010.10.2.125
  23. Kim MS. A study on the planning for construction of high-rise building project [dissertation]. [Busan (Korea)]: Pukyong National University; 2010. 70 p.
  24. Ahn BJ. A decision-making model of integrated vertical and horizontal move plan for finishing material in tall building construction [dissertation]. [Seoul (Korea)]: Hanyang University; 2004. 190 p.
  25. Park MS, Ha SB, Lee HS, Kim SY. An optimization model of temporary lift’s vertical zoning for worker lifting operation in the high-rise building construction. Journal of The Architectural Institute of Korea Structure & Construction. 2011 Nov;27(11):193-202.
  26. Ahn BJ, Kim JJ, Jee N. Planning an optimized horizontal move for finishing material in high-rise building construction. Journal of The Architectural Institute of Korea Structure & Construction. 2001 Aug;17(8):119-30.
  27. Lim YJ, Yun JI, Joung EI, Lee SJ. A study on the emergency exitways in super high-rise buildings. Proceeding of the Architectural Institute of Korea Conference; 2007 Oct 26; Chungju, Korea. Seoul (Korea): Architectural Institute of Korea; 2007. p. 355-8.
  28. Choi GL, Kang SJ. Disaster prevention plan during the construction of super high-rise buildings. Journal of the Korea Institute of Building Construction. 2003 Jun;3(2):50-5. https://doi.org/10.5345/JKIC.2003.3.2.050
  29. Sho KH, Jung DW, Yang KY. A study on the survey method for compensation of column shortening in high-rise building construction. Journal of The Architectural Institute of Korea (Structure & Construction section). 2003 May;19(5):169-76.
  30. Lee JH. A study on the design of heating and cooling system in super high-rise building [dissertation]. [Seoul (Korea)]: Chung-Ang University; 2013. 69 p.
  31. Cho JK, Jeong CS, Kim BS. The energy conservational HVAC system design approaches of the large-scale buildings. Journal of The Architectural Institute of Korea (Planning & Design section). 2008 Jun;24(6):347-54.
  32. Cho CS. Water supply system planning of high-rise building. Korean Association of Air Conditioning Refrigerating and Sanitary Engineers. 2005 Jan; 22(1):36-41.
  33. Chun BJ. A study on development of fire protection system in super high rise building [dissertation]. [Suwon (Korea)]: Kyonggi University; 2009. 58 p.
  34. Kim WP. Basic Statical Analysis. Seoul(Korea): WiseIN Company; 2017. 328-74 p.
  35. Chen Y, Okudan GE, Riley DR. Sustainable performance criteria for construction method selection in soncrete buildings. Automation in Construction. 2010 Mar;19(2):235-44. https://doi.org/10.1016/j.autcon.2009.10.004
  36. Lee HS, Lim JH. Statistical package for the social sciences SPSS 12.0 manual. Paju(Korea): Bobmunsa; 2005. Chapter 14, Factor analysis; p.338-64
  37. Song JH. SPSS/AMOS Statistic analysis method. 2nd ed. Paju(Korea): 21CBOOK; c2013. Chapter 7, Factor analysis; p.61-114.
  38. Jung CY, Kim JJ, Jung YG. Recycling factor analysis on wood wastes in the construction site by classification origination reason. Korean Journal of Construction Engineering and management. 2007 Feb;8(1):107-15.