DOI QR코드

DOI QR Code

건설 현장 강행공사 방지가 인적사고에 미치는 영향에 관한 연구

A study on effects of the prevention of rush work of construction sites on human accidents

  • 이성일 (명지대학교 산업경영공학과) ;
  • 강경식 (명지대학교 산업경영공학과)
  • Lee, Sung-Il (Department of Industrial Management Engineering, MYONGJI University) ;
  • Kang, Kyung-Sik (Department of Industrial Management Engineering, MYONGJI University)
  • 투고 : 2016.12.24
  • 심사 : 2017.02.02
  • 발행 : 2017.03.31

초록

In the construction sites, rush (speedy construction) work have recently been overused because of budget reductions by reducing the construction duration after the long-term economic recession and construction business stagnation with institutional change including the instruction of the duration shortening bidding system and the introduction of the post-construction sales system by the Korea Research Institute for Human Settlements. Due to this, negligent accidents have frequently occurred by forcing manpower, equipment, finance, and material procurement and pressing ahead with impractical construction wok at night according to the reduction of construction schedules. Therefore, this paper has the necessity of this study to seek for alternatives to prevent negligent accidents by finding factors related to rush work in the reality that the importance for preventing negligent accidents is more emphasized while they have not been reduced in construction sites.

키워드

참고문헌

  1. Kang, Seong-o (2007), "A Study on the process analysis and setting up normal duration of Large scale military modular building", Doctor's thesis, Mokwon University.
  2. Gwak, Jin-yeol(2011), "Developing a Time-Cost Estimation Model for Evaluating Construction Alternatives of Structural Works in Housing", Doctor's thesis, Ajou University.
  3. Korea Research Institute for Human Settlements(2012), "Introduction of the post-construction sales system".
  4. Park, Geun-se (2012), "A Study on the estimation of an Approproate Construction Duration of Apartment", Master's thesis, Seoul National University of Science and Technology.
  5. Yoon, Yeong-ho et al.(2010), "A study on the feasibility of apartment remodeling household expansion", Ministry of Land, Infrastructure and Transport.
  6. Cho, Gwang-chan (2012), "Development of the Half-Ship Towing Building Method for Reducing Construction Period", Master's thesis, Changwon National University.
  7. Choi, Do-seung(2009), "A Decision Making Framework for Reducing Project Duration By Applying Concurrent Engineering in Construction", Doctor's thesis, Dongguk University.
  8. Choi, Min-ji, Lee, Dong-cheol, and Ha, Du-ri(2011), "A Study on Ways to Improve Construction Safety Management for a Safer Society", Korea Research Institute for Human Settlements, 12.
  9. Han, Jong-gwan, Kim, Cheol, Joo, Hoon (2003), "Analysis on Delay factors of Major Trades in Apartment Housing Projects, Architectural Institute of Korea", 2(-).
  10. D Fang, Y Chen, L Wong(2006), "Safety climate in construction industry: a case study in Hong Kong", Journal of construction engineering, ascelibrary.org.
  11. EC Lim, J Alum(1995), "Construction productivity: issues encountered by contractors in Singapore", International Journal of Project Management, No. 6.
  12. JP Zhang, ZZ Hu(2011), "BIM-and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies", Automation in construction, No.5.
  13. N Kaldor(1940), "A model of the trade cycle", The Economic Journal, No. 4
  14. O Abudayyeh, TK Fredericks, SE Butt(2006), "An investigation of management's commitment to construction safety", International Journal, No. 7.
  15. P Kines, LPS Andersen, S Spangenberg(2010), "Improving construction site safety through leader-based verbal safety communication", Journal of Safet